title: "Ameren asks Missouri to bill customers for its 2,100 MW gas plant while it is built, cost still redacted"
description: "Ameren pressed the request at a Nov. 18 hearing, with the plant's cost still redacted in its own filings. The financing ruling decides who pays during construction: Missouri bills if it is granted, Ameren's $38.1 billion plan and $5 billion of new equity if it is refused."
publisher: "The Inference"
section: "Power"
published: 2026-11-21T16:10:35.288Z
modified: 2026-11-21T16:10:35.288Z
canonical: https://theinference.org/article/ameren-asks-missouri-to-bill-customers-for-its-2-100-mw-gas-plant-while-it-is-built-cost-still-redacted
language: en
keywords: "Ameren, Missouri, Utilities, Data Centers, Power Plants"
---

# Ameren asks Missouri to bill customers for its 2,100 MW gas plant while it is built, cost still redacted

> Ameren pressed the request at a Nov. 18 hearing, with the plant's cost still redacted in its own filings. The financing ruling decides who pays during construction: Missouri bills if it is granted, Ameren's $38.1 billion plan and $5 billion of new equity if it is refused.

## A hearing, and still no price tag

Ameren Missouri took its West Alton Energy Center, 2,100 megawatts of combined-cycle gas in three units beside the Sioux coal plant in St [1]. Charles County, to a public hearing at St. Charles Community College on November 18, with construction planned from June 2027 and the units finished one by one through 2031. [1] There the utility pressed its request to bill customers for the plant while it is being built, and the project's cost is still redacted in [its state filings](https://hoodline.com/2026/11/st-charles-county-residents-push-back-on-ameren-s-hidden-cost-gas-plant/) [2], the gap [The Inference flagged in previewing the hearing](https://theinference.org/article/missouri-hearings-nov-18-on-ameren-s-2-100-mw-west-alton-plant-which-has-no-price-tag) on November 10.

## Ameren wants to bill financing costs while it builds

The mechanism, legalized in Missouri in 2025, collects financing costs from customer bills during construction rather than after the plant opens. [3] [Ameren](https://theinference.org/markets/companies/ameren) says waiting until completion means more borrowing over a longer period, and it has [asked the Missouri Public Service Commission for an order by May 2027](https://fox2now.com/news/missouri/ameren-proposes-west-alton-energy-plant-customers-could-pay-some-costs-upfront/). [3] The statute, as quoted from the Missouri Revisor of Statutes, withholds the financing from any resource the commission has not approved and sets the allowable amount only in a separate rate proceeding. [2] Liberty, a smaller Missouri utility, has already received it for a gas plant of its own. [2]

## The consumer advocate says the load is not committed

John Kleiser of the Office of Public Counsel, Missouri's consumer advocate, told the hearing the plant primarily serves "high-demand customers" such as data centers, and the office disputes that the state needs it. [1][2] Its chief economist, Geoff Marke, [testified that absent firm data-center commitments covering entire project costs](https://www.kbia.org/kbia-news/2026-11-11/ameren-plans-three-more-missouri-battery-plants), he does "not believe it is prudent for Ameren Missouri to move forward," warning against "overbuilding for a wildly unpopular industry that is seemingly bleeding money." [4]

## Ameren counts 2.8 gigawatts as signed

Rob Dixon, Ameren Missouri's vice president of regulatory and legislative affairs, answered that Missouri must provide power "to everyone who participates in the economy... and that includes data centers." [1] The utility points to 2.8 gigawatts of signed contracts, Google and [Amazon](https://theinference.org/markets/companies/amazon) among them, [5] which [The Inference reported in September](https://theinference.org/article/ameren-justifies-a-gas-buildout-and-missouri-coal-to-2042-with-2-8-gw-of-signed-demand), and $21 million of projected base-rate savings for customers over two years. [2]

*Chart: **West Alton is sized against load that is mostly not yet under contract** Bars comparing Ameren Missouri's large-load demand by stage: completed interconnection studies, signed electric service agreements, and projects with construction agreements, in gigawatts*

*Nameplate gigawatts by stage of Ameren Missouri's large-load queue, per Ameren's Q3 2026 call materials as reported by Midwest CRE Advisors; reference line is West Alton's 2.1 GW capacity per Ameren's Missouri filing. [2][5]*

