title: "Oracle Moves to Defer the Rent on a Data Center It Says Is On Schedule"
description: "Oracle's force majeure notice on Project Jupiter defers its rent if the New Mexico campus misses its 2028 opening. The $18 billion of loans behind the site already trade below 90 cents, and they cannot be repaid until the campus opens."
publisher: "The Inference"
section: "Data Center"
published: 2026-09-27T21:22:05.877Z
modified: 2026-09-27T21:22:05.877Z
canonical: https://theinference.org/article/oracle-moves-to-defer-the-rent-on-a-data-center-it-says-is-on-schedule
language: en
keywords: "Oracle, Data Centers, Stargate, Project Jupiter, New Mexico"
---

# Oracle Moves to Defer the Rent on a Data Center It Says Is On Schedule

> Oracle's force majeure notice on Project Jupiter defers its rent if the New Mexico campus misses its 2028 opening. The $18 billion of loans behind the site already trade below 90 cents, and they cannot be repaid until the campus opens.

## The notice moves the bill one seat down the table

[Oracle](https://theinference.org/markets/companies/oracle) sent a [force majeure notice](https://www.msn.com/en-us/money/markets/oracle-sends-force-majeure-notice-about-data-center-project-stock-sinks-7/ar-AA2cT7I7) on 24 September to the developer of Project Jupiter, the Stargate campus in Doña Ana County, New Mexico [2][4]. The ask is simple: if the campus misses its planned 2028 opening, Oracle's rent does not start [1]. If the rent never starts, what happens to the lenders?

The developer, STACK Infrastructure, is a Blue Owl Capital unit, and the $18 billion of loans behind the site were already [quoted at 89 to 91 cents on the dollar](https://financefeeds.com/oracle-debt-project-jupiter-loans-90-cents-bonds-85/) [4][3]. That is the lending leg of the stack charted in The Inference's *Oracle's $664 Billion Backlog Runs on Three Balance Sheets*, taking its first mark-to-market hit [4]. Oracle's own quarter explains the reflex: $28.5 billion of capital spending against negative $5.4 billion of free cash flow in the quarter to 31 August [5].

*Chart: **Oracle's capex has outrun its free cash flow for four straight quarters** Column chart of Oracle's quarterly capital spending versus free cash flow from the quarter ended November 2025 to the quarter ended August 2026; capital spending rises from 12 billion to 28.5 billion dollars while free cash flow stays negative in all four quarters.*

*Oracle capital spending and free cash flow by calendar quarter, in billions of US dollars; labels are calendar quarters, with the quarter to 31 August 2026 being Oracle's fiscal first quarter of 2027. Source: Sharadar quarterly fundamentals from Oracle's SEC filings. [11]*

## The power still has no permit

The site's power plan has been rebuilt once already. New Mexico's land commissioner [rejected the feeding pipeline's right-of-way](https://www.gearlive.com/news/article/oracle-force-majeure-new-mexico-stargate-project-jupiter) in March and again in July, which forced a switch from 2.2 gigawatts of gas turbines to 2.45 gigawatts of [Bloom Energy](https://theinference.org/markets/companies/bloom-energy) fuel cells [6][4]. The cells still need gas, and earliest pipeline service has slipped to 1 February 2027 [6].

The site also lacks the air permit for the fuel cells themselves. The New Mexico Supreme Court paused that process on 23 August while it weighs two challenges from environmental groups, and the state must rule by 23 November [4][7]. Oracle wrote itself aggressive commitments with little wiggle room on this campus [8]. Force majeure is the wiggle.

## Every date has already slipped

The Financial Times puts the build at least seven months late. [SemiAnalysis](https://theinference.org/markets/companies/semianalysis) moves the first phase from 2027 to 2029, and state officials say nothing opens before 2030 [3]. A power-related force majeure event could win Oracle up to three years of rent deferral, back rent still owed later, and until completion STACK collects no rent at all [6][3]. The market marked the whole chain in one morning, hardest at the far end:

*Chart: **The further from the tenant, the harder the fall** Bar chart of reported one-day share-price falls for Oracle, Blue Owl and Bloom Energy after the Project Jupiter force majeure report; Bloom fell hardest at 6 percent, Blue Owl 4, Oracle 3.5.*

*Reported one-day share-price moves after the 24 September 2026 Project Jupiter force majeure report; percent change. Sources: Yahoo Finance, Gear Live, Blockonomi, Seeking Alpha. [3][6][9][10]*

Oracle is [down 28.6 percent this year](https://blockonomi.com/oracle-orcl-stock-plunges-3-6-amid-18-billion-project-jupiter-debt-concerns/), the worst tech stock in the S&P 500 [9][3].

