title: "Core Scientific's $1.2 billion profit is mostly a warrant gain, not rent"
description: "The miner turned landlord booked $215.4 million of colocation rent, then reported a $1.18 billion profit that was mostly a warrant gain, while its anchor tenant's bonds trade near distressed levels and its own buildout leans on that tenant's cash."
publisher: "The Inference"
section: "Data Center"
published: 2026-11-25T17:36:27.947Z
modified: 2026-11-25T17:36:27.947Z
canonical: https://theinference.org/article/core-scientific-s-1-2-billion-profit-is-mostly-a-warrant-gain-not-rent
language: en
keywords: "Core Scientific, CoreWeave, Data Centers, Colocation, ERCOT"
---

# Core Scientific's $1.2 billion profit is mostly a warrant gain, not rent

> The miner turned landlord booked $215.4 million of colocation rent, then reported a $1.18 billion profit that was mostly a warrant gain, while its anchor tenant's bonds trade near distressed levels and its own buildout leans on that tenant's cash.

## The mining is gone; the rent is real

[Core Scientific](https://theinference.org/markets/companies/core-scientific)'s third quarter ended the argument about what the company is. Colocation, renting powered data center halls to AI computing firms, brought in $215.4 million of $232.9 million total revenue, up from $15.0 million a year earlier [9][3]. Self-mining produced $12.3 million and stops by December 31, 2026, when the company becomes a landlord full time [9][3]. [Billing capacity reached 485 megawatts](https://theinference.org/article/core-scientific-s-10-q-counts-its-backlog-in-megawatts-not-24-billion), worth over $700 million in annualized colocation revenue [9].

*Chart: **Colocation replaced mining as Core Scientific's revenue in four quarters** Grouped columns comparing Core Scientific's Q3 2025 and Q3 2026 revenue by segment: colocation jumps from $15 million to $215 million while self-mining falls from $57 million to $12 million*

*Revenue by segment, in millions of dollars, for the quarters ended Sept. 30, 2025 and Sept. 30, 2026. Colocation is 92 percent of third-quarter 2026 revenue; self-mining stops by December 31, 2026. Sources: Core Scientific's third-quarter 2026 results, Form 8-K (Nov. 5, 2026), and Texas Technology News on bitcoin miners turned AI landlords. [9][2]*

## The profit is paper, the bill is cash

Net income of $1.18 billion carried a $1.03 billion non-cash gain on the fair value of warrants; operating income was $72.4 million [9]. The quarter cost $985.1 million of capital spending, long-term debt stands at $4.30 billion, and book equity is negative $1.09 billion [9].

*Chart: **Net income swings on warrant marks while free cash flow stays negative** Grouped columns of Core Scientific's quarterly net income against free cash flow from late 2024 to the third quarter of 2026: net income ranges from negative $1.16 billion to positive $1.18 billion while free cash flow is negative in every quarter*

*Net income and free cash flow, $ billions, for the quarters ended Sept. 30, 2024 through Sept. 30, 2026. Free cash flow is operating cash flow less capital spending. Source: Core Scientific's quarterly SEC filings. [13]*

The tenant is paying the building bill. [CoreWeave](https://theinference.org/markets/companies/coreweave) funded $180.9 million of Core Scientific's capital spending in the first nine months of 2026, with $202.2 million more of pass-through spending expected, and Core Scientific carried a $282.7 million customer funding receivable at September 30 [1][9]. [A review of the results](https://texastechnologynews.com/texas-bitcoin-miners-turn-landlords-riots-28-billion-lease/) found the roughly $6 billion project-bond financing for the [AMD](https://theinference.org/markets/companies/amd) buildout still unsecured [2].

![Aerial view of Core Scientific's Pecos, Texas data center campus under construction, with finished data halls and crane work on the next buildings](https://storage.googleapis.com/theinference-public/img/49c600eab1cd5c45.jpg)

*Core Scientific's Pecos, Texas campus in a November 2026 flyover. The company says the first tranche of capacity there is due in early 2027, funded in part by its tenant's cash. (Core Scientific via X)*

## The tenant's credit is the landlord's risk

CoreWeave is the anchor tenant under a [500-megawatt hosting agreement](https://constructionreviewonline.com/core-scientifics-100-mw-muskogee-ai-data-center-advances-under-8-7b-coreweave-deal/) worth about $8.7 billion over 12 years [7]. Its 9.625 percent note due 2032 fell to 74.9 cents on the dollar on November 24, the lowest since issuance [10]. Its 2031 bond traded at 74.23 cents on November 25 for a 17.91 percent yield [4], and five-year credit default swaps, insurance against a missed payment, imply a 68 percent chance of default within five years [5]. The stock halved after Core Scientific shareholders [refused CoreWeave's $9 billion takeover bid](https://theinference.org/article/coreweave-s-stock-has-halved-since-core-scientific-shareholders-refused-its-9-billion-bid); the rent ledger that survived is now priced against the would-be buyer's own bonds [11].

