title: "Oracle Bought the Option to Pay Late. Bloom and Blue Owl Carry the 2028 Date"
description: "Oracle filed contract language on 24 September that lets it defer payments if Project Jupiter misses its 2028 online date, then reaffirmed the 2.4-gigawatt order that notice hedged against. Five sessions of tape show who underwrites the date."
publisher: "The Inference"
section: "Data Center"
published: 2026-09-30T19:35:02.818Z
modified: 2026-09-30T19:35:02.818Z
canonical: https://theinference.org/article/oracle-bought-the-option-to-pay-late-bloom-and-blue-owl-carry-the-2028-date
language: en
keywords: "Oracle, Bloom Energy, Blue Owl, Data Centers, Project Finance"
---

# Oracle Bought the Option to Pay Late. Bloom and Blue Owl Carry the 2028 Date

> Oracle filed contract language on 24 September that lets it defer payments if Project Jupiter misses its 2028 online date, then reaffirmed the 2.4-gigawatt order that notice hedged against. Five sessions of tape show who underwrites the date.

## The marker: Bloom gets the week back in one session

[Bloom Energy](https://theinference.org/markets/companies/bloom-energy) rose as much as 13% on 29 September after [Oracle](https://theinference.org/markets/companies/oracle) [reaffirmed the 2.4-gigawatt fuel-cell order](https://coincentral.com/bloom-energy-be-stock-surges-13-after-oracle-reaffirms-project-jupiter-deal/) behind Project Jupiter, the AI campus rising near Santa Teresa, New Mexico [1][5]. The session also credited a second document: Bloom has [taken another 158,000 square feet in Fremont](https://seekingalpha.com/news/4648132-bloom-energy-stock-gains-on-factory-expansion-fuel-cell-demand-outlook), California, nearly the size of the 164,000-square-foot plant it already runs there [2]. Oracle, whose reassurance did the lifting, slipped about 1% on the day it delivered it [3].

## The rewind: one notice, five sessions

On 24 September Oracle [sent a force majeure notice](https://finance.yahoo.com/technology/ai/articles/oracle-sends-force-majeure-notice-233200891.html) to Blue Owl Capital, owner of the builder Stack Infrastructure, preserving the right to defer payments if the campus is not online in 2028 as planned [5]. Oracle closed down 3.5% with its credit default swaps at a record, Blue Owl fell 3.6%, and Bloom dropped as much as 7% [8][5][7]. [Arm](https://theinference.org/markets/companies/arm) fell about 7% to near $305.50 on read-through alone: its architecture sits under Oracle's cloud processors, and a deferred campus defers the CPU demand meant to fill it [6].

Roughly $18 billion of construction loans on the campus were already quoted at 89 to 91 cents on the dollar [5]. Bloom recovered 8.7% on 25 September after [saying Oracle "remains committed" to the 2.4 gigawatts](https://finance.yahoo.com/markets/stocks/articles/bloom-energy-8-7-oracle-220801648.html) [4]. On 28 September it gave that back, down 8.7% as the notice revived financing concerns and the loans were quoted below 90 cents [9].

*Chart: **Oracle's paperwork moved its suppliers; Oracle itself barely moved** Column chart of one-day share price moves on Project Jupiter news, each bar marked close or intraday: on 24 September Oracle closed down 3.5% while Arm and Bloom fell 7% intraday on the force majeure notice; on 25 September Bloom closed up 8.7% while Oracle slipped 1% intraday; on 28 September Bloom closed down 8.7%; on 29 September Bloom rose 13% intraday on the reaffirmation.*

*One-day share price moves in percent as reported each session; (close) marks reported closing moves and (intraday) marks moves reported as session extremes. Arm holds no Jupiter contract; it trades on read-through demand for data-center CPUs. [1][3][4][5][6][7][8][9]*

## The pattern: the option sits with Oracle, the date with everyone else

The notice is routine for Oracle and load-bearing for everyone else. [A filing bought the right to pay late](https://theinference.org/article/oracle-moves-to-defer-the-rent-on-a-data-center-it-says-is-on-schedule); Bloom's order book, Blue Owl's buildings and the desks holding $18 billion of loans all sit on 2028 holding. The schedule rests on permits none of them controls.

New Mexico's environment department has [until 23 November to rule on the air permit](https://www.enr.com/articles/63720-oracle-invokes-force-majeure-as-new-mexico-project-jupiter-power-work-faces-hurdles) for the 2,462-megawatt fuel-cell microgrid, which cannot begin construction without it [10]. The gas line feeding the cells has slipped from August to February 2027, and federal regulators have not yet authorized building it [10]. In July the microgrid's developer told the state it stood to lose $325 million a month beginning in November [10].

