title: "Amazon Bought 20 Years of Nuclear Power the Day PJM's Backstop Auction Failed to Open"
description: "Constellation hit a two-month low on FERC's freeze of PJM's 6,831 MW backstop, then announced a 20-year, 690 MW Amazon contract that funds a $3 billion expansion of Maryland's only nuclear plant. The bilateral market is answering a capacity market that just stalled."
publisher: "The Inference"
section: "Power"
published: 2026-10-01T02:08:57.109Z
modified: 2026-10-01T02:08:57.109Z
canonical: https://theinference.org/article/amazon-bought-20-years-of-nuclear-power-the-day-pjm-s-backstop-auction-failed-to-open
language: en
keywords: "Nuclear, Data Centers, Power Markets, Amazon, Constellation, PJM"
---

# Amazon Bought 20 Years of Nuclear Power the Day PJM's Backstop Auction Failed to Open

> Constellation hit a two-month low on FERC's freeze of PJM's 6,831 MW backstop, then announced a 20-year, 690 MW Amazon contract that funds a $3 billion expansion of Maryland's only nuclear plant. The bilateral market is answering a capacity market that just stalled.

## The selloff reversed at 4 p.m.

[Constellation](https://theinference.org/markets/companies/constellation-energy) fell about 4% on 30 September to its lowest level in more than two months, after the Federal Energy Regulatory Commission suspended PJM's one-time procurement for a 6,831 MW capacity shortfall until 28 February 2027 [1]. At 4 p.m. the company [announced a 20-year agreement](https://finance.yahoo.com/energy/articles/constellation-amazon-announce-20-power-200000338.html) with [Amazon](https://theinference.org/markets/companies/amazon) covering 690 MW at Calvert Cliffs, Maryland's only nuclear plant, including a 190 MW uprate and more than $3 billion of investment across the 1,790 MW site [2]. The stock rose as much as 5% after hours [3].

## The frozen auction was a fight over who pays

The backstop window was to open that same day and run to 21 October, offering contracts of up to 15 years for new generation [4]. FERC accepted the core design but suspended it five months over how costs are divided. [Chairman Laura Swett warned "the region's reliability hangs in the balance"](https://www.reuters.com/business/energy/ferc-asks-grid-operator-pjm-revise-plan-shield-homes-data-center-costs-2026-09-30/); Commissioner Lindsay See wrote that "existing customers should not be left paying costs attributable to new demand" [5]. PJM's previous auction [had already cleared at its $325 per megawatt-day cap, paying generators $16.4 billion](https://oilprice.com/Energy/Energy-General/PJM-Auction-Comes-Up-68-Gigawatts-Short-As-Data-Centers-Devour-Power.html) [6].

## Amazon's first Calvert Cliffs plan died at the ballot box

Amazon once wanted to build on the plant itself: a 2.4 million square foot data center campus, [withdrawn in August after Calvert County voters ousted three commissioners](https://thedailyrecord.com/2026/08/05/amazon-abandons-data-center-plans-calvert-cliffs/) in a June primary dominated by data center anger [7]. The new contract needs no campus. All of Calvert Cliffs' output keeps flowing to the PJM grid [2], and PJM's own filing says bilateral contracts shrink the backstop target [4].

![Aerial view of the Calvert Cliffs Nuclear Power Plant, its two containment domes and switchyard on the shore of the Chesapeake Bay.](https://storage.googleapis.com/theinference-public/img/8b00911e33a90afc.jpg)

*Calvert Cliffs, Maryland's only nuclear plant, a 1,790 MW site on the Chesapeake Bay. Amazon's 20-year contract covers 690 MW there and funds a more than $3 billion expansion, including a 190 MW uprate. (Jbs666 via Wikimedia Commons)*

## The pattern is nine days old

Google [agreed on 21 September to back roughly 96 MW of uprates at the Vogtle and Hatch plants](https://theinference.org/article/google-is-paying-to-stretch-georgia-s-reactors-southern-s-stock-hit-a-52-week-low-anyway) in Georgia, under [a new tariff filed with state regulators](https://www.world-nuclear-news.org/articles/google-agreement-to-support-Georgia-plant-uprates) [8]. Amazon's deal is the second such underwriting, and it sits inside PJM, the market whose collective procurement just stalled.