## The financing ruling moves a $38.1 billion plan

West Alton sits inside a $38.1 billion capital plan for 2027 through 2031, more than 20 percent above its predecessor, [6][7] one Ameren says will grow rate base, the asset base on which a regulated utility earns its allowed return, about 13.3 percent a year against 8 to 10 percent annual growth in earnings per share. [6] About $5 billion of new equity backs it, $1.7 billion already sold forward, [7] part of the buildout The Inference traced with the September signed-demand story. [Nine-month capital expenditure ran $4.09 billion against $3.12 billion a year earlier](https://www.morningstar.com/news/pr-newswire/20261105cg90490/ameren-announces-third-quarter-2026-results). [6]

*Chart: **Ameren's capex has outrun its operating cash flow in all 12 quarters** Column chart of Ameren's quarterly capital expenditure and operating cash flow from Q4 2023 through Q3 2026 in billions of dollars; capital spending exceeds operating cash flow in every quarter*

*Quarterly capital expenditure and cash from operations, US$ billions, from Ameren's SEC filings, Q4 2023 through Q3 2026. Capex is shown as positive spending and the two series are not netted. [8]*

## Either way the plant gets built, the ruling decides who pays

On the statute's requirement of a separate rate proceeding to set any amount, the commission could approve the plant and still refuse the financing; that is a reading of the text Hoodline quotes, not a settled ruling. [2] A grant puts construction on bills from the first shovel.

A refusal leaves Ameren carrying the plant on its balance sheet and its equity plan until a rate case prices it. Ameren asked for its order by May 2027, [3] the month its Missouri rate-case decision is expected. [7] If Missouri approves the plant, either financing outcome still builds it; the ruling decides who pays while it does.

## Takeaway

Missouri's ruling by May 2027 decides who carries the 2,100 MW West Alton plant while it is built: customers on their bills, or Ameren on its balance sheet and its $5 billion of new equity.

## Sources

1. [The Telegraph (via MSN), "Ameren Missouri seeks approval for new gas plant at Sioux Energy Center in West Alton," 19 November 2026](https://www.msn.com/en-us/news/other/ameren-missouri-seeks-approval-for-new-gas-plant-at-sioux-energy-center-in-west-alton/ar-AA2hN6cm)
2. [Hoodline, "St. Charles County Residents Push Back on Ameren's Hidden-Cost Gas Plant," November 2026](https://hoodline.com/2026/11/st-charles-county-residents-push-back-on-ameren-s-hidden-cost-gas-plant/)
3. [Fox 2 Now (KTVI St. Louis), "Ameren proposes West Alton energy plant, customers could pay some costs upfront," 28 July 2026](https://fox2now.com/news/missouri/ameren-proposes-west-alton-energy-plant-customers-could-pay-some-costs-upfront/)
4. [KBIA, "Ameren plans three more Missouri battery plants," 11 November 2026](https://www.kbia.org/kbia-news/2026-11-11/ameren-plans-three-more-missouri-battery-plants)
5. [Midwest CRE Advisors, "What Ameren's Q3 Call Means for Powered Land in Missouri," 13 November 2026](https://www.mwcreadvisors.com/insights/what-amerens-q3-call-means-for-powered-land-in-missouri)
6. [Ameren Corporation press release via PR Newswire (Morningstar), "Ameren Announces Third Quarter 2026 Results," 5 November 2026](https://www.morningstar.com/news/pr-newswire/20261105cg90490/ameren-announces-third-quarter-2026-results)
7. [Fracmoo, "One Morning, Three Answers: Ameren Raises the Bar, DTE Sells a Business, ConEd Narrows the Guide," 17 November 2026](https://fracmoo.com/energy-investing/november-5-earnings-ameren-dte-conedison/)
8. [Ameren, quarterly figures from its SEC filings, retrieved 21 November 2026](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0001002910)


---

Ameren asks Missouri to bill customers for its 2,100 MW gas plant while it is built, cost still redacted — The Inference. Canonical: https://theinference.org/article/ameren-asks-missouri-to-bill-customers-for-its-2-100-mw-gas-plant-while-it-is-built-cost-still-redacted