## The counterweight: everyone says nothing changed

Oracle calls such notices commonplace on projects of this scale, saying they "do not, by themselves, establish a project delay" [10]. Stack says the companies remain "fully aligned" and the notice "does not change the financial commitments" [5]. Bloom declined to answer questions about the microgrid's construction status and commissioning schedule, referring to a social media statement [10]. The statements address intent. The permits decide the date.

## The fork: 23 November prices 2028

If the permit lands and gas flows by early 2027, the notice stays paperwork and lenders get repaid at par. If either slips, Oracle's deferral right activates against the same counterparties that just spent five days trading on its reassurance, and $325 million a month becomes someone's income statement. The next hard reading on 2028 is a state ruling due 23 November [10].

## Takeaway

Oracle's force majeure notice bought the right to defer payments if Project Jupiter misses 2028; the reaffirmed 2.4-gigawatt order leaves Bloom, Blue Owl and $18 billion of construction loans waiting on a New Mexico air permit due 23 November.

## Sources

1. [CoinCentral, "Bloom Energy (BE) Stock Surges 13% After Oracle Reaffirms Project Jupiter Deal", 29 September 2026](https://coincentral.com/bloom-energy-be-stock-surges-13-after-oracle-reaffirms-project-jupiter-deal/)
2. [Seeking Alpha, "Bloom Energy stock gains on factory expansion, fuel-cell demand outlook", 29 September 2026](https://seekingalpha.com/news/4648132-bloom-energy-stock-gains-on-factory-expansion-fuel-cell-demand-outlook)
3. [24/7 Wall St, "Bloom Energy Jumps 8% as Oracle Reaffirms 2.4 GW Fuel Cell Contract After Force Majeure Notice", 25 September 2026](https://247wallst.com/investing/2026/09/25/bloom-energy-jumps-8-as-oracle-reaffirms-2-4-gw-fuel-cell-contract-after-force-majeure-notice/)
4. [Simply Wall St via Yahoo Finance, "Bloom Energy (BE) Is Up 8.7% After Oracle Reaffirms 2.4 GW AI Fuel Cell Deal Commitment", 25 September 2026](https://finance.yahoo.com/markets/stocks/articles/bloom-energy-8-7-oracle-220801648.html)
5. [The Santa Fe New Mexican via Yahoo Finance, "Oracle sends 'force majeure' notice to Project Jupiter developers to protect itself from liability", 24 September 2026](https://finance.yahoo.com/technology/ai/articles/oracle-sends-force-majeure-notice-233200891.html)
6. [Kobaran, "ARM Stock Slides 7% Toward $300 After Oracle Force Majeure Notice on Project Jupiter", 24 September 2026](https://www.kobaran.com/arm-stock-slides-7-toward-300-after-oracle-force-majeure-notice-on-project-jupiter/)
7. [Blockonomi, "Bloom Energy (BE) Stock Tumbles 7% Following Oracle's Force Majeure Notice on Project Jupiter", 24 September 2026](https://blockonomi.com/bloom-energy-be-stock-tumbles-7-following-oracles-force-majeure-notice-on-project-jupiter/)
8. [The Motley Fool, "Stock Market Today, Sept. 24: Oracle Stock Dips As it Issues Force Majeure Notice on Project Jupiter Data Center", 24 September 2026](https://www.fool.com/coverage/stock-market-today/2026/09/24/stock-market-today-sept-24-oracle-stock-dips-as-it-issues-force-majeure-notice-on-project-jupiter-data-center/)
9. [StockStory via Yahoo Finance, "Why Bloom Energy (BE) Shares Are Sliding Today", 28 September 2026](https://finance.yahoo.com/markets/stocks/articles/why-bloom-energy-shares-sliding-000636170.html)
10. [Engineering News-Record, "Oracle Invokes Force Majeure as New Mexico Project Jupiter Power Work Faces Hurdles", 28 September 2026](https://www.enr.com/articles/63720-oracle-invokes-force-majeure-as-new-mexico-project-jupiter-power-work-faces-hurdles)


---

Oracle Bought the Option to Pay Late. Bloom and Blue Owl Carry the 2028 Date — The Inference. Canonical: https://theinference.org/article/oracle-bought-the-option-to-pay-late-bloom-and-blue-owl-carry-the-2028-date