title: "Equinix says power limits its 255 data centers, then bills 299,300 cabinets"
description: "The data center operator's filings count its 255-site estate in cabinets while its own risk factor says power is what binds, so no outsider can price its promise that households will not carry grid costs. Its policy chief now sits in the Washington fight that will decide who does."
publisher: "The Inference"
section: "Data Center"
published: 2026-11-29T17:07:08.624Z
modified: 2026-11-29T17:07:08.624Z
canonical: https://theinference.org/article/equinix-says-power-limits-its-255-data-centers-then-bills-299-300-cabinets
language: en
keywords: "Equinix, Data Centers, Power, Ratepayers, Grid"
---

# Equinix says power limits its 255 data centers, then bills 299,300 cabinets

> The data center operator's filings count its 255-site estate in cabinets while its own risk factor says power is what binds, so no outsider can price its promise that households will not carry grid costs. Its policy chief now sits in the Washington fight that will decide who does.

Two sentences from [Equinix](https://theinference.org/markets/companies/equinix) landed three days apart. On November 25, chief executive Adaire Fox-Martin told [McKinsey](https://theinference.org/markets/companies/mckinsey) that buying energized land is "job number one" for her teams and that large users "must ensure households do not bear those grid costs" [3]. On November 28, the company's head of energy policy, Cy McGeady, [was reported joining the Washington fight over who pays for grid upgrades](https://broadbandbreakfast.com/equinixs-cy-mcgeady-who-called-power-ais-binding-constraint-joins-ratepayer-fights/), on a panel beside the aide carrying a bill that would force data centers to pay everything [4][5][7]. The document underneath both moves says one thing and counts another.

## The filing says power limits Equinix, and counts its data centers in space instead

Equinix's [2025 Form 10-K, filed February 11, 2026](https://btw.media/en/equinix-power-is-the-limit-its-numbers-count-space), states in a risk factor: "power, not space, is a limiting factor in many of our IBX data centers" [1]. The properties section then counts the same 255-site estate in the quantity that sentence rules out: 392,300 cabinets of capacity, 299,300 billed, revenue per cabinet, no megawatt column anywhere [1]. The Q3 2026 materials keep the habit: 399,700 cabinet equivalents, 313,300 billed, $2,574 a month per cabinet, 78% utilization [1].

## A cabinet is 4 kW in the base and about 18 at Dallas 12

That count is nearly the whole business. Billed cabinets at that rate annualize to about $9.7 billion against FY2025 revenue of $9,217 million [1]. The unit is slippery, too. Equinix's chief business officer put new deals at 6.6 kW a cabinet and the installed base "somewhere just north of 4" at a March conference; Dallas 12, [the build we covered on November 17](https://theinference.org/article/equinix-plans-a-500-million-dallas-data-center-blackstone-pays-a-7-yield-for-amazon-leased-buildings), prints both units at once, about 3,700 cabinets or 67 megawatts, on $837 million of capex targeting Q2 2028 [1]. AI racks industry-wide are climbing from 20 kW toward a megawatt [2].

*Chart: **A cabinet means 4 kW in Equinix's installed base and about 18 at Dallas 12** Column chart comparing kilowatts per cabinet across Equinix's installed base (about 4 kW), new deals (6.6 kW) and the Dallas 12 project (about 18.1 kW, derived and marked as an estimate).*

*Kilowatts of power per cabinet across three Equinix figures. Installed base and new deals: chief business officer, Morgan Stanley Technology, Media & Telecom Conference, March 2, 2026, third-party transcript. Dallas 12: 67 MW divided by about 3,700 announced cabinets, whether the megawatts are IT or facility load unstated, target Q2 2028; derived, not reported. Source: BTW Media's reading of Equinix filings and conference records, November 26, 2026. [1]*

## The ratepayer fight, now with Equinix on both sides

McGeady, who co-wrote a 2025 CSIS report calling electricity supply "the most acutely binding constraint" on US computing, sits on the December 1 panel "The Data Center Power Crisis and Ratepayer Protection" [4]. Beside him is Tashia Roberson-Wing, a senior legislative assistant to Rep. Greg Landsman, D-Ohio [5]. Her boss's [No Harm Data Centers Act](https://broadbandbreakfast.com/rep-greg-landsman-wants-federal-rules-on-data-center-power-costs/) would give the Federal Energy Regulatory Commission sole authority over retail rates for data centers above 50 megawatts, at rates covering the full cost of grid and generation upgrades, with utilities barred from shifting those costs to other customers [5][7].

The House passed the milder version, asking states only to consider such a standard above 100 megawatts, 417 to 3 in September; Senate Democrats blocked it [6][7]. [Equinix's facilities typically run 30 to 60 megawatts](https://www.cnbc.com/2026/11/06/equinix-us-data-center-growth-asia.html), so Landsman's 50 megawatt line would catch its upper range and the House's 100 would not [8].

