title: "An Indiana county asks American Electric Power to suspend a 75-mile line behind its $100 billion plan"
description: "AEP's growth case, 84 gigawatts of new contracted load and $100 billion of spending through 2031, needs land, ballots and regulators to say yes. On Nov. 17 an Indiana county board asked the utility to suspend one of the transmission lines behind it, two weeks after voters restricted data centers in 40 of 41 ballot contests."
publisher: "The Inference"
section: "Power"
published: 2026-11-21T18:08:36.276Z
modified: 2026-11-21T18:08:36.276Z
canonical: https://theinference.org/article/an-indiana-county-asks-american-electric-power-to-suspend-a-75-mile-line-behind-its-100-billion-plan
language: en
keywords: "American Electric Power, Transmission, Data Centers, Utilities, Indiana"
---

# An Indiana county asks American Electric Power to suspend a 75-mile line behind its $100 billion plan

> AEP's growth case, 84 gigawatts of new contracted load and $100 billion of spending through 2031, needs land, ballots and regulators to say yes. On Nov. 17 an Indiana county board asked the utility to suspend one of the transmission lines behind it, two weeks after voters restricted data centers in 40 of 41 ballot contests.

## A county board asks AEP to stop advancing the line

On Nov. 17 the Steuben County Board of Commissioners asked [AEP Transmission](https://theinference.org/markets/companies/american-electric-power) to suspend the Lulu-Sorenson project until independent research covers public health, the environment, property values and quality of life [1]. The line would run about 75 miles between the Sorenson substation and the Indiana-Michigan state line, on towers up to 175 feet tall; no route is picked, and one is due by late February 2027 [1][2].

Becca Leider, a registered nurse whose land sits in the path, calls the fight "all encompassing" [2]. DeKalb County's board voted unanimously on Nov. 9 to oppose it, after more than 1,000 people attended the September open houses [6][7].

![A high-voltage transmission line on a single steel pole with a wide cleared right of way cut through autumn woodland, looking toward distant fields](https://storage.googleapis.com/theinference-public/img/7b3bebdea7727bd2.jpg)

*A wide cleared right of way cuts through woodland for a high-voltage line. Route selection decides where such corridors go: AEP's Lulu-Sorenson route is due by late February 2027. (Wikideas1)*

## The line carries a $100 billion promise

American Electric Power, the Columbus utility that runs the country's largest transmission network, told investors on Oct. 28 it will spend $100 billion from 2027 through 2031, lifting rate base, the pool of regulated assets it earns on, to $162 billion [3].

*Chart: **AEP's capital spending has outrun operating cash flow in 10 of the last 12 quarters** Line chart of American Electric Power's quarterly capital spending and operating cash flow from the fourth quarter of 2023 through the third quarter of 2026; capital spending sits above operating cash flow in ten of the twelve quarters*

*American Electric Power capital spending and operating cash flow by quarter, US$ billions, as reported. Capital spending exceeded operating cash flow in 10 of the 12 quarters shown. Source: AEP quarterly figures from its SEC filings, retrieved 21 Nov 2026. [12]*

The plan rests on [84 gigawatts of incremental contracted load](https://theinference.org/article/aep-s-100-billion-plan-serves-84-gw-of-signed-load-with-no-equity-number-for-the-other-78-billion) by 2031, 15 gigawatts of it signed in the third quarter alone, and carries [guidance for 9% to 11% annual operating-earnings growth](https://www.sec.gov/Archives/edgar/data/4904/000000490426000069/aep-20261028.htm) with up to $21 billion of bill offsets for residential customers [3]. [Evercore](https://theinference.org/markets/companies/evercore) ISI kept its Outperform rating on Nov. 13 with a $154 target, 19% above the $129.18 close [4].

*Chart: **AEP's $100 billion plan averages $20 billion a year after capex jumped 48% in 2025** Column chart of AEP capital spending by fiscal year from 2020 to 2025, with a dashed bar for the derived average of the 2027-2031 plan*

*AEP capital spending by fiscal year, US$ billions. Final bar divides the $100 billion 2027-2031 plan evenly across five years, a derived average rather than annual guidance. Sources: AEP SEC filings; AEP 8-K, 28 Oct 2026. [11][3]*

## The megawatt queue is thinning

The permission problem shows up first in AEP Ohio's own numbers. Developers requested more than 30,000 megawatts of capacity; once the utility began charging for engineering studies and requiring binding commitments, 13,023 megawatts went to study, and by February 2026 only 5,642 megawatts had signed contracts [5][8]. Another 12,219 megawatts were contracted before the data-center tariff took effect in July 2025 [5][8]. On Nov. 3, voters favored data-center restrictions in 40 of 41 local ballot contests, five of them outright bans [5][9]. In Oklahoma, opponents of [AEP's Branson 345-kilovolt overlay](https://theinference.org/article/203-protests-six-intervenors-oklahoma-decides-monday-who-can-fight-aep-s-power-line) [handed state regulators a petition](https://fox23.com/news/local/landowners-voice-opposition-to-aep-line-to-occ-11-17-2026) with more than 1,400 signatures [10].