## Both sides insist this is routine

"Project Jupiter remains on our planned schedule," Oracle says, pointing to 3,600 workers on site [1][6]. Blue Owl's line: the notice "does not change the financial commitments to this multi-year project" [1]. Bloom says it stays committed to the contract and the timeline [1].

The loan price has a calmer reading: Oracle's own bonds fair-value near 84.6 cents, so project loans at 89 to 91 price the campus roughly where its tenant is priced [4]. The tell lands on 23 November: grant the air permit and the loans have a path back toward par; deny it and 2028 stops being a schedule. New Mexico keeps saying no, and Wall Street holds the paper.

## Takeaway

Oracle's force majeure notice shifts the delay risk on Project Jupiter to developer STACK and its lenders, whose $18 billion of loans cannot be repaid until the campus opens. The next tell is New Mexico's air permit ruling on 23 November.

## Sources

1. [CNBC via MSN (Samantha Subin), "Oracle sends 'force majeure' notice about data center project, stock drops 3%", 24 September 2026](https://www.msn.com/en-us/money/markets/oracle-sends-force-majeure-notice-about-data-center-project-stock-sinks-7/ar-AA2cT7I7)
2. [Quartz via Yahoo Finance (Cris Tolomia), "Oracle invokes force majeure on New Mexico AI data center", 24 September 2026](https://finance.yahoo.com/technology/ai/articles/oracle-invokes-force-majeure-mexico-141727376.html)
3. [Yahoo Finance (Colin Harper), "Inside Oracle's delays at $165B Project Jupiter data center", 25 September 2026](https://finance.yahoo.com/technology/articles/inside-oracle-8217-delays-165b-231001464.html)
4. [FinanceFeeds (Tobi Opeyemi Amure), "Oracle Debt: Jupiter Loans at 90 Cents, Its Own Bonds at 85", 21 September 2026](https://financefeeds.com/oracle-debt-project-jupiter-loans-90-cents-bonds-85/)
5. [Sharadar quarterly fundamentals from Oracle's SEC filings, retrieved 27 September 2026](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0001341439)
6. [Gear Live (Andru Edwards), "Oracle Says Its New Mexico Stargate Site Is On Schedule. It Filed to Delay the Rent Anyway.", 25 September 2026](https://www.gearlive.com/news/article/oracle-force-majeure-new-mexico-stargate-project-jupiter)
7. [SiliconANGLE (Mike Wheatley), "Oracle issues 'force majeure' notice to New Mexico data center developer on energy delays", 24 September 2026](https://siliconangle.com/2026/09/24/oracle-issues-force-majeure-notice-to-developer-of-new-mexico-data-center-over-energy-delays/)
8. [The Wall Street Journal (Rudegeair, Gardizy, Wirz), "Cracks in Oracle's AI Data-Center Build-Out Appear in Massive New Mexico Project", 25 September 2026](https://www.wsj.com/finance/investing/cracks-in-oracles-ai-data-center-build-out-appear-in-massive-new-mexico-project-effb51c2)
9. [Blockonomi, "Oracle (ORCL) Stock Plunges 3.6% Amid $18 Billion Project Jupiter Debt Concerns", 25 September 2026](https://blockonomi.com/oracle-orcl-stock-plunges-3-6-amid-18-billion-project-jupiter-debt-concerns/)
10. [Seeking Alpha (Carl Surran), "Bloom Energy slides on reported Oracle data center force majeure", 24 September 2026](https://seekingalpha.com/news/4646631-bloom-energy-slides-on-reported-oracle-data-center-force-majeure)
11. [Sharadar quarterly fundamentals, from Oracle's SEC filings, retrieved 27 September 2026](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0001341439)


---

Oracle Moves to Defer the Rent on a Data Center It Says Is On Schedule — The Inference. Canonical: https://theinference.org/article/oracle-moves-to-defer-the-rent-on-a-data-center-it-says-is-on-schedule