title: "Louisiana defers Entergy's private grid hearing for Meta to Dec. 16 as a $12.9 billion gas-plant vote nears"
description: "The same December docket now holds a consultant's verdict on Entergy's next rate increase, a hearing on the private grid serving Meta, and the vote on $12.9 billion of gas plants. Whose money carries it moves ETR shareholders and Louisiana ratepayers alike."
publisher: "The Inference"
section: "Power"
published: 2026-11-19T16:53:15.077Z
modified: 2026-11-19T16:53:15.077Z
canonical: https://theinference.org/article/louisiana-defers-entergy-s-private-grid-hearing-for-meta-to-dec-16-as-a-12-9-billion-gas-plant-vote-nears
language: en
keywords: "Entergy, Meta, Louisiana, Utilities, Data Centers, Power Plants"
---

# Louisiana defers Entergy's private grid hearing for Meta to Dec. 16 as a $12.9 billion gas-plant vote nears

> The same December docket now holds a consultant's verdict on Entergy's next rate increase, a hearing on the private grid serving Meta, and the vote on $12.9 billion of gas plants. Whose money carries it moves ETR shareholders and Louisiana ratepayers alike.

Louisiana's Public Service Commission approved [Entergy](https://theinference.org/markets/companies/entergy)'s (NYSE: ETR) [application to review a potential rate increase](https://www.wbrz.com/news/entergy-s-application-to-review-potential-rate-increase-approved-by-louisiana-public-service-commission) on Nov. 18, a vote to hire an outside consultant to judge whether an increase, through a Formula Rate Plan extension or a full rate review, is "sustainable [1]." No rates changed. [1] The same meeting deferred, to Dec. 16 in Shreveport, the hearing on "private use electrical networks" to serve new large loads, the docket covering [Meta](https://theinference.org/markets/companies/meta)'s northwest Louisiana data center. [1]

That pairing is what is new since [The Inference last took up Entergy's Meta math](https://theinference.org/article/entergy-tells-louisiana-regulators-its-meta-deal-may-not-save-customers-a-penny-amid-a-33-billion-buildout): both cost questions, the rate one and the private-network one, are now open at once, in the same month the commission is set to vote on the gas plants. [8][2]

## Twelve point nine billion for seven gas plants

Entergy plans about $12.9 billion for seven combined-cycle gas plants totaling 5,278 megawatts, plus a $1.4 billion transmission line and 200 megawatts of batteries, to serve Meta's $50 billion Hyperion campus in Richland Parish. [2][5] With the three plants the commission approved in August 2025, the count reaches ten and roughly 7.5 gigawatts. [3] The fuel is reserved: [firm pipeline contracts covering 1.325 billion cubic feet a day](https://morningoverview.com/entergy-signed-gas-supply-deals-to-run-10-new-power-plants-in-louisiana/), which CEO Drew Marsh told analysts is enough for ten new combined cycles. [2]

*Chart: **Meta's Louisiana build dwarfs the $470 million so far pinned to ratepayers** Bars comparing $12.9 billion for seven gas plants, $1.4 billion for a transmission line and $470 million as the minimum ratepayer share.*

*Entergy's planned spend on generation and transmission for Meta's Hyperion campus, against the minimum ratepayer-funded share of Meta-related infrastructure under Entergy's Louisiana PSC application as reported in June 2025. Planned figures are company projections, not approved costs. Units: billions of US dollars. Sources: Utility Dive, Nov. 5, 2026; WWNO/Gulf States Newsroom, Nov. 12, 2026. [2][4]*

![Entergy's Ninemile 6 combined-cycle gas unit lit at dusk near New Orleans, with transmission lines overhead](https://storage.googleapis.com/theinference-public/img/eb5d0c77c6a65224.jpg)

*Entergy's 560-megawatt Ninemile 6 combined-cycle gas unit near Westwego, Louisiana. The utility wants approval for seven more combined cycles, 5,278 megawatts, to serve Meta's Hyperion campus. (Chad Davis)*

Commission staff have settled the outstanding issues in the contested case, and the vote is expected this month. [2] The quarter behind the ask was strong: [earnings of $1.98 a share against $1.53 a year earlier](https://www.sec.gov/Archives/edgar/data/7323/000006598426000322/earningsrelease3q26_ex991.htm), and a capital plan of about $55 billion through 2030. [7]

*Chart: **Entergy's capital spending has outrun operating cash flow every year since 2020** Column chart of Entergy capital spending against operating cash flow, fiscal 2020 to 2025, showing capital spending above operating cash flow in every year.*