*Chart: **Landsman's 50 MW line cuts through Equinix's 30 to 60 MW sites; the House's 100 MW does not** Range chart of megawatt thresholds: Equinix facilities typically run 30 to 60 MW, Rep. Greg Landsman's bill sets FERC authority above 50 MW, and the House-passed version asks states to consider a 100 MW standard.*

*Megawatts. Equinix facilities typically run 30 to 60 MW. Landsman's No Harm Data Centers Act would give FERC sole authority over retail rates for data centers above 50 MW; the House-passed version asks states only to consider a standard above 100 MW. A single value is drawn as a flat range. Sources: CNBC, November 6, 2026; Broadband Breakfast, November 28 and 29, 2026. [8][5][7]*

## In Georgia, Equinix already pays the whole grid cost

Since August, Equinix has been under [a 20-year take-or-pay contract](https://www.aol.com/articles/equinix-partners-central-georgia-electric-120100000.html) with Central Georgia Electric Membership Corporation covering all grid infrastructure costs at its Hampton, Georgia project, tied to the White House's Ratepayer Protection Pledge [9][4]. [The industry's trade group told Congress its members already pay full cost of service](https://broadbandbreakfast.com/data-center-coalitions-josh-levi-manages-a-new-political-reality/), and the E3 review it commissioned found no historical evidence of higher residential bills while tying about half of PJM's capacity price rise to data center load [10].

## A promise priced in megawatts, audited in cabinets

With no megawatt printed for the 255-site estate, nobody outside Equinix can say what Hampton-style funding would cost across the fleet, or how much of the 93,000 unbilled cabinet equivalents sits dark because power, not demand, said no [1].

The backlash is arriving anyway: voters backed data center restrictions in 40 of 41 local ballot measures across 10 states this month, a single-outlet count [11], and Cincinnati has restricted new data centers through February 2027 while drafting permanent zoning rules [7]. [Equinix's record quarter](https://theinference.org/article/equinix-s-record-quarter-ran-on-3-8-billion-of-new-debt-and-a-2-billion-stock-shelf), with annualized gross bookings exceeding $500 million for the first time, up 35% year over year, says scarcity is pricing in its favor despite the politics [8].

Watch the December 1 panel, Landsman's bill in the Democratic House arriving in January [10], and, if the next 10-K is filed in February on last year's schedule, whether it prints the column the constraint lives in.

## Takeaway

Equinix's own filings say power, not space, limits its data centers, yet the estate is reported only in cabinets, so no outsider can price its pledge that households will not carry grid costs.

## Sources

1. [BTW Media, Equinix says power limits its data centres. Its books count cabinets, 26 November 2026](https://btw.media/en/equinix-power-is-the-limit-its-numbers-count-space)
2. [Computer Weekly, Power now the binding constraint on AI datacentres, 26 November 2026](https://www.computerweekly.com/news/366655535/Power-now-the-binding-constraint-on-AI-datacentres)
3. [StartupHub.ai, Equinix CEO bets inference rewrites data centers, 25 November 2026](https://www.startuphub.ai/ai-news/artificial-intelligence/2026/equinix-ceo-bets-inference-rewrites-data-centers)
4. [Broadband Breakfast, Equinix's Cy McGeady, Who Called Power AI's Binding Constraint, Joins Ratepayer Fights, 28 November 2026](https://broadbandbreakfast.com/equinixs-cy-mcgeady-who-called-power-ais-binding-constraint-joins-ratepayer-fights/)
5. [Broadband Breakfast, Tashia Roberson-Wing, a Landsman Aide, Speaks for Making Data Center Grid Upgrades, 28 November 2026](https://broadbandbreakfast.com/tashia-roberson-wing-a-landsman-aide-speaks-for-making-data-center-grid-upgrades/)
6. [Broadband Breakfast, NARUC's Tony Clark Guards State Rate Authority as Democrats Weigh Federal Data Center Pricing, 28 November 2026](https://broadbandbreakfast.com/narucs-tony-clark-guards-state-rate-authority-as-democrats-weigh-federal-data-center-pricing/)
7. [Broadband Breakfast, Rep. Greg Landsman Wants Federal Rules on Data Center Power Costs, 29 November 2026](https://broadbandbreakfast.com/rep-greg-landsman-wants-federal-rules-on-data-center-power-costs/)
8. [CNBC, Equinix points to smaller facilities as scrutiny of U.S. data center construction grows, 6 November 2026](https://www.cnbc.com/2026/11/06/equinix-us-data-center-growth-asia.html)
9. [Equinix press release via PR Newswire, Equinix Partners with Central Georgia Electric Membership Corporation to Protect Ratepayers, 6 August 2026](https://www.aol.com/articles/equinix-partners-central-georgia-electric-120100000.html)
10. [Broadband Breakfast, Data Center Coalition's Josh Levi Manages a New Political Reality, 28 November 2026](https://broadbandbreakfast.com/data-center-coalitions-josh-levi-manages-a-new-political-reality/)
11. [MarketBeat via Yahoo Finance, Why Equinix and Digital Realty Benefit From Data Center Zoning Battles, 15 November 2026](https://finance.yahoo.com/technology/articles/why-equinix-digital-realty-benefit-130000160.html)


---

Equinix says power limits its 255 data centers, then bills 299,300 cabinets — The Inference. Canonical: https://theinference.org/article/equinix-says-power-limits-its-255-data-centers-then-bills-299-300-cabinets