title: "Applied Digital signed a $5.4 billion lease, then delivered 25 megawatts of it"
description: "Two days after a lease took contracted revenue past $41 billion, Applied Digital handed over 25 MW of a 200 MW deal, with interest already outrunning rent and a 300 MW year-end goal one hall from failure."
publisher: "The Inference"
section: "Data Center"
published: 2026-11-26T16:08:37.581Z
modified: 2026-11-26T16:08:37.581Z
canonical: https://theinference.org/article/applied-digital-signed-a-5-4-billion-lease-then-delivered-25-megawatts-of-it
language: en
keywords: "Applied Digital, Data Centers, CoreWeave, AI Infrastructure, Credit Risk"
---

# Applied Digital signed a $5.4 billion lease, then delivered 25 megawatts of it

> Two days after a lease took contracted revenue past $41 billion, Applied Digital handed over 25 MW of a 200 MW deal, with interest already outrunning rent and a 300 MW year-end goal one hall from failure.

## $41 billion of paper, 25 megawatts of steel

[Applied Digital](https://theinference.org/markets/companies/applied-digital)'s numbers now argue both sides of its own stock. On November 23 the Dallas-based AI data center developer [signed an 18-year, 150 MW lease with a tier-one investment-grade hyperscaler](https://ir.applieddigital.com/news-events/press-releases/detail/165/applied-digital-secures-new-150-mw-18-year-lease-with), worth about $5.4 billion in base-term revenue and $12.7 billion if renewals run, lifting contracted base-term revenue above $41 billion [2]. On November 25 it [announced its first ready-for-service hall at Polaris Forge 2 in Harwood, North Dakota](https://www.datacenterdynamics.com/en/news/applied-digital-brings-online-25mw-data-hall-at-polaris-forge-2-data-center-in-north-dakota/): 25 megawatts, one-third of the first 75 MW phase, and 12.5% of the 200 MW lease the building sits under [1][4]. Signed paper: $41 billion [1][4]. Delivered steel: 25 MW [1][4].

*Chart: **Applied Digital's fixed claims ran 2.6 times its base rent in the August quarter** Bars comparing Applied Digital's quarterly base rent of $65.8 million, interest expense of $77.4 million, and implied fixed claims of about $171 million including Macquarie's preferred dividend, in the quarter ended August 31, 2026.*

*USD millions, Applied Digital fiscal first quarter ended August 31, 2026. Base rent $65.8 million and interest expense $77.4 million as reported [3]; the third bar is implied from the reported 2.6x ratio of interest plus Macquarie's preferred dividend to base rent [3], not separately reported. Sources: [3] Yahoo Finance/TIKR, November 26, 2026. [3]*

## A goal the release stopped quoting

The release did not repeat the target the company set on October 7: 300 MW of delivered critical IT load across North Dakota by December 31 [1]. Harwood's hall lifts the state total to 275 MW [1]. One more 25 MW hall inside 37 days decides whether that goal is met, and the release names no date for the next two halls [1].

## Lenders and Macquarie get paid before shareholders

The fixed claims sit ahead of equity. In the August quarter, base rent was $65.8 million [3], against [interest expense of $77.4 million](https://theinference.org/article/applied-digital-s-interest-bill-passed-its-rent-for-the-first-time-77-4-million-vs-65-8-million) [3] on $6.4 billion of debt; with [Macquarie Asset Management's preferred dividend](https://theinference.org/article/bondholders-and-macquarie-eat-first-at-applied-digital-s-36-2-billion-table), fixed claims ran 2.6 times rent [3]. Revenue still leans on one-time tenant fit-out fees, $152.4 million of $258.7 million in fiscal Q4, which convert to recurring rent only as halls reach service [1]. Debt rose from $0.8 billion to $6.5 billion in [eight quarters of filings](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0001144879) [5].

*Chart: **Applied Digital's debt rose $5.7 billion over eight quarters, almost matching $5.5 billion of capital spending** Column chart of Applied Digital's capital spending and total debt by quarter, from $0.17 billion of capex and $0.80 billion of debt in the quarter ended November 2024 to $2.08 billion of capex and $6.48 billion of debt in the quarter ended August 2026.*

*USD billions, Applied Digital fiscal quarters, labelled by calendar quarter. Capital spending is capex as reported in SEC filings; total debt is the balance at quarter end. Over the eight quarters shown debt rose from $0.80 billion to $6.48 billion while capex totalled $5.54 billion. Source: [7] Applied Digital, quarterly figures from its SEC filings, retrieved November 26, 2026. [7]*

## The bulls are trimming into the good news

Lucid Capital cut its target to $40 from $83 on November 23, still 227% above the $12.22 close; Roth MKM cut to $28, [Morgan Stanley](https://theinference.org/markets/companies/morgan-stanley) to $25 [3]. And the tenant is the pressure point: [CoreWeave](https://theinference.org/markets/companies/coreweave), whose leases are about a quarter of the backlog, carries a [1,314 basis point credit default spread pricing a 68% five-year default probability](https://economictimes.indiatimes.com/world/us/ai-credit-risk-mounts-as-oracle-and-coreweave-hit-record-cds-spreads-ai-stock-sell-off-adds-to-market-fears-could-rising-debt-costs-derail-the-massive-ai-boom/articleshow/136164314.cms) [6]. Contracts show demand; rent that covers the interest bill shows delivery. If a second Harwood hall lands by December 31, the conversion story holds [6]. If it does not, the market has already priced the answer at $12.22 [6].

## Takeaway

Contracted revenue passed $41 billion on paper while 25 MW of a 200 MW lease is live, fixed claims already run 2.6 times base rent, and one more 25 MW hall by December 31 decides the 300 MW goal.

## Sources

1. [Tech Times, Applied Digital Polaris Forge 2 Data Center Hall Ready for Service; North Dakota 25 MW Short of Goal, 25 November 2026](https://www.techtimes.com/articles/331469/20261125/applied-digital-polaris-forge-2-data-center-hall-ready-service-north-dakota-25-mw-short-goal.htm)
2. [Applied Digital press release, Applied Digital Secures New 150 MW, 18-Year Lease with Tier-One Investment-Grade Hyperscaler, 23 November 2026](https://ir.applieddigital.com/news-events/press-releases/detail/165/applied-digital-secures-new-150-mw-18-year-lease-with)
3. [Yahoo Finance/TIKR, Lucid Capital Cut Its Applied Digital Target to $40 From $83. It Still Sees 227% Upside, 26 November 2026](https://finance.yahoo.com/markets/stocks/articles/lucid-capital-cut-applied-digital-112020828.html)
4. [Data Center Dynamics, Applied Digital brings online 25MW data hall at Polaris Forge 2 data center in North Dakota, 25 November 2026](https://www.datacenterdynamics.com/en/news/applied-digital-brings-online-25mw-data-hall-at-polaris-forge-2-data-center-in-north-dakota/)
5. [Applied Digital quarterly figures from SEC filings, via The Inference company_series, retrieved 26 November 2026](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0001144879)
6. [The Economic Times, AI credit risk mounts as Oracle and CoreWeave hit record CDS spreads, 25 November 2026](https://economictimes.indiatimes.com/world/us/ai-credit-risk-mounts-as-oracle-and-coreweave-hit-record-cds-spreads-ai-stock-sell-off-adds-to-market-fears-could-rising-debt-costs-derail-the-massive-ai-boom/articleshow/136164314.cms)
7. [Applied Digital, quarterly figures from its SEC filings, retrieved 26 November 2026](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0001144879)


---