*Entergy's capital spending and cash from operations, fiscal years 2020 to 2025. Capital spending exceeded operating cash flow in all six years, and the gap widened to $2.8 billion in 2025, the year before the $55 billion plan through 2030. Units: billions of US dollars, as reported. Source: Entergy quarterly and annual figures from its SEC filings, retrieved Nov. 19, 2026. [9]*

## Ratepayers carry at least $470 million of it

Under Entergy's application, Meta, filing as Evest LLC, would pay for 2,500 megawatts of new renewables and storage and fund billions in substations and upgrades, but ratepayers carry at least $470 million, including the nearly 58-mile, 500-kilovolt Mount Olive-to-Sarepta line. [2][4] To secure that line's path, Entergy [sued 14 Lincoln Parish landowners](https://theinference.org/article/who-pays-for-the-ai-grid-arkansas-wants-money-back-louisiana-families-want-their-land) on Oct [4]. 14 for servitudes, Louisiana's version of easements, arguing the project serves a public purpose. [4]

On Nov. 9, three landowner groups [sued the commission itself](https://www.ktbs.com/news/louisiana-groups-sue-public-service-commission-over-fast-track-approval-for-meta-power-projects/article_8a844ca4-def7-42ae-9e2a-d32154444306.html), claiming its Lightning Directive fast track, adopted 4-1 in December 2025, skipped required public notice; consumer advocates note the White House ratepayer-protection pledges for the project carry no binding force. [5][6]

## Marsh will not promise flat rates

Marsh has told investors Meta helps offset Louisiana costs but will not necessarily hold rates flat the way Google's deal does in Arkansas. [2] If the Dec. 16 hearing lets Meta's money carry the dedicated network while the ratepayer share stays contained, the $55 billion build has a funding path that does not fight the rate review [1]. If it does not, the plants and the bills collide in front of the same commission that deferred the hearing. [1]

## Takeaway

December decides whether Meta's money or Louisiana ratepayers carry the $12.9 billion build.

## Sources

1. [WBRZ, Entergy's application to review potential rate increase approved by Louisiana Public Service Commission, Nov. 18, 2026](https://www.wbrz.com/news/entergy-s-application-to-review-potential-rate-increase-approved-by-louisiana-public-service-commission)
2. [Utility Dive, Entergy sees progress on Arkansas data center deal, strong Q3 sales, Nov. 5, 2026](https://www.utilitydive.com/news/entergy-makes-progress-on-arkansas-data-center-reports-strong-q3-sales/873873/)
3. [Morning Overview, Entergy signed gas supply deals to run 10 new power plants in Louisiana, Nov. 9, 2026](https://morningoverview.com/entergy-signed-gas-supply-deals-to-run-10-new-power-plants-in-louisiana/)
4. [WWNO / Gulf States Newsroom, Entergy says Meta power lines serve 'public purpose' in Lincoln Parish land rights lawsuit, Nov. 12, 2026](https://www.wwno.org/economy/2026-11-12/entergy-says-meta-power-lines-serve-public-purpose-in-lincoln-parish-land-rights-lawsuit)
5. [KTBS / Louisiana Illuminator, Louisiana groups sue Public Service Commission over fast-track approval for Meta power projects, Nov. 9, 2026](https://www.ktbs.com/news/louisiana-groups-sue-public-service-commission-over-fast-track-approval-for-meta-power-projects/article_8a844ca4-def7-42ae-9e2a-d32154444306.html)
6. [WWNO / Gulf States Newsroom, Entergy wants their land for Meta's power lines. They're suing the regulators approving them, Nov. 9, 2026](https://www.wwno.org/economy/2026-11-09/entergy-wants-their-land-for-metas-power-lines-theyre-suing-the-regulators-approving-them)
7. [Entergy Corporation, third quarter 2026 earnings release, SEC Form 8-K Exhibit 99.1, Nov. 2, 2026](https://www.sec.gov/Archives/edgar/data/7323/000006598426000322/earningsrelease3q26_ex991.htm)
8. [The Inference, Entergy tells Louisiana regulators its Meta deal may not save customers a penny, amid a $33 billion buildout, Nov. 11, 2026](https://theinference.com/article/entergy-tells-louisiana-regulators-its-meta-deal-may-not-save-customers-a-penny-amid-a-33-billion-buildout)
9. [Entergy, annual figures from its SEC filings, retrieved 19 November 2026](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0000065984)


---

Louisiana defers Entergy's private grid hearing for Meta to Dec. 16 as a $12.9 billion gas-plant vote nears — The Inference. Canonical: https://theinference.org/article/louisiana-defers-entergy-s-private-grid-hearing-for-meta-to-dec-16-as-a-12-9-billion-gas-plant-vote-nears