title: "FirstEnergy lifts capital plan to $38 billion after West Virginia approves gas plant"
description: "The approval came with a surcharge that bills West Virginia ratepayers while the plant is built, and FirstEnergy answered by lifting its five-year plan to $38 billion, its growth target to 7% to 9%, and its equity ask to $2.8 billion. No large-load customer is named in the filing."
publisher: "The Inference"
section: "Power"
published: 2026-11-20T16:12:44.646Z
modified: 2026-11-20T16:12:44.646Z
canonical: https://theinference.org/article/firstenergy-lifts-capital-plan-to-38-billion-after-west-virginia-approves-gas-plant
language: en
keywords: "FirstEnergy, West Virginia, Utilities, Data Centers, Power Plants"
---

# FirstEnergy lifts capital plan to $38 billion after West Virginia approves gas plant

> The approval came with a surcharge that bills West Virginia ratepayers while the plant is built, and FirstEnergy answered by lifting its five-year plan to $38 billion, its growth target to 7% to 9%, and its equity ask to $2.8 billion. No large-load customer is named in the filing.

[FirstEnergy](https://theinference.org/markets/companies/firstenergy)'s filing this morning answers who pays when AI needs a power plant: shareholders first, West Virginia ratepayers second. A [Form 8-K dated November 20](https://www.sec.gov/Archives/edgar/data/1031296/000103129626000148/0001031296-26-000148-index.htm) raises the utility's five-year capital plan from $36 billion to $38 billion, after state regulators approved its 1,200-megawatt Maidsville Energy Center gas plant beside the Fort Martin coal station near Morgantown [1]. The same document lifts FirstEnergy's core earnings growth target for 2026-2030 to 7% to 9%, aiming at the upper half, up from 6% to 8% [1][2].

Shareholders' part of the bill is explicit: the equity FirstEnergy expects to issue through 2030 rises from $2.0 billion to $2.8 billion [1]. About 35% of the plant itself will be funded with equity or equity-like securities [1]. Ratepayers' part starts sooner, under a new generation surcharge [the order created to recover financing costs during construction](https://wvmetronews.com/2026/11/17/state-public-service-commission-approves-2-48-billion-natural-gas-plant-project-at-fort-martin-in-monongalia-county/), an initial $1.18 a month on a residential bill [1][3].

*Chart: **Capex has topped operating cash in nine of the last ten quarters** Line chart of FirstEnergy quarterly capital spending against operating cash flow from mid-2024 to the third quarter of 2026, showing capex above cash flow in nine of ten quarters*

*FirstEnergy capital spending and operating cash flow by quarter, Q2 2024 to Q3 2026, in $ billions, from its SEC filings. The Maidsville plant is not in these figures: site work begins in the first quarter of 2027. [7]*

## The surcharge is what turned a plant into a growth story

The certificate was the expected part; the surcharge is the mechanism. It lets Mon Power and Potomac Edison collect the cost of financing the $2.48 billion plant in cash while it is being built, rather than after it enters service at the end of 2031 [1][4]. Rate base compounds during construction, site work starts in the first quarter of next year, and FirstEnergy is asking the Department of Energy for a low-cost loan to soften the bill [1]. This is the company's first new plant since 1972, proposed in February against a projected capacity shortage that begins in 2029 [4].

*Chart: **Maidsville added $2 billion of capex and $800 million of equity** Column chart comparing FirstEnergy's February 2026 five-year capital plan and equity needs with the plan raised on November 20, 2026*

*FirstEnergy's 2026-2030 capital plan and the equity it expects to issue, as given in February 2026 and as raised in the November 20, 2026 Form 8-K after the November 17 West Virginia order. $ billions. [1]*

## The bill lands on people who did not ask for the plant

The plant is sized to power roughly half a million homes [6]. Mon Power serves about 395,000 customers [6]. Emmett Pepper of Energy Efficient West Virginia says no cost belongs on residential bills for a plant built for data centers, and United Mine Workers president Brian Sanson calls the approval a blank check drawn on working families so out-of-state billionaires can power their data centers [5]. FirstEnergy's West Virginia president Chris Beam says the power will be sold to the utilities' own customers, with turbines already secured under [a reservation agreement that locked delivery dates](https://wvmetronews.com/2026/11/19/construction-on-firstenergys-2-48-billion-natural-gas-plant-solar-projects-expected-to-start-next-year/) [5].

## The only missing signature is the customer's

No large-load customer appears anywhere in the filing, and the November 17 order has not changed what we noted on [November 2](https://theinference.org/article/firstenergy-reserved-siemens-turbines-for-a-2-7-billion-plant-whose-customer-has-not-signed), when the turbines were reserved and the buyer was not [1]. The order does allow contracts with new large loads structured so other customers do not subsidize them, and FirstEnergy has issued a request for proposals for another 3 gigawatts of gas, with an update due early next year [1].

The state has signed its half of this contract. The customer has not signed the other half. Building the plant is right: AI's demand for electricity is real, and the shortage on the other side of 2029 is a grid study, not a lobbying slide [4].

But a growth target resting on a surcharge and a turbine reservation, with no named buyer, puts risk in the wrong hands: ratepayers carry the surcharge, shareholders carry the dilution, and the load that justifies both has committed to nothing. Whoever turns this capacity into a signed contract is creating the value, and that signature, promised as an early-2027 update, is the thing to watch [1].

## Takeaway

West Virginia's new surcharge makes ratepayers fund the $2.48 billion Maidsville gas plant while it is built; FirstEnergy answers with a $38 billion capital plan and $2.8 billion of equity, and still names no large-load customer.

## Sources

1. [FirstEnergy Corp Form 8-K and Exhibit 99.1 investor presentation, filed with the SEC, 20 November 2026](https://www.sec.gov/Archives/edgar/data/1031296/000103129626000148/0001031296-26-000148-index.htm)
2. [Reuters, FirstEnergy lifts capex plan to $38 billion, lifts outlook for earnings growth, 20 November 2026](https://www.reuters.com/legal/litigation/firstenergy-lifts-capex-plan-38-billion-lifts-outlook-earnings-growth-2026-11-20/)
3. [WV MetroNews, State Public Service Commission approves $2.48 billion natural gas plant project at Fort Martin in Monongalia County, 17 November 2026](https://wvmetronews.com/2026/11/17/state-public-service-commission-approves-2-48-billion-natural-gas-plant-project-at-fort-martin-in-monongalia-county/)
4. [The Inter-Mountain, Mon Power/Potomac Edison plan for gas-fired plant in Maidsville approved, 18 November 2026](https://www.theintermountain.com/news/local-news/2026/11/mon-power-potomac-edison-plan-for-gas-fired-plant-in-maidsville-approved/)
5. [WV MetroNews, Construction on FirstEnergy's $2.48 billion natural gas plant, solar projects expected to start next year, 19 November 2026](https://wvmetronews.com/2026/11/19/construction-on-firstenergys-2-48-billion-natural-gas-plant-solar-projects-expected-to-start-next-year/)
6. [Mon Power and Potomac Edison press release via PR Newswire (Yahoo Finance), Mon Power and Potomac Edison Select Maidsville, West Virginia, Site for New Natural Gas Power Plant, 13 February 2026](https://finance.yahoo.com/news/mon-power-potomac-edison-select-213600207.html)
7. [FirstEnergy, quarterly figures from its SEC filings, retrieved 20 November 2026](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0001031296)


---

FirstEnergy lifts capital plan to $38 billion after West Virginia approves gas plant — The Inference. Canonical: https://theinference.org/article/firstenergy-lifts-capital-plan-to-38-billion-after-west-virginia-approves-gas-plant