## Contracted floors, frozen auctions

The stock split marks the divide: Constellation is down 31% this year, [NRG](https://theinference.org/markets/companies/nrg-energy) Energy 42%, Talen about 21% [1]. Constellation now holds a 20-year contracted revenue floor at Calvert Cliffs, plus a path to relicense the plant for 20 more years [2]. NRG and Talen hold what TD Cowen calls "acute" uncertainty [1].

*Chart: **Three merchant power stocks are down 21% to 42% this year, with NRG hit hardest** Bar chart of year-to-date 2026 share declines at three merchant power companies: NRG Energy down 42%, Constellation down 31% and Talen about 21%.*

*Share price change year to date through 30 September 2026, in TD Cowen's 30 September note on the FERC suspension; Talen's figure is approximate. Source: StockTwits via Yahoo Finance. [1]*

The contract's price was not disclosed, and its new megawatts arrive between 2030 and 2032, after the delivery year the frozen backstop was meant to cover [2]. The bilateral route is real; it is also slow and small.

*Chart: **Amazon's bilateral answer is a tenth the size of PJM's frozen gap** Bar chart comparing the frozen PJM backstop gap of 6,831 MW with the 1,790 MW Calvert Cliffs plant, Amazon's 690 MW 20-year contract and the 190 MW uprate.*

*Megawatts of capacity. The PJM bar is the 2028/29 reliability shortfall its suspended backstop procurement was to fill; Calvert Cliffs bars are from the 30 September 2026 announcement. Sources: StockTwits; Constellation press release. [1][2]*

## A revised filing is due by 28 February

PJM says it is incorporating FERC's directives [5]. Watch the refiled backstop terms and the Calvert Cliffs relicensing docket. FERC can suspend a procurement; it cannot suspend a contract.

## Takeaway

FERC froze PJM's 6,831 MW backstop auction until 28 February 2027, and the bilateral market answered the same day: Amazon's 20-year, 690 MW Calvert Cliffs deal funds a $3 billion expansion of Maryland's only nuclear plant, with new megawatts due 2030 to 2032.

## Sources

1. [StockTwits via Yahoo Finance, "CEG, NRG, TLN Stocks In Spotlight: TD Cowen Warns Of 'Acute' Uncertainty After FERC Delays PJM's Plan To Meet AI Demand", 30 September 2026](https://finance.yahoo.com/energy/articles/ceg-nrg-tln-stocks-spotlight-175147633.html)
2. [Constellation / Business Wire via Yahoo Finance, "Constellation and Amazon Announce 20-Year Power Purchase Agreement Adding 190 Megawatts of Nuclear Capacity at Calvert Cliffs", 30 September 2026](https://finance.yahoo.com/energy/articles/constellation-amazon-announce-20-power-200000338.html)
3. [Investing.com via Yahoo Finance, "Constellation Energy stock climbs on Amazon nuclear power deal", 30 September 2026](https://finance.yahoo.com/markets/stocks/articles/constellation-energy-stock-climbs-amazon-204446267.html)
4. [Utility Dive, "PJM files backstop auction plan at FERC to meet capacity shortfall", 3 August 2026](https://www.utilitydive.com/news/pjm-backstop-capacity-auction-ferc-data-centers/826792/)
5. [Reuters, "FERC asks grid operator PJM to revise plan to shield homes from data center costs", 30 September 2026](https://www.reuters.com/business/energy/ferc-asks-grid-operator-pjm-revise-plan-shield-homes-data-center-costs-2026-09-30/)
6. [OilPrice (ZeroHedge), "PJM Auction Comes Up 6.8 Gigawatts Short As Data Centers Devour Power", 15 July 2026](https://oilprice.com/Energy/Energy-General/PJM-Auction-Comes-Up-68-Gigawatts-Short-As-Data-Centers-Devour-Power.html)
7. [Maryland Matters via The Daily Record, "Amazon abandons plans for data center campus at Calvert Cliffs", 5 August 2026](https://thedailyrecord.com/2026/08/05/amazon-abandons-data-center-plans-calvert-cliffs/)
8. [World Nuclear News, "Google agreement to support Georgia plant uprates", 22 September 2026](https://www.world-nuclear-news.org/articles/google-agreement-to-support-Georgia-plant-uprates)


---

Amazon Bought 20 Years of Nuclear Power the Day PJM's Backstop Auction Failed to Open — The Inference. Canonical: https://theinference.org/article/amazon-bought-20-years-of-nuclear-power-the-day-pjm-s-backstop-auction-failed-to-open