title: "Ameren justifies a gas buildout and Missouri coal to 2042 with 2.8 GW of signed demand"
description: "Ameren Missouri's new 20-year plan leans on signed large-load contracts to justify a gas-heavy buildout and six more years for two Labadie coal units. Households are already contesting the first bill."
publisher: "The Inference"
section: "Power"
published: 2026-09-29T22:50:59.424Z
modified: 2026-09-29T22:50:59.424Z
canonical: https://theinference.org/article/ameren-justifies-a-gas-buildout-and-missouri-coal-to-2042-with-2-8-gw-of-signed-demand
language: en
keywords: "Data Centers, Utilities, Natural Gas, Coal, Electricity Rates"
---

# Ameren justifies a gas buildout and Missouri coal to 2042 with 2.8 GW of signed demand

> Ameren Missouri's new 20-year plan leans on signed large-load contracts to justify a gas-heavy buildout and six more years for two Labadie coal units. Households are already contesting the first bill.

## The bill lands before the plants

The AI buildout reached Missouri households long before it reaches a turbine. [Ameren Missouri](https://theinference.org/markets/companies/ameren)'s [pending rate review, filed in June](https://www.msn.com/en-us/money/general/missouri-lawmaker-challenges-proposed-ameren-rate-hike/ar-AA2cmy5C), asks for about $343 million more a year, roughly 10% on residential bills, or $13 a month, the third increase in five years following a 12% increase implemented in June 2025 [2][7]. On 28 September the utility showed regulators what the demand behind that bill looks like, filing a [20-year integrated resource plan](https://www.sec.gov/Archives/edgar/data/1002910/000110465926111420/0001104659-26-111420-index.htm) with the Missouri Public Service Commission [1][3].

## The demand has signatures

The plan's high-load scenarios run 2.9 to 3.9 GW of new demand by 2030, 5 to 6 GW by 2035 and 6 to 9 GW by 2045 [1]. The company has committed to serving 2.8 GW of aggregate large-load demand by 2030 through [signed electric service agreements](https://finance.yahoo.com/energy/articles/ameren-missouri-updates-20-energy-220000809.html) [3], and its rate filing projects electricity sales up more than 60% in five years, largely driven by new large-load customers [2]. The 8-K ties the whole forecast to "the large load customers that signed electric service agreements with Ameren Missouri in 2026" [1]. RBC sizes the opening at $3.5 to $5 billion of potential additional capex [4].

*Chart: **Ameren's quarterly capex jumped 47% in Q1 2026, its biggest quarter in two years** Column chart of Ameren quarterly capital expenditures from Q3 2024 to Q2 2026*

*Quarterly capital expenditures in USD billions, as reported in Ameren's SEC filings; Q1 2026 spend was 47.5% above Q1 2025. Source: Sharadar quarterly fundamentals, retrieved 29 September 2026. [5]*

## Gas does the work, coal gets the years

The preferred plan, picked from more than 20 candidates [3], opens with 1,900 MW of simple-cycle gas by 2029 and closes with 2,400 MW more after 2040 [3], and it pushes two units at the Labadie coal energy center from a 2036 retirement to 2042 [1]. The cleanest line items, 2,400 MW of battery storage by 2030 and 1,200 MW of new nuclear by 2040, ride in the same truck as the gas [1][3]. About 1,800 MW of older gas plants retire along the way [1].

*Chart: **Gas opens the buildout in 2029 and closes it in 2045** Column chart of the plan's eleven dated generation tranches in chronological order, with the gas categories highlighted*

*Preferred-plan resource additions as stated in Ameren's Form 8-K of 28 September 2026, in MW by in-service deadline. Each column is one dated tranche, not a running total; planned, not built. [1]*

## North Carolina killed a forecast. Missouri gets a contract

Ten days earlier, North Carolina regulators [denied Duke Energy a $584 million, 255 MW gas turbine](https://www.msn.com/en-us/news/other/nc-regulators-deny-duke-energys-584-million-gas-turbine-proposal-near-amazon-data-center/ar-AA2cwkzm) beside [Amazon](https://theinference.org/markets/companies/amazon)'s planned $10 billion campus, saying much of the growth behind it "appears tied to future data centers" the commission had not finished verifying [6]. Ameren's demand is papered, and on paper it pays.

