title: "Oracle's two ledgers: a $27 billion subpoena file and a $664 billion backlog"
description: "The Senate Veterans' Affairs Committee's minority set an October 23 deadline for the files behind a VA health-record contract whose ceiling jumped from $10 billion to about $27 billion. The same week, Oracle stock rose on OpenAI's near-$70 billion run rate, the customer behind almost half its $664 billion backlog."
publisher: "The Inference"
section: "Policy & Labor"
published: 2026-09-30T19:35:52.623Z
modified: 2026-09-30T19:35:52.623Z
canonical: https://theinference.org/article/oracle-s-two-ledgers-a-27-billion-subpoena-file-and-a-664-billion-backlog
language: en
keywords: "Oracle, Government Contracts, AI Infrastructure, Debt, OpenAI, Subpoenas"
---

# Oracle's two ledgers: a $27 billion subpoena file and a $664 billion backlog

> The Senate Veterans' Affairs Committee's minority set an October 23 deadline for the files behind a VA health-record contract whose ceiling jumped from $10 billion to about $27 billion. The same week, Oracle stock rose on OpenAI's near-$70 billion run rate, the customer behind almost half its $664 billion backlog.

Seven Senate Veterans' Affairs Committee members, led by Richard Blumenthal, have given [Oracle](https://theinference.org/markets/companies/oracle)'s Larry Ellison and Mike Sicilia [until October 23 to hand over the files behind the VA electronic health record contract](https://www.veterans.senate.gov/2026/9/blumenthal-committee-minority-back-up-house-subpoenas-demand-answers-from-larry-ellison-on-ballooning-costs-of-oracle-s-va-electronic-health-record-contract). The no-bid contract's ceiling moved from $10 billion to about $27 billion [1][2].

The senators want Oracle's internal lifecycle cost projections through 2031, a full itemization of the "unanticipated complexities" behind the increase, and a reconciliation with Sicilia's 2022 Senate pledge to deliver the system "without exceeding the contracted cost" [1][2]. They also want to know why Congress heard about the ceiling jump from reporters before it heard from Oracle or the VA [1].

## A 19-0 vote against a broken fixed-price promise

Oracle accepted, then declined, the invitation to the House Veterans' Affairs Committee's September 2 hearing, citing time constraints; the panel [voted 19-0 to subpoena both executives](https://www.nextgov.com/modernization/2026/09/house-panel-subpoenas-oracle-heads-over-va-health-record-overhauls-ballooning-costs/415791/), now scheduled to testify in November and December [2][3][4]. VA Deputy Secretary Paul Lawrence [could not say what drove the $17 billion increase](https://www.yahoo.com/news/politics/articles/va-said-electronic-health-record-004933091.html) [3]. Lawmakers also cited roughly 300 dermatology patients whose referrals were canceled after go-lives, some with cancer diagnoses, and GAO counts 14 of its 18 program recommendations still not fully implemented [3][4].

## The ceiling tripled; full-program estimates run near $50 billion

The $27 billion is a ceiling, not a check: work is negotiated beneath it on a time-and-materials basis [3]. VA's own arithmetic points higher, about $37 billion to deploy through 2031 plus $11 billion to sustain, roughly $48 billion, not, Lawrence conceded, an independent estimate [3]. The Institute for Defense Analyses put lifecycle cost at $49.8 billion in 2022 [1]. Contract filings say VA hit its ceiling "sooner than originally planned," [after weighing Epic, Veradigm, Athenahealth and Meditech and finding "no other source than Oracle"](https://fedscoop.com/bipartisan-backlash-27-billion-va-oracle-ehrm-contract/) [4].

*Chart: **The VA ceiling nearly tripled to $27 billion; full-program estimates sit near $50 billion** Bar chart comparing the VA EHRM contract ceiling with deployment and lifecycle cost estimates*

*VA Electronic Health Record Modernization contract ceiling and cost estimates, USD billions. The last three bars are estimates, not obligations: VA's stated figures through 2031 and the Institute for Defense Analyses' 2022 lifecycle estimate. Sources: [1][3][4]. [1][3][4]*

## Half the backlog rides on one customer, with no published conversion schedule

Oracle stock rose 4.27% on September 29 after a report that [OpenAI](https://theinference.org/markets/companies/openai)'s [annualized revenue run rate neared $70 billion](https://finance.yahoo.com/markets/stocks/articles/openai-q3-2026-revenue-run-171727199.html), with enterprise sales more than doubling since July [5][6]. Roughly $300 billion of Oracle's $664 billion backlog, [about 45%, rides on that one customer](https://financefeeds.com/oracle-664-billion-backlog-and-18-billion-in-debt/) [7]. In the material available, Oracle has published no maturity schedule for how much of that backlog converts in which quarter [8].