| CoreWeave credit marker | Level | Date |
| --- | --- | --- |
| 9.625% note due 2032 | 74.9 cents on the dollar, lowest since issuance | Nov. 24, 2026 |
| 2031 bond | 74.23 cents on the dollar, 17.91% yield | Nov. 25, 2026 |
| Five-year credit default swaps | 68% implied chance of default within five years | Nov. 25, 2026 |

*CoreWeave's debt and default insurance, as reported by GuruFocus, Investing.com and StockTwits on November 24 and 25, 2026.*

## The bull case has a second tenant

AMD has leased about 110 megawatts at the Hunt County, Texas site, a $1.3 billion project [listed in the state's construction records](https://www.tokenpost.com/news/business/60231), with first deliveries in the first half of 2028 [3]. Bernstein and B. Riley kept Buy ratings on the stock, at $19 and $27 price targets [1]. Sellers did not care: the stock fell 10.8 percent on November 24 and sits below every major moving average [8].

## The gate is ERCOT on December 10

December 10 [6]. ERCOT, the Texas grid operator, rules that day on 6.5 gigawatts of large-load designations under its [Batch Zero review](https://finance.yahoo.com/technology/articles/6-5-gw-texas-data-155707557.html), Core Scientific among the applicants, and power approvals are the gate for everything above [6]. For readers who want the same AI power demand without the tenant's credit risk, the same trade exists one step upstream as a power seller: [Constellation Energy](https://theinference.org/markets/companies/constellation-energy), the nation's largest producer of clean energy, counts data centers among its customers [12].

## Takeaway

Core Scientific is now a landlord: $215.4 million of colocation rent in the third quarter, 92 percent of revenue. The $1.18 billion profit on top of it was mostly a $1.03 billion non-cash warrant gain, and the buildout is funded partly by the tenant whose bonds trade near distressed levels.

## Sources

1. [Poisar (fiscal.ai), Core Scientific Discloses Financial Details of CoreWeave Colocation Agreement, 19 November 2026](https://poisar.com/news/127186348)
2. [Texas Technology News, Texas bitcoin miners become AI landlords: Riot's $28 billion Corsicana lease, 25 November 2026](https://texastechnologynews.com/texas-bitcoin-miners-turn-landlords-riots-28-billion-lease/)
3. [TokenPost, Texas Record Lists $1.3 Billion Data Center Project at Core Scientific Site, 25 November 2026](https://www.tokenpost.com/news/business/60231)
4. [Yahoo Finance (Investing.com), CoreWeave bonds plunge as 2031 yield surges to 17.91%; Shares drop 10%, 25 November 2026](https://finance.yahoo.com/technology/ai/articles/coreweave-bonds-plunge-2031-yield-160749981.html)
5. [Yahoo Finance (StockTwits), ORCL, GOOGL, SPCX, CRWV Credit Default Swap Spreads Hit Records, 25 November 2026](https://finance.yahoo.com/markets/stocks/articles/ai-concerns-resurface-orcl-googl-065618202.html)
6. [Yahoo Finance (Blockspace), 6.5 GW of Texas data center load faces December 10 ERCOT Batch Zero decision: Needham, 23 November 2026](https://finance.yahoo.com/technology/articles/6-5-gw-texas-data-155707557.html)
7. [Construction Review Online, Core Scientific's 100-MW Muskogee AI Data Center Advances Under $8.7B CoreWeave Deal, 19 November 2026](https://constructionreviewonline.com/core-scientifics-100-mw-muskogee-ai-data-center-advances-under-8-7b-coreweave-deal/)
8. [Traders Union, Core scientific slides 10.82% today, 25 November 2026](https://tradersunion.com/news/stocks/show/4397314-core-scientific-slides-10-82percent-today/)
9. [SEC Form 8-K, Core Scientific Announces Third Quarter 2026 Results, 5 November 2026](https://www.sec.gov/Archives/edgar/data/1839341/000183934126000028/core-20261105.htm)
10. [Yahoo Finance (GuruFocus), CoreWeave's Debt Trades Near 75 Cents on the Dollar, 25 November 2026](https://finance.yahoo.com/markets/stocks/articles/coreweaves-debt-trades-near-75-151923965.html)
11. [The Inference, CoreWeave owes $10.6 billion by 2027; its landlord Core Scientific just hit a 52-week low of $12.79, 16 October 2026](https://theinference.org/article/coreweave-owes-10-6-billion-by-2027-its-landlord-core-scientific-just-hit-a-52-week-low-of-12-79)
12. [Constellation, Electricity Provider and Gas Supplier, company website, retrieved 25 November 2026](https://www.constellation.com/)
13. [Core Scientific, quarterly figures from its SEC filings, retrieved 25 November 2026](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0001839341)


---

Core Scientific's $1.2 billion profit is mostly a warrant gain, not rent — The Inference. Canonical: https://theinference.org/article/core-scientific-s-1-2-billion-profit-is-mostly-a-warrant-gain-not-rent