*Chart: **AEP Ohio's data-center queue: 30,000-plus MW asked, 5,642 MW signed by February 2026** Bar chart of AEP Ohio's data-center queue showing requested capacity, megawatts that went to paid studies, contracts signed under the tariff, and pre-tariff contracts*

*Stages of AEP Ohio's data-center queue, megawatts. The requested figure is reported as more than 30,000; pre-tariff contracts predate the July 2025 tariff. Sources: Motley Fool via The Globe and Mail, 17 Nov 2026; cleveland.com, 6 Oct 2026. [5][8]*

## The contracts, not the county votes, decide who pays

AEP's Ohio tariff pushes the risk back onto developers: minimum monthly bills, full reimbursement of buildout costs on cancellation or a year's delay, and exit fees worth three years of minimum charges [8]. Federal regulators are weighing the same protections for the regional grid, with [filings due Dec. 16](https://www.cleveland.com/metro/2026/10/ohio-is-planning-for-huge-data-center-demand-what-if-some-projects-never-show-up.html) [8]. AEP says it has "invested time engaging with property owners, local officials and community members" [10]. County boards, DeKalb's president conceded, have no authority to stop a line [6]. The question of who funds the plan was traced in [The Inference's October reporting](https://theinference.org/article/american-electric-power-added-22-billion-of-spending-and-5-2-billion-of-stock-cfo-won-t-promise-24-again) [6].

## The route and the signed megawatts are the checkpoints

The route is named by late February 2027, and AEP Ohio's next signed-megawatt count is the other checkpoint [1][5]. At the February 2026 pace of conversion, AEP either spends $100 billion against less load than planned, or slows the build and the growth promise slips [1][5]. Wall Street underwrote the megawatts; the townships are underwriting the right of way.

## Takeaway

AEP's $100 billion plan leans on 84 gigawatts of contracted load, but a county board's request in Indiana and a thinning Ohio queue show how much of that load still depends on routes, permits and ballots, not signed megawatts.

## Sources

1. [WPTA 21Alive, Steuben County commissioners urge AEP to address community concerns before Lulu-Sorenson project advances, 18 November 2026](https://www.21alivenews.com/2026/11/18/steuben-county-commissioners-urge-aep-address-community-concerns-before-lulu-sorenson-project-advances/)
2. [The Village Reporter, Landowner Questions Health, Land Impact Of Lulu-Sorensen Power Line, 20 November 2026](https://thevillagereporter.com/landowner-questions-health-land-impact-of-lulu-sorensen-power-line/)
3. [American Electric Power, SEC Form 8-K: third-quarter 2026 earnings release and expanded capital plan, 28 October 2026](https://www.sec.gov/Archives/edgar/data/4904/000000490426000069/aep-20261028.htm)
4. [TradingView, Evercore ISI Group maintains American Electric Power at Outperform, raises price target to $154 from $153, November 2026](https://www.tradingview.com/news/tradingview:558fbd48e8c63:0-evercore-isi-group-maintains-american-electric-power-at-outperform-raises-price-target-to-154-from-153/)
5. [Motley Fool via The Globe and Mail, Why a Data Center Slowdown Would Reach Utilities and Electrical Suppliers Before Chipmakers, 17 November 2026](https://www.theglobeandmail.com/investing/markets/stocks/ETN-N/pressreleases/8873214/why-a-data-center-slowdown-would-reach-utilities-and-electrical-suppliers-before-chipmakers/)
6. [The Star (KPCNews), Commissioners oppose proposed power line, 10 November 2026](https://www.kpcnews.com/thestar/article_c49d2490-5ca9-4e16-97d7-5671c0e40359.html)
7. [WANE 15 via MSN, Lulu-Sorenson: I&M, coalition on lingering concerns over transmission improvement project, 28 September 2026](https://www.msn.com/en-us/news/other/lulu-sorenson-i-m-coalition-on-lingering-concerns-over-transmission-improvement-project/ar-AA2d9bXE)
8. [cleveland.com, Who pays if Ohio data center projects don't materialize?, 6 October 2026](https://www.cleveland.com/metro/2026/10/ohio-is-planning-for-huge-data-center-demand-what-if-some-projects-never-show-up.html)
9. [24/7 Wall St., Voters Just Rejected AI Data Centers in 40 of 41 Elections. Is the $1 Trillion Boom in Trouble?, 12 November 2026](https://247wallst.com/investing/2026/11/12/voters-just-rejected-ai-data-centers-in-40-of-41-elections-is-the-1-trillion-boom-in-trouble/)
10. [KOKI FOX 23, Landowners voice opposition to AEP line to OCC, 17 November 2026](https://fox23.com/news/local/landowners-voice-opposition-to-aep-line-to-occ-11-17-2026)
11. [American Electric Power, annual figures from its SEC filings, retrieved 21 November 2026](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0000004904)
12. [American Electric Power, quarterly figures from its SEC filings, retrieved 21 November 2026](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0000004904)


---

An Indiana county asks American Electric Power to suspend a 75-mile line behind its $100 billion plan — The Inference. Canonical: https://theinference.org/article/an-indiana-county-asks-american-electric-power-to-suspend-a-75-mile-line-behind-its-100-billion-plan