## Oracle calls it routine; its lenders price it otherwise

Oracle calls the week's darker headline routine: force majeure notices are "commonplace," "Project Jupiter remains on our planned schedule," and Oracle Health's Seema Verma says the company "remains committed" to the VA build [9][4].

The lease behind Jupiter is hell-or-high-water, though, and the notice defers full rent for up to three years on a campus carrying $18 billion of bank construction loans [9]. [One arranger has sold that paper below 90 cents](https://www.msn.com/en-us/news/other/cracks-in-oracle-s-ai-data-center-build-out-appear-in-massive-new-mexico-project/ar-AA2cWIuq), a loss of at least $1.8 billion, and S&P holds Oracle at BBB-, one notch above junk, citing AI infrastructure risk [9][7].

Quarterly capital spending, $28.5 billion in the August quarter, has now passed quarterly revenue twice this year [10].

*Chart: **Capital spending caught quarterly revenue this year, then passed it** Line chart of Oracle quarterly revenue and capital expenditure over 12 quarters*

*Oracle quarterly revenue and capital expenditure, USD billions, by calendar quarter; Oracle's fiscal year ends in May, so the final label (August 2026) is fiscal Q1 2027. Source: [10], Sharadar quarterly fundamentals from Oracle's SEC filings. [10]*

## The markers are dated, and they are close

Oracle's answer to a fixed-price promise was a bigger ceiling; its answer to a hell-or-high-water lease was a force majeure notice. If slippage gets absorbed that way, [the counterparties holding $664 billion of cloud contracts](https://theinference.org/article/openai-s-1-2-trillion-round-pays-the-vendors-first), and the syndicates financing the buildings, own the other side of the trade. Documents are due October 23, Sicilia testifies in November, Ellison in December, and December's quarterly results give the first hard read on whether the backlog converts [1][4][7].

## Takeaway

Oracle spent the week defending two balance sheets at once: a VA contract whose ceiling tripled to $27 billion under subpoena threat, and an AI backlog that is half one customer and financed on paper rated one notch above junk.

## Sources

1. [U.S. Senate Committee on Veterans' Affairs, "Blumenthal, Committee Minority Back Up House Subpoenas, Demand Answers from Larry Ellison on Ballooning Costs of Oracle's VA Electronic Health Record Contract," 29 September 2026](https://www.veterans.senate.gov/2026/9/blumenthal-committee-minority-back-up-house-subpoenas-demand-answers-from-larry-ellison-on-ballooning-costs-of-oracle-s-va-electronic-health-record-contract)
2. [Nextgov/FCW, "House panel subpoenas Oracle heads over VA health record overhaul's ballooning costs," 2 September 2026](https://www.nextgov.com/modernization/2026/09/house-panel-subpoenas-oracle-heads-over-va-health-record-overhauls-ballooning-costs/415791/)
3. [Yahoo News, "VA said electronic health record modernization would cost $10 billion, now it's $48 billion," 2 September 2026](https://www.yahoo.com/news/politics/articles/va-said-electronic-health-record-004933091.html)
4. [FedScoop, "Inside the bipartisan backlash to the $27 billion VA-Oracle EHRM contract blindsiding Congress," 21 September 2026](https://fedscoop.com/bipartisan-backlash-27-billion-va-oracle-ehrm-contract/)
5. [Investor's Business Daily via Yahoo Finance, "OpenAI Revenue Growth Report Boosts Oracle Stock; DevDay On Deck," 29 September 2026](https://finance.yahoo.com/m/a859e3cf-b549-3c8b-938f-746e974e0e16/openai-revenue-growth-report.html)
6. [Quartz via Yahoo Finance, "OpenAI Q3 2026 revenue run rate nears $70 billion," 29 September 2026](https://finance.yahoo.com/markets/stocks/articles/openai-q3-2026-revenue-run-171727199.html)
7. [FinanceFeeds, "Oracle's $664 Billion Backlog and $18 Billion in Debt the Market Won't Price at Par," 25 September 2026](https://financefeeds.com/oracle-664-billion-backlog-and-18-billion-in-debt/)
8. [btw.media, "Oracle Cloud AI build-out: $664bn contracted vs 850MW delivered," 2026](https://btw.media/en/oracle-cloud-ai-capacity-delivery-gap)
9. [The Wall Street Journal via MSN, "Cracks in Oracle's AI data-center build-out appear in massive New Mexico project," 25 September 2026](https://www.msn.com/en-us/news/other/cracks-in-oracle-s-ai-data-center-build-out-appear-in-massive-new-mexico-project/ar-AA2cWIuq)
10. [Sharadar quarterly fundamentals from Oracle's SEC filings, retrieved 30 September 2026](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0001341439)


---

Oracle's two ledgers: a $27 billion subpoena file and a $664 billion backlog — The Inference. Canonical: https://theinference.org/article/oracle-s-two-ledgers-a-27-billion-subpoena-file-and-a-664-billion-backlog