title: "AI buyers have locked W3.6tr of 2027 parts from Samsung Electro-Mechanics"
description: "Five long-term supply agreements in five months have reserved about W3.6 trillion of AI components for 2027-28 delivery, against W6.78 trillion of capacity spending now underway. The customers are buying certainty; the shareholders are carrying the build."
publisher: "The Inference"
section: "Chips"
published: 2026-10-03T07:20:52.556Z
modified: 2026-10-03T07:20:52.556Z
canonical: https://theinference.org/article/ai-buyers-have-locked-w3-6tr-of-2027-parts-from-samsung-electro-mechanics
language: en
keywords: "Samsung, MLCC, AI Servers, Supply Chain, Capex"
---

# AI buyers have locked W3.6tr of 2027 parts from Samsung Electro-Mechanics

> Five long-term supply agreements in five months have reserved about W3.6 trillion of AI components for 2027-28 delivery, against W6.78 trillion of capacity spending now underway. The customers are buying certainty; the shareholders are carrying the build.

## The fifth deal tips the total past W3.6tr

[A deal disclosed this week](https://www.koreaittimes.com/news/articleView.html?idxno=157627) made it five: an unnamed global buyer agreed to take about W290bn of multilayer ceramic capacitors and inductors from [Samsung Electro-Mechanics](https://theinference.org/markets/companies/samsung-electro-mechanics), delivered across 2027 [1][2]. Together, this year's five disclosed long-term supply agreements cover roughly W3.6tr ($2.6bn) of AI components, nearly all of it for servers that will be built in 2027 and 2028 [1][2].

## Four months of contracts, every window opening in 2027

The run, in order: W1.56tr of silicon capacitors in May for 2027-28 delivery; W454bn of AI-server MLCCs in June; W295bn in July; W1.07tr on 1 September, [the largest MLCC contract in company history](https://biz.heraldcorp.com/article/10858377), covering all of calendar 2027; and this week's W290bn [1][3][4]. The disclosed figures sum to about W3.67tr, against the W3.6tr the company rounds to [1][2].

*Chart: **Five deals in five months reserved W3.67tr of 2027-28 supply** Bars of the five disclosed long-term supply agreements Samsung Electro-Mechanics signed in 2026, from W1.56tr in May to W290bn in late September*

*Disclosed long-term supply agreements by announcement date, trillions of won. Outlets round the cumulative total to about W3.6tr. Figures from The Investor (2 October 2026), Herald Business (1 September 2026), Korea Herald (3 August 2026) and Korea IT Times (29 September 2026). [1][2][3][4]*

## What the buyers reserve is a place in the queue

Scale explains the rush: [Nvidia](https://theinference.org/markets/companies/nvidia)'s coming Vera Rubin platform is expected to carry about 800,000 MLCCs per system, its Feynman successor about a million [4]. Every delivery window disclosed so far opens in 2027 or later [1][2][3].

Hana Securities analyst Kim Min-kyung puts FC-BGA substrate lead times at 48 to 56 weeks against a normal 12, and says AI server buyers carry high price tolerance into talks [1]. The company raised MLCC prices 30 percent in August with lines near full capacity, and long-term MLCC agreements now cover more than 10 global customers [3][4][5].

The Inference [traced the demand squeeze](https://theinference.org/article/ai-racks-need-600-000-capacitors-each-so-samsung-electro-mechanics-is-rationing-its-phone-book) on 28 September, when AI racks needing 600,000 capacitors each had the supplier rationing its order book.

## W6.78tr of shareholder money rides on 2027

The build costs more than the backlog. On 28 September the board [approved W4.27tr to expand FC-BGA capacity at Sejong](https://biz.heraldcorp.com/article/10886620), its largest single-product investment ever and 43.6 percent of consolidated equity, with spending through May 2028 and first mass production in September 2028 [6][7].

A further W2.51tr goes to substrate equipment in Vietnam, where construction costs sit outside the disclosed figure [8]. Global Big Tech customers are putting up part of the capital for Sejong and guaranteeing future volume, per the filing [6][8].