The utility's own rate filing pegs about $2.8 million of cost to serve large-load customers against $13.4 million of annual revenue from them, which state Representative Brad Christ says would net households $5.2 million a year if it holds [2][7]. Senate Bill 4 and the Powering Missouri Growth Plan are built to make those customers carry their own infrastructure costs [3][7]. Geoff Marke, chief economist at the Office of Public Counsel, still [warns residential customers are exposed unless cost allocation is exact](https://www.kcur.org/housing-development-section/2026-08-28/missouri-power-grid-upgrades-ai-data-center-electrictiy) [8].

*Chart: **Large-load customers pay in nearly five times what they cost to serve** Bar chart comparing the annual cost to serve Ameren Missouri's large-load customers, their annual revenue, and the projected net benefit to households*

*Annual figures in USD millions from Ameren Missouri's rate filing, as cited by state Representative Brad Christ. The net to households is Christ's projection if the filing's allocation holds. Sources: FOX 2 St. Louis; KFVS12/KCTV, September 2026. [2][7]*

## The check is already in the mail

The rate case, File No. ER-2026-0291, settles the first bill [2], and every plant in the plan still needs its own certificate of convenience and necessity from the commission [1]. RBC [cut its price target from $114 to $107](https://www.ad-hoc-news.de/boerse/news/corporate-news/ameren-corporation-stock-outlines-a-20-year-power-plan-for-missouri/70196387) on 25 September anyway, with the stock at $99.39, 16% below its 52-week high [9]. A forecast died in North Carolina. Missouri is being asked to bet on a signature.

## Takeaway

Ameren Missouri has turned signed data-center contracts into the case for a gas-heavy buildout and coal running to 2042, and the fight over who pays has already reached households.

## Sources

1. [SEC EDGAR, Ameren Corporation and Union Electric Company Form 8-K, 28 September 2026](https://www.sec.gov/Archives/edgar/data/1002910/000110465926111420/0001104659-26-111420-index.htm)
2. [FOX 2 St. Louis (KTVI) via MSN, "Missouri lawmaker challenges proposed Ameren rate hike", September 2026](https://www.msn.com/en-us/money/general/missouri-lawmaker-challenges-proposed-ameren-rate-hike/ar-AA2cmy5C)
3. [Ameren Missouri press release via PR Newswire/Yahoo Finance, "Ameren Missouri updates 20-year energy roadmap", 28 September 2026](https://finance.yahoo.com/energy/articles/ameren-missouri-updates-20-energy-220000809.html)
4. [MT Newswires via Yahoo Finance, "Ameren's Expected Missouri Resource Plan May Point to Higher Spending, RBC Capital Markets Says", 25 September 2026](https://finance.yahoo.com/energy/articles/ameren-apos-expected-missouri-plan-154257922.html)
5. [Sharadar quarterly fundamentals from Ameren's SEC filings, retrieved 29 September 2026](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0001002910)
6. [WRAL News via MSN, "NC regulators deny Duke Energy's $584 million gas turbine proposal near Amazon data center", 18 September 2026](https://www.msn.com/en-us/news/other/nc-regulators-deny-duke-energys-584-million-gas-turbine-proposal-near-amazon-data-center/ar-AA2cwkzm)
7. [KFVS12/KCTV via MSN, "Will data centers drive up your electric bill? Missouri lawmaker asks state regulators to step in", 16 September 2026](https://www.msn.com/en-us/politics/government/will-data-centers-drive-up-your-electric-bill-missouri-lawmaker-asks-state-regulators-to-step-in/ar-AA2cpozD)
8. [KCUR/KBIA, "Missouri power grid faces costly upgrades as AI data centers drive electricity demand", 28 August 2026](https://www.kcur.org/housing-development-section/2026-08-28/missouri-power-grid-upgrades-ai-data-center-electrictiy)
9. [Ad Hoc News, "Ameren Corporation stock outlines a 20-year power plan for Missouri", 29 September 2026](https://www.ad-hoc-news.de/boerse/news/corporate-news/ameren-corporation-stock-outlines-a-20-year-power-plan-for-missouri/70196387)


---