title: "Crusoe kills its $1.25B Boom turbine order days after a $3.9B raise"
description: "Boom Supersonic's turbine business just lost its only named customer and the anchor revenue behind its plan to fund the Overture jet. Crusoe, days after a $3.9 billion raise, is buying grid power and proven machines instead."
publisher: "The Inference"
section: "Power"
published: 2026-09-27T23:31:36.832Z
modified: 2026-09-27T23:31:36.832Z
canonical: https://theinference.org/article/crusoe-kills-its-1-25b-boom-turbine-order-days-after-a-3-9b-raise
language: en
keywords: "Crusoe, Boom Supersonic, Data Centers, Gas Turbines, AI Infrastructure"
---

# Crusoe kills its $1.25B Boom turbine order days after a $3.9B raise

> Boom Supersonic's turbine business just lost its only named customer and the anchor revenue behind its plan to fund the Overture jet. Crusoe, days after a $3.9 billion raise, is buying grid power and proven machines instead.

## The launch customer walked

Blake Scholl broke the news himself. In [an X post on Friday](https://techcrunch.com/2026/09/25/crusoe-abandons-1-25b-plan-to-use-boom-turbines-at-ai-data-centers/), after congratulating [Crusoe](https://theinference.org/markets/companies/crusoe)'s founders on their $3.9 billion raise, Boom Supersonic's CEO wrote that "turbines are no longer part of Crusoe's near term primary power mix at Abilene/etc., so a launch partnership just didn't make sense," and Crusoe confirmed the split [1].

What died was [a December 2025 agreement worth $1.25 billion](https://www.unite.ai/boom-and-crusoe-end-superpower-turbine-launch-partnership/): 29 of Boom's 42-megawatt Superpower turbines, about 1.21 gigawatts, with first deliveries due from 2027 [1][2].

The raise Scholl congratulated [closed on 17 September at a $30.9 billion valuation](https://techcrunch.com/2026/09/17/crusoe-raises-3-9b-to-build-massive-data-centers-and-small-modular-ai-factories/), with [Nvidia](https://theinference.org/markets/companies/nvidia) and the Qatar Investment Authority in the round [3]. Crusoe's funding week then ended in a Texas permit freeze and a Bronze rating, a run of reversals the Boom exit now extends, as tracked in *Crusoe's $3.9 Billion Week Ended With a Texas Permit Freeze and a Bronze Rating*.

## The jet was supposed to run on turbine profits

Boom built Superpower as a derivative play, sharing roughly 80 percent of its parts with the Symphony engine destined for Overture, and raised $300 million in December 2025 largely to commercialize it [1][2]. The stated plan: stationary-power profits fund the airliner, which carries an order book of 130 aircraft including United, American and Japan Airlines [2]. That plan now has no anchor tenant.

*Chart: **Boom's cancelled Crusoe order was bigger than its entire 2028 target** Bar chart comparing Boom's cancelled 1.21 gigawatt Crusoe order with its 1 gigawatt 2028 delivery target and 250 megawatt of 2027 deliveries to other sites.*

*Capacity in megawatts. Crusoe's cancelled order was 1.21 GW across 29 turbines, $1.25 billion. The 2027 and 2028 figures are Boom CEO Blake Scholl's stated delivery plans, not reported shipments. Sources: TechCrunch, 25 Sep 2026; Unite.AI, 25 Sep 2026. [1][2]*

![Rendering of Boom Supersonic's Overture supersonic airliner in flight](https://storage.googleapis.com/theinference-public/img/8284e3904c294002.png)

*A rendering of Overture, the supersonic airliner Boom planned to fund partly with Superpower turbine profits. Its order book lists 130 aircraft, including United, American and Japan Airlines. (Kuat-Entralla 3D Engineering via Wikimedia Commons)*

## A famine, and still no taker for the new machine

The backdrop is the worst turbine famine on record. A heavy-duty GE Vernova unit ordered today arrives in 2031, Siemens Energy quotes three years or more, and [Wood Mackenzie counts 60 to 70 gigawatts of world manufacturing capacity against roughly 110 gigawatts of orders](https://www.msn.com/en-us/technology/artificial-intelligence/the-gas-turbine-shortage-just-became-ai-s-biggest-constraint/ar-AA2aJCdJ) [5]. GE Vernova's book is full through 2029, about 20 percent of it feeding data centers [6].

