description: "A long-time skeptic turned bull on Bloom's fuel cells and their milestone-based payments. Those same milestones are why record revenue still burned cash, and the fourth-quarter report, with 2027 guidance, decides which reading holds."
publisher: "The Inference"
section: "Power"
published: 2026-11-19T18:38:47.323Z
modified: 2026-11-19T18:38:47.323Z
canonical: https://theinference.org/article/bmo-upgrades-bloom-energy-and-cuts-its-target-to-230-as-its-record-quarter-burned-181-million-of-cash
language: en
keywords: "Bloom Energy, Fuel Cells, Data Centers, Analyst Ratings, AI Infrastructure"
---

# BMO upgrades Bloom Energy and cuts its target to $230 as its record quarter burned $181 million of cash

> A long-time skeptic turned bull on Bloom's fuel cells and their milestone-based payments. Those same milestones are why record revenue still burned cash, and the fourth-quarter report, with 2027 guidance, decides which reading holds.

BMO Capital Markets, the investment bank whose analysts rate stocks, upgraded [Bloom Energy](https://theinference.org/markets/companies/bloom-energy) to Outperform on November 19, its rating for shares it expects to beat the market, and cut its price target to $230 from $260; the fuel-cell maker's shares still jumped 6%. [1][2]

The day did part of the work: [Anthropic](https://theinference.org/markets/companies/anthropic), the AI lab, went public on Nasdaq in [an offering read as a test of investor appetite for AI](https://finance.yahoo.com/technology/ai/articles/bloom-energy-upgraded-bmo-anthropic-131136589.html), which pulled attention back to everything the buildout needs, power included. [1] Analyst Ameet Thakkar, long a skeptic of the stock, now points to execution and contract protections. [1][2]

The technology is the strong half of the call. The open question is who finances the speed, and this quarter the answer was Bloom's own balance sheet.

## Fuel cells cut the power wait to months

Bloom's fuel cells turn natural gas into electricity through a chemical reaction rather than by burning it, sitting on site at the data center. [3] Bala Naidu, the company's vice president of energy transition, says a grid connection can take five to seven years where power is scarce, while Bloom delivers in months. [3] That gap is why every major US hyperscaler, the giant cloud companies, has approved its systems. [6] Clearing the wait for power does not finish a project; it moves the bottleneck.

## At the showcase site, power finished first

At the New Jersey data center of [Nebius](https://theinference.org/markets/companies/nebius), an AI-cloud builder supplying [Microsoft](https://theinference.org/markets/companies/microsoft), Bloom won approval within three months of signing and had its first units feeding electricity two months later. [3] Nebius still pushed the rest of Microsoft's ordered compute to the second quarter of 2027, blaming site developer DataOne for retiring temporary generators early; Microsoft helped plan the revised timetable and the contracts stand. [3][5] Power was the first constraint solved. The opening date now rests on construction and generators, none of it Bloom's, the same slow conversion [we traced last week](https://theinference.org/article/bloom-energy-s-newest-billion-dollar-ntt-data-and-google-power-deals-ship-nothing-until-2027) in Bloom's order book [3][5].

## Milestone billing puts the wait on Bloom's books

[Third-quarter revenue set a record at $1.24 billion](https://www.sec.gov/Archives/edgar/data/1664703/000162828026066890/be-20261022.htm) and 2026 guidance rose for the third time, [4][6] yet the quarter used $181 million of cash, [as we reported on October 23](https://theinference.org/article/bloom-energy-sold-a-record-1-24-billion-of-fuel-cells-and-still-used-cash-doing-it). [2][6] The cause is milestone-based billing: revenue booked but not yet billed more than tripled this year, to $859 million from $241 million at the end of 2025. [2][6] CFO Simon Edwards calls the cash use "not the beginning of a trend". [6] With two customers making up 69% of revenue, one late milestone moves the quarter. [2]

*Chart: **Revenue has more than tripled since 2023, and the record quarter still burned cash** Line chart of Bloom Energy quarterly revenue from Q4 2023 to Q3 2026, rising from $0.357 billion to a record $1.236 billion, with the Q3 2026 point annotated free cash flow of -$181 million*

*Quarterly revenue, $ billions, by calendar quarter, from Bloom Energy's SEC filings (retrieved November 19, 2026). The Q3 2026 quarter set a record $1.236 billion of revenue and still used $181 million of cash. [4][8]*

## The fourth quarter settles the argument

BMO expects $7.88 billion of 2027 revenue, above the $7.09 billion consensus, on a number Bloom has not yet guided. [1][2] [Oracle](https://theinference.org/markets/companies/oracle), the software company building AI data centers and the customer behind Bloom's 2.8-gigawatt order, burned $5 billion of cash in its August quarter; it reports on December 10, and [its own CFO has promised the data-center spending peaks this year](https://finance.yahoo.com/markets/stocks/articles/oracle-cfo-promises-30-billion-174406178.html). [2][6][7] Bloom follows early next year, needing fourth-quarter revenue of $1.35 billion to $1.55 billion and cash flow back above zero. [6]

Bloom's fuel cells can put power on a site in months. Payment arrives by milestone and can lag by quarters; until billing catches up, Bloom's shareholders fund the gap.

## Takeaway

BMO upgraded Bloom Energy to Outperform and cut its price target to $230 from $260. The record $1.24 billion quarter still used $181 million of cash because milestone billing runs quarters behind revenue, so the fourth-quarter report and 2027 guidance decide whether the bull case holds.

## Sources

1. [Yahoo Finance / Investing.com, "Bloom Energy upgraded at BMO as Anthropic IPO revives AI infrastructure trade", 19 November 2026](https://finance.yahoo.com/technology/ai/articles/bloom-energy-upgraded-bmo-anthropic-131136589.html)
2. [Yahoo Finance, "Bloom Energy Soars 6% as One-Time Skeptic BMO Upgrades on Anthropic IPO Day", 19 November 2026](https://finance.yahoo.com/markets/stocks/articles/bloom-energy-soars-6-one-143423834.html)
3. [Benzinga, "Exclusive: AI Data Centers Face Years Waiting for Grid Power. Bloom Says They Don't Have to Wait", 19 November 2026](https://www.benzinga.com/markets/prediction-markets/26/11/63408856/exclusive-ai-data-centers-face-years-waiting-for-grid-power-bloom-says-they-dont-have-to-wait)
4. [Bloom Energy Corporation, Form 8-K reporting third-quarter 2026 results, filed 22 October 2026](https://www.sec.gov/Archives/edgar/data/1664703/000162828026066890/be-20261022.htm)
5. [FinanceFeeds, "Nebius Stock Falls 18% Despite Q3 Beat as 2026 Outlook Weakens", 13 November 2026](https://financefeeds.com/nebius-stock-falls-18-despite-q3-beat-as-2026-outlook-weakens/)
6. [Yahoo Finance, "'A Standard for AI Onsite Power': Bloom Energy Is Up 100% in 2026. Is It Too Late to Buy?", 17 November 2026](https://finance.yahoo.com/markets/stocks/articles/standard-ai-onsite-power-bloom-045903234.html)
7. [Yahoo Finance, "Oracle CFO Promises '$30 Billion Plus' in Free Cash Flow by Fiscal 2029 After a 70% Plunge", 11 November 2026](https://finance.yahoo.com/markets/stocks/articles/oracle-cfo-promises-30-billion-174406178.html)
8. [Bloom Energy, quarterly figures from its SEC filings, retrieved 19 November 2026](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0001664703)


---