title: "AEP counts 84 GW of contracted data-center load; 46 GW of it, in Texas, cannot yet energize"
description: "AEP sells investors 84 GW of contracted demand and a $100.4 billion buildout, but half of that load is Texas letters of agreement that obligate no one to buy power, and ERCOT has paused the process that could approve any of it. The stock, at 20.9 times earnings, prices the full headline."
publisher: "The Inference"
section: "Power"
published: 2026-11-16T16:20:30.491Z
modified: 2026-11-16T16:20:30.491Z
canonical: https://theinference.org/article/aep-counts-84-gw-of-contracted-data-center-load-46-gw-of-it-in-texas-cannot-yet-energize
language: en
keywords: "AEP, Data Centers, Texas, ERCOT, Utilities"
---

# AEP counts 84 GW of contracted data-center load; 46 GW of it, in Texas, cannot yet energize

> AEP sells investors 84 GW of contracted demand and a $100.4 billion buildout, but half of that load is Texas letters of agreement that obligate no one to buy power, and ERCOT has paused the process that could approve any of it. The stock, at 20.9 times earnings, prices the full headline.

The press release says 84 gigawatts of "contracted" load by 2031 [1]. The filing says none of the Texas half of it can switch on yet. On [the October 28 call](https://electroneconomics.substack.com/p/aep-holds-us2-billion-of-texas-collateral), [American Electric Power](https://theinference.org/markets/companies/american-electric-power) chief executive Bill Fehrman reported collecting "over $2 billion of cash or collateral just for Texas" from data-center developers [1]. The money is real. What it buys is not a contract.

## The split the release does not make

Chief financial officer Trevor Mihalik supplied it when he spoke: 35 GW of the 84 sits under firm take-or-pay electric service agreements in PJM and SPP, grids where customers pay for reserved capacity [1]. All 46 GW of Texas, 55 percent of the headline, is backed only by letters of agreement under state law SB6, commitments to pursue service that obligate no one to buy a kilowatt [1]. In April, a [Jefferies](https://theinference.org/markets/companies/jefferies) analysis counted 36 GW of AEP's then-56 GW Texas book under letters of intent; the number has grown since, the instrument has not [1].

*Chart: **AEP's letter-backed Texas load has climbed from 36 GW to 46 GW since April** A line chart of the gigawatts of AEP Texas load counted as contracted but backed only by letters of agreement rather than supply contracts: 36 GW in April 2026 per a Jefferies analysis, 40 GW in the prior quarter per AEP's filing, and 46 GW on the October 28 call.*

*Gigawatts of AEP's Texas load that the company counts as contracted but that is backed only by letters of agreement under state law SB6: 36 GW from a Jefferies analysis in April 2026, 40 GW in the company's second-quarter filing, and 46 GW on the October 28 earnings call. Source: Electron Economics. [1]*

## A deposit you can mostly get back

The 10-Q behind the call carries a quieter sentence: ERCOT "has currently paused Batch Zero classification and study activity" and "will not authorize large loads to energize until verification is complete" [1]. About $1.2 billion of the $2 billion sits in a segregated cash account, roughly $44 per kilowatt across 45 GW, below the $50,000/MW the Texas commission's September rule sets [1]. The refund terms let a developer recover most of it, in full if ERCOT allocates zero [1].

## The dollars have not followed the gigawatts

AEP raised its [2027 to 2031 capital plan](https://thefinance.co.kr/en/utilities/story/2026/11/n-2963) to $100.4 billion, rate base to $162 billion by 2031 [2] ([The Inference covered the raise itself on October 29](https://theinference.org/article/american-electric-power-added-22-billion-of-spending-and-5-2-billion-of-stock-cfo-won-t-promise-24-again)). But Texas takes $17 billion of it, mostly reliability work; broader Texas load wiring sits "not in the plan," as upside [1]. ERCOT is 55 percent of claimed gigawatts and 17 percent of the dollars [1]. Next door, Oncor holds about $6 billion of similar collateral and books it as upside, never as contracted [1][3].

*Chart: **AEP's capital spending jumped 48% in 2025 and now runs well ahead of its operating cash** A column chart comparing AEP's capital spending and operating cash flow each year from 2020 to 2025: capital spending rose from $6.2 billion to $11.9 billion while operating cash flow went from $3.8 billion to $6.9 billion.*

*Capital spending and cash from operations, US dollars in billions, fiscal years ended December 31, from AEP's annual SEC filings. The 2027 to 2031 capital plan of $100.4 billion is a forecast and is not shown. Source: AEP filings. [4]*

## December is when 46 GW gets tested

The stock, at 20.9 times earnings after an 84.9 percent three-year run [2], prices all 84 GW. ERCOT files its verification report on December 10 and the commission meets December 17; ERCOT's own general counsel says the study will not be done by April 9, 2027 [1]. If verification trims the queue, the contracted-load number investors quote falls first. The $2 billion measures intent [1]. The wires, not yet.

## Takeaway

Half of AEP's headline 84 GW of contracted data-center load is Texas letters of agreement that obligate no one to buy power, and ERCOT has paused the study that would let any of it energize.

## Sources

1. [Electron Economics, AEP holds US$2 billion of Texas collateral and no date for the wires, 16 November 2026](https://electroneconomics.substack.com/p/aep-holds-us2-billion-of-texas-collateral)
2. [The Finance Journal, American Electric Power Raises Capital Plan to $100.4B to Meet Rising Grid Demand, 14 November 2026](https://thefinance.co.kr/en/utilities/story/2026/11/n-2963)
3. [Dallas Express via Yahoo Finance, Oncor Eyes Bigger Texas Grid Buildout As Data Center Requests Raise Cost Questions, 8 November 2026](https://finance.yahoo.com/energy/articles/oncor-eyes-bigger-texas-grid-170015265.html)
4. [American Electric Power, annual figures from its SEC filings, retrieved 16 November 2026](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0000004904)


---

AEP counts 84 GW of contracted data-center load; 46 GW of it, in Texas, cannot yet energize — The Inference. Canonical: https://theinference.org/article/aep-counts-84-gw-of-contracted-data-center-load-46-gw-of-it-in-texas-cannot-yet-energize