title: "Legrand puts data centers at 32% of revenue just as Thailand asks 49 data-center builds to pause"
description: "The French group's Southeast Asia chief put numbers on its AI exposure: data centers are about a third of revenue and close to €3 billion a year, just as Thailand and Singapore start rationing the power and water new builds need."
publisher: "The Inference"
section: "Data Center"
published: 2026-11-17T00:03:29.113Z
modified: 2026-11-17T00:03:29.113Z
canonical: https://theinference.org/article/legrand-puts-data-centers-at-32-of-revenue-just-as-thailand-asks-49-data-center-builds-to-pause
language: en
keywords: "Legrand, Data Centers, Thailand, Malaysia, Southeast Asia"
---

# Legrand puts data centers at 32% of revenue just as Thailand asks 49 data-center builds to pause

> The French group's Southeast Asia chief put numbers on its AI exposure: data centers are about a third of revenue and close to €3 billion a year, just as Thailand and Singapore start rationing the power and water new builds need.

[Legrand](https://theinference.org/markets/companies/legrand), the French electrical-equipment maker, has put hard numbers on the business investors price as an AI story. Karine Alquier-Caro, the group's area vice-president for Southeast Asia, said data centers now account for about 32% of group revenue, approaching €3 billion a year, and that Malaysian sales have climbed from roughly €20 million in 2023 to around €300 million [1].

## A third of revenue rides one end market

The [nine-month results published on November 5](https://www.legrand.com/en/investors-and-shareholders/capital-markets-days/capital-markets-day-2026) show what that exposure buys: revenue of €8.3 billion, up 22% excluding currency, split between 12.7% organic growth and 8.3% from acquisitions, with net profit up 19.6% and chief executive Benoît Coquart putting data-center growth close to 40% organic [2][3][4]. Much of it was bought: seven acquisitions this year include Malaysia's SRS Power Engineering in May and the US data-center power specialist Girtz Industries in June [2][3]. Legrand lifted its 2026 organic-growth target to 11–13% from 8–10% [4], extending the guidance raise [covered here on November 13](https://theinference.org/article/legrand-raises-2026-outlook-again-to-11-13-organic-growth-as-data-centers-grow-near-40).

*Chart: **Data centers grew about three times as fast as the group** Bar chart of nine-month sales growth to September 2026: data centers about 40% organic, group organic 12.7%, group total including acquisitions 22%*

*Nine months to September 30, 2026, year-on-year sales growth. The data-center bar is chief executive Benoît Coquart's "close to 40%" organic figure, so it is marked as an estimate; the group bars are as reported. Source: Actualité Business, November 5, 2026. [2]*

## The constraint is power and water

The same region is now rationing the buildout. Thailand [asked 49 data centers under construction to pause](https://www.techrepublic.com/article/news-data-center-pause-apac-thailand/), a request regulators have no power to enforce, and [held approval decisions on 117 more](https://theinference.org/article/thailand-paused-data-center-approvals-delta-electronics-chose-penang-and-its-taipei-shares-fell-9-8), about 166 projects in all [6][7].

On November 10 the cabinet [set the standards new builds must meet](https://www.msn.com/en-ph/money/general/thailand-sets-noise-water-use-limits-for-data-centers/ar-AA2h7MQO): noise capped at 70 decibels at the site boundary, recirculated cooling water, and centers above 20 megawatts confined to industrial zones [8]. Much of the queue behind them may never be built: more than 110 applicants sought over 30,000 megawatts of power, and officials judged a quarter or fewer to have genuine plans [8].

## Singapore rations, Johor builds

Singapore, constrained by land and power, added just 95 megawatts between 2023 and 2026 and has become a retrofit market where operators upgrade as tenants move, Alquier-Caro said [1][6]. In Johor, next door, data centers already draw 24% of the state's electricity [6].

*Chart: **Johor's pipeline is nearly triple the capacity it has running** Bar chart of data-center capacity in Johor, Malaysia: 94MW operational in 2023, 1,110MW operational in 2026 and 3,088MW under construction or planned*

*Johor, Malaysia data-center capacity: operational in 2023 and 2026, plus capacity under construction or planned, per Cushman & Wakefield data reported November 7, 2026. Source: The Guardian. [6]*

## The offset sells into scarcity

About 40% of Legrand's data-center sales are equipment that cuts energy and water use, kit the company says can move PUE, total energy divided by computing energy, from around 1.6 toward 1 [1].

The bull case prices the same scarcity: UBS, which [upgraded the stock to buy on November 9 with a €170 target](https://www.ideal-investisseur.fr/en/stock-news/legrand-among-the-biggest-gainers-on-the-cac-40-after-ubs-upgrade/29169.html), expects data centers to add about 14 points to group growth in 2027, and cites an 8% discount to Schneider Electric and ABB, its two big European rivals, with bolt-ons bought at about 11 times forward EBITA, earnings before interest, tax and amortization [4][5].

That discount, against a pipeline now partly written by regulators, is a case to hold rather than chase. Legrand does not yet split retrofit from new-build orders; the annual results due on February 9 are the first place to look [5].

## Takeaway

Data centers are now about a third of Legrand's revenue and growing near 40% organic, but the Southeast Asian buildout feeding them is being rationed on power and water.

## Sources

1. [Orixanews, Southeast Asia emerges as important market for Legrand, 16 November 2026](https://orixanews.com/southeast-asia-emerges-as-important-market-for-legrand/)
2. [Actualité Business, Legrand relève ses objectifs après un bond de 22 % de ses ventes, 5 November 2026](https://actualite-business.fr/article/legrand-neuf-mois-2026-centres-donnees-record/)
3. [Legrand, Capital Markets Day 2026 investor page (nine-month 2026 release summary), accessed 16 November 2026](https://www.legrand.com/en/investors-and-shareholders/capital-markets-days/capital-markets-day-2026)
4. [Ideal Investisseur, Legrand Among the Biggest Gainers on the CAC 40 After UBS Upgrade, 11 November 2026](https://www.ideal-investisseur.fr/en/stock-news/legrand-among-the-biggest-gainers-on-the-cac-40-after-ubs-upgrade/29169.html)
5. [MarketScreener, Legrand benefits from prospects for data center acceleration in 2027, UBS says, 9 November 2026](https://www.marketscreener.com/news/legrand-benefits-from-prospects-for-data-center-acceleration-in-2027-ubs-says-ce785fd3db8ffe27)
6. [The Guardian, The datacentre arms race hits pause in south-east Asia, 7 November 2026](https://www.theguardian.com/technology/2026/nov/07/datacentres-southeast-asia)
7. [TechRepublic, Thailand Asks 49 Data Centers to Pause as New Power and Water Rules Loom, 10 September 2026](https://www.techrepublic.com/article/news-data-center-pause-apac-thailand/)
8. [Agence France-Presse via The Manila Times, Thailand sets noise, water-use limits for data centers, 10 November 2026](https://www.msn.com/en-ph/money/general/thailand-sets-noise-water-use-limits-for-data-centers/ar-AA2h7MQO)


---