title: "Entergy's gas plant for Meta hits $1.755 billion, 63% over estimate"
description: "A redacted Louisiana filing puts the first hard number on construction inflation in power built for a single AI customer, weeks before regulators vote on seven more Entergy plants under a fast-track that waives lowest-cost rules. December decides whether the bill lands on Meta, on Louisiana ratepayers, or on the growth story behind Entergy's premium multiple."
publisher: "The Inference"
section: "Power"
published: 2026-11-20T16:11:46.219Z
modified: 2026-11-20T16:11:46.219Z
canonical: https://theinference.org/article/entergy-s-gas-plant-for-meta-hits-1-755-billion-63-over-estimate
language: en
keywords: "Entergy, Meta, Data Center Power, Louisiana, Utilities"
---

# Entergy's gas plant for Meta hits $1.755 billion, 63% over estimate

> A redacted Louisiana filing puts the first hard number on construction inflation in power built for a single AI customer, weeks before regulators vote on seven more Entergy plants under a fast-track that waives lowest-cost rules. December decides whether the bill lands on Meta, on Louisiana ratepayers, or on the growth story behind Entergy's premium multiple.

Waterford 5, one of three gas plants [Entergy](https://theinference.org/markets/companies/entergy) Louisiana is building to serve a single customer, [Meta](https://theinference.org/markets/companies/meta)'s Hyperion data center in Richland Parish, is now projected at $1.755 billion, according to [the quarterly report the utility filed this month](https://www.wwno.org/investigations/2026-11-19/entergys-meta-gas-plant-costs-soar-as-utility-seeks-approval-for-seven-more) with state regulators at the Louisiana Public Service Commission [1]. That is 63% above the original estimate, and the public version of the filing redacts the spending detail behind the increase [1].

The AI demand behind the plant is not the risk; [who pays when construction outruns an estimate](https://theinference.org/article/who-pays-for-the-ai-grid-arkansas-wants-money-back-louisiana-families-want-their-land) is, and in December Entergy asks the state to repeat this structure seven more times [2].

## Soft ground and higher labor, on the record since May

The cause is on the record in [an earlier filing](https://www.msn.com/en-us/news/other/cost-of-entergy-power-plant-for-meta-project-jumps-676m-to-nearly-18b/ar-AA2hP0CB): soil that forces the site to be built up several feet on 120-foot piles, plus higher labor and equipment costs; the same dollar figure has stood in Entergy's reports since May [2]. The pattern runs wider. The full Laidley build for Meta now costs more than Entergy originally filed, even with two components under budget [1], and Waterford 6, a separate plant approved in 2025, is already nearly $500 million over its projection, according to Environmental Defense Fund intervenors [1].

*Chart: **Waterford 5 is 63% over its filed cost; the wider Meta build climbed too** Range chart: Waterford 5 gas plant cost rises from $1.079 billion as filed to $1.755 billion forecast, and the Laidley Project total from $3.956 billion to $4.3625 billion.*

*Entergy Louisiana quarterly monitoring reports to the Louisiana Public Service Commission, covering generation and transmission serving Meta's $50 billion Hyperion data center. Source: WWNO/Gulf States Newsroom, November 19, 2026. [1]*

![Entergy's Ninemile 6 natural gas unit near Westwego, Louisiana, lit at dusk, with a levee road in the foreground](https://storage.googleapis.com/theinference-public/img/eb5d0c77c6a65224.jpg)

*Entergy's 560-megawatt Ninemile 6 gas unit near Westwego, Louisiana, the same kind of plant the utility is now building for Meta at Waterford and Laidley. Construction costs for that build have outrun their estimates. (Chad Davis)*

## Meta pays for 15 years; the plants run for decades

Entergy told Meta of the increase in January and was told to keep building; Meta pays more during its 15-year contract, and gas plants outlive contracts [1]. The commission declined to cap construction costs, and denial in the prudence reviews after construction is, in consumer advocate Logan Burke's words, wildly unusual [1].

[Testifying under oath in October](https://www.wwltv.com/article/news/investigations/david-hammer/entergy-ratepayers-likely-to-shoulder-part-of-20b-buildout-for-meta/289-ca52465b-0b54-411f-bd38-31b3e1c46fa1), Entergy executive Ryan Jones put the residual risk on the record: if the plants still provide value after Meta's term, the company would expect to recover what remains from its other customers [6]. Ratepayers already carry at least $470 million of the project's transmission under the application [1].