*Chart: **The build outweighs the backlog: W6.78tr of capex against W3.67tr of orders** Bars comparing W3.67tr of locked-in 2026 supply agreements with W4.27tr of Sejong FC-BGA capex and W2.51tr of Vietnam substrate capex*

*Disclosed 2026 supply agreements versus board-approved capital spending announced 28 September 2026, trillions of won. The Vietnam figure covers equipment only; construction costs are excluded from disclosure. Figures from The Investor, Korea Times, Herald Business and Tech Times. [1][6][7][8]*

The profit case is in the current books: the securities industry expects Component Solutions operating profit of up to W1.3tr this year, more than double 2025's roughly W600bn [5]. If 2027 demand slips, the spend is committed regardless: the program runs to May 2028, and the customer funding covers part of the build, not all of it [6][8].

## Watch the fourth-quarter price settlements

Two readings carry the story: MLCC prices settled in fourth-quarter talks, which Hana expects to beat market expectations [1], and 2027 capital spending, guided to double from W3tr to W6tr [4]. [A sixth contract, near W700bn with a global power and components company, was in final talks in late September](https://www.msn.com/en-xl/news/other/samsung-electro-mechanics-nears-4-trillion-won-in-ai-mlcc-contracts/ar-AA2cAJpd) [5].

The counterparty split is the tradable fact in the run: the supplier holds five contracts of locked volume and the pricing talks, while its customers hold the bill at prices Hana describes as high-tolerance [1]. The counterweights are real: Ajinomoto controls about 95 percent of the build-up film inside every substrate and is weighing a rise of at least 30 percent of its own [8], while Chinese makers take the conventional MLCC ground being ceded [4]. First output from the new Sejong lines is scheduled for September 2028 [6].

## Takeaway

Five long-term contracts have pre-sold about W3.6tr of Samsung Electro-Mechanics components for 2027-28, while the board commits W6.78tr to new capacity. Customers are buying queue position; shareholders are funding a build bigger than the disclosed backlog.

## Sources

1. [The Investor, "Samsung Electro-Mechanics' AI component deals hit W3.6tr as buyers lock in future supply", 2 October 2026](https://www.theinvestor.co.kr/article/10892078)
2. [Korea IT Times, "Samsung Electro-Mechanics Secures $200M AI Server Component Deal", 29 September 2026](https://www.koreaittimes.com/news/articleView.html?idxno=157627)
3. [The Herald Business, "Samsung Electro-Mechanics lands record W1.7tr MLCC deal with global tech giant", 1 September 2026](https://biz.heraldcorp.com/article/10858377)
4. [The Korea Herald, "AI demand lifts MLCC profits, and Chinese rivals", 3 August 2026](https://www.koreaherald.com/article/10829283)
5. [The Chosun Ilbo (via MSN), "Samsung Electro-Mechanics nears 4 trillion won in AI MLCC contracts", 20 September 2026](https://www.msn.com/en-xl/news/other/samsung-electro-mechanics-nears-4-trillion-won-in-ai-mlcc-contracts/ar-AA2cAJpd)
6. [The Korea Times, "Samsung Electro-Mechanics to invest $3.14 bil. for substrate plant in Sejong", 28 September 2026](https://www.koreatimes.co.kr/business/companies/20260928/samsung-electro-mechanics-to-invest-314-bil-for-substrate-plant-in-sejong)
7. [The Herald Business, "Samsung Electro-Mechanics to invest W4.27tr in Sejong package substrate facility", 28 September 2026](https://biz.heraldcorp.com/article/10886620)
8. [Tech Times (via MSN), "Samsung Electro-Mechanics commits $5 billion to AI chip substrates; record bet hits upstream wall", 28 September 2026](https://www.msn.com/en-us/technology/hardware-and-devices/samsung-electro-mechanics-commits-5-billion-to-ai-chip-substrates-record-bet-hits-upstream-wall/ar-AA2d8Ely)


---

AI buyers have locked W3.6tr of 2027 parts from Samsung Electro-Mechanics — The Inference. Canonical: https://theinference.org/article/ai-buyers-have-locked-w3-6tr-of-2027-parts-from-samsung-electro-mechanics