Even that market would not take the product risk: Crusoe's 1.2-gigawatt Abilene campus for [Oracle](https://theinference.org/markets/companies/oracle) and [OpenAI](https://theinference.org/markets/companies/openai) runs on grid power, and its 900-megawatt [Microsoft](https://theinference.org/markets/companies/microsoft) campus will use conventional on-site gas turbines [1]. A shortage deep enough to sell out GE Vernova to 2031 still could not sell the industry a turbine that has never run in the field.

*Chart: **Crusoe's gigawatt-scale sites run on grid power and proven gas, not Boom turbines** Column chart comparing Crusoe's three power arrangements: 1,200 megawatts at the Abilene campus on grid power, 900 megawatts at its Microsoft campus on conventional gas turbines, and the cancelled 1,210 megawatt Boom Superpower order highlighted.*

*Site capacity in megawatts. Crusoe's 1.2 GW Abilene campus for Oracle and OpenAI runs on grid power; its 900 MW Microsoft campus will use conventional on-site gas turbines. The cancelled Boom order covered 29 Superpower turbines, about 1.21 GW, worth $1.25 billion. Sources: TechCrunch, 25 Sep 2026; Unite.AI, 25 Sep 2026. [1][2]*

## Both sides left the door open, and the risk moved

Scholl says Boom will deliver about 250 megawatts to other sites next year, targets a gigawatt in 2028, and holds out a reunion, saying "the future is long" [1]. Crusoe spokesperson Andrew Schmitt called Boom "a great partner" that is "not the right fit today," with Crusoe picking turbines, wind, solar, batteries or the grid site by site [1].

[One report says Boom's backlog still lists the Crusoe order](https://cryptobriefing.com/crusoe-abandons-boom-supersonic-turbine-deal/), and that Baker Hughes, which was contracted to supply generators behind the deal, is left exposed [4]. The unnamed 2027 buyers now carry the delivery risk.

## Watch the 250 megawatts

Crusoe keeps its capital and its schedule; Boom's jet now waits on customers it has not named and a 2027 delivery plan with no reference customer. First Superpowers running in the field, not pitch decks, is what rebuilds this.

## Takeaway

Crusoe walked from Boom's 29-turbine, $1.25 billion Superpower order days after closing a $3.9 billion raise at a $30.9 billion valuation, leaving Boom's turbine business with no named customer and its Overture funding plan without an anchor. Even a turbine market sold out to 2031 would not take an unfielded machine.

## Sources

1. [TechCrunch, "Crusoe abandons $1.25B plan to use Boom turbines at AI data centers", 25 September 2026](https://techcrunch.com/2026/09/25/crusoe-abandons-1-25b-plan-to-use-boom-turbines-at-ai-data-centers/)
2. [Unite.AI, "Boom and Crusoe End Superpower Turbine Launch Partnership", 25 September 2026](https://www.unite.ai/boom-and-crusoe-end-superpower-turbine-launch-partnership/)
3. [TechCrunch, "Crusoe raises $3.9B to build massive data centers and small modular 'AI factories'", 17 September 2026](https://techcrunch.com/2026/09/17/crusoe-raises-3-9b-to-build-massive-data-centers-and-small-modular-ai-factories/)
4. [Crypto Briefing, "Crusoe abandons $1.25B turbine plan with Boom Supersonic", 25 September 2026](https://cryptobriefing.com/crusoe-abandons-boom-supersonic-turbine-deal/)
5. [Oilprice via MSN, "The gas turbine shortage just became AI's biggest constraint", Michael Kern, 22 August 2026](https://www.msn.com/en-us/technology/artificial-intelligence/the-gas-turbine-shortage-just-became-ai-s-biggest-constraint/ar-AA2aJCdJ)
6. [CNBC, "How GE Vernova builds the massive gas turbines powering the AI data center boom", 27 June 2026](https://www.cnbc.com/2026/06/27/ge-vernova-gas-turbines-ai-data-centers.html)


---

Crusoe kills its $1.25B Boom turbine order days after a $3.9B raise — The Inference. Canonical: https://theinference.org/article/crusoe-kills-its-1-25b-boom-turbine-order-days-after-a-3-9b-raise