## Investors are banking the same demand

[Third-quarter adjusted earnings of $1.98 a share](https://finance.yahoo.com/markets/stocks/articles/entergy-reports-third-quarter-2026-113000474.html) beat estimates, and management raised the floor of its 2026 guidance [3][4]. Entergy [added $1.5 billion of capital investment through 2030](https://www.fool.com/earnings/takeaways/2026/11/02/entergy-3-key-takeaways-for-long-term-investors/) [5] and told investors that standardized plant designs cut engineering time roughly in half, blunting labor-cost exposure [5]. Waterford 5 shows where that blunting ends: a standard design does not move soft ground [4]. The stock trades near 25 times trailing earnings [4].

## December decides who owns the overrun

On December 10 the commission takes up Project Evest: seven more gas plants, more than $14 billion of build, for Meta, under the Lightning Directive, a fast-track that waives the rule pushing utilities toward the lowest-cost option [7][8]. Three groups sued on November 9 to void the directive, [arguing the commission changed its rules without public notice](https://www.thecentersquare.com/louisiana/article_d213f647-72b9-4212-937d-8e501c32e702.html) [8].

*Chart: **December's vote covers seven plants, at about eight times Waterford 5's cost** Bar chart: Waterford 5 at $1.755 billion, the Laidley Project at $4.3625 billion, and Project Evest, seven plants for Meta, at more than $14 billion.*

*Capital cost of the gas plants Entergy Louisiana is building and proposing for Meta's Hyperion data center, in billions of dollars. Waterford 5 is one of three plants under construction; Project Evest is the seven awaiting the commission's December 10 vote. Sources: WWNO/Gulf States Newsroom and WWL-TV, November 2026. [1][7][8]*

Approval at these costs keeps the growth plan intact and embeds the prudency risk; friction that slows the fast-track hits the capex behind the valuation. The buildout should happen, and [the risk belongs with the parties who signed for the megawatts](https://theinference.org/article/meta-will-take-4-500-megawatts-from-entergy-whose-ceo-admits-it-hasn-t-studied-the-downside), not with ratepayers who never got a vote. The bottleneck in AI power is no longer megawatts; it is the fine print that decides who pays when the ground is softer than the estimate.

## Takeaway

Waterford 5, one of the gas plants Entergy Louisiana is building for Meta, is now projected at $1.755 billion, 63% above its filed cost, with the spending detail redacted. On December 10 the Louisiana commission votes on seven more plants worth more than $14 billion under a fast-track that waives lowest-cost rules, and the suit against that fast-track is already filed.

## Sources

1. [WWNO / Gulf States Newsroom, "Entergy's Meta gas plant costs soar as utility seeks approval for seven more," 19 November 2026](https://www.wwno.org/investigations/2026-11-19/entergys-meta-gas-plant-costs-soar-as-utility-seeks-approval-for-seven-more)
2. [WWL-TV New Orleans (David Hammer), "Cost of Entergy power plant for Meta project jumps $676M to nearly $1.8B," 20 November 2026](https://www.msn.com/en-us/news/other/cost-of-entergy-power-plant-for-meta-project-jumps-676m-to-nearly-18b/ar-AA2hP0CB)
3. [Entergy Corporation press release (PR Newswire via Yahoo Finance), "Entergy reports third quarter 2026 financial results," 2 November 2026](https://finance.yahoo.com/markets/stocks/articles/entergy-reports-third-quarter-2026-113000474.html)
4. [AInvest, "Entergy Leads Market Volume as AI Demand and Earnings Beat Fuel $0.37B Trading Spree," 20 November 2026](https://www.ainvest.com/news/entergy-leads-market-volume-ai-demand-earnings-beat-fuel-0-37b-trading-spree-2611/)
5. [The Motley Fool, "Entergy: 3 Key Takeaways for Long-Term Investors," 2 November 2026](https://www.fool.com/earnings/takeaways/2026/11/02/entergy-3-key-takeaways-for-long-term-investors/)
6. [WWL-TV (David Hammer), "Entergy ratepayers could shoulder part of $20B buildout tied to Meta data center," 23 October 2026](https://www.wwltv.com/article/news/investigations/david-hammer/entergy-ratepayers-likely-to-shoulder-part-of-20b-buildout-for-meta/289-ca52465b-0b54-411f-bd38-31b3e1c46fa1)
7. [WWNO / Gulf States Newsroom, "Entergy wants their land for Meta's power lines. They're suing the regulators approving them," 9 November 2026](https://www.wwno.org/economy/2026-11-09/entergy-wants-their-land-for-metas-power-lines-theyre-suing-the-regulators-approving-them)
8. [The Center Square, "Consumer advocates sue regulators over fast-track Louisiana data center approvals," 9 November 2026](https://www.thecentersquare.com/louisiana/article_d213f647-72b9-4212-937d-8e501c32e702.html)


---

Entergy's gas plant for Meta hits $1.755 billion, 63% over estimate — The Inference. Canonical: https://theinference.org/article/entergy-s-gas-plant-for-meta-hits-1-755-billion-63-over-estimate