title: "PPL paid $9.9 million for a Lancaster farm to wire a data center; 1.5 million customers may share the bill"
description: "A 143-acre Pequea Township purchase anchors 16.4 miles of new wires feeding the Lancaster AI Hub East project. Who pays for the shared parts, the data center's owners or the utility's 1.5 million customers, now sits with Pennsylvania regulators, and the governor has asked to join the case."
publisher: "The Inference"
section: "Power"
published: 2026-11-17T18:13:51.636Z
modified: 2026-11-17T18:13:51.636Z
canonical: https://theinference.org/article/ppl-paid-9-9-million-for-a-lancaster-farm-to-wire-a-data-center-1-5-million-customers-may-share-the-bill
language: en
keywords: "PPL, Data Centers, Utilities, Pennsylvania, Regulation"
---

# PPL paid $9.9 million for a Lancaster farm to wire a data center; 1.5 million customers may share the bill

> A 143-acre Pequea Township purchase anchors 16.4 miles of new wires feeding the Lancaster AI Hub East project. Who pays for the shared parts, the data center's owners or the utility's 1.5 million customers, now sits with Pennsylvania regulators, and the governor has asked to join the case.

## The Herrs preferred a substation to a housing development

The Herr family has farmed at 133 Sprecher Road in Pequea Township since the late 1800s [1]. This month the family sold the 143 acres to [PPL Electric Utilities](https://theinference.org/markets/companies/ppl), which delivers power to about 1.5 million homes and businesses in eastern and central Pennsylvania, for $9.9 million [1][2][4]. Who ultimately repays that price, the data center the new wires will feed or the utility's other customers, is the question PPL says it is too early to answer [1].

The sale lets the Herrs keep farming the land. They had wanted to sell for years and preferred a substation to a housing development [1]. "We thought it was probably in the best interest of the community," co-owner Dennis Herr said [1].

## The new wire serves a data center and replaces 1950s lines

PPL will build the substation on part of the farm, anchoring 16.4 miles of new and rebuilt transmission east and south of Lancaster city, constructed in 2028 and 2029, with approval from the Pennsylvania Public Utility Commission sought next year [1][3]. The lines connect to the Lancaster AI Hub East data center on Greenfield Road, whose owners expect to spend $200 million on grid upgrades at the site [1][3]. The same project replaces wires installed in the 1950s and 1960s for everyone on the system [1][3].

## The cost split has a precedent next door

PPL's rule is that data-center customers must pay for facilities and upgrades required solely for their operations [1][3]. On how this project divides, spokesperson Dana Burns said it is too early to discuss allocations [1]. The corridor already shows the pattern: a $36.4 million switchyard PPL is building beside the data center puts $21.3 million on the large-load customer and $14.9 million on the utility and its customers, as PUC Chairman Stephen DeFrank noted when the commission approved it in August [3]. About 60 percent customer, the rest shared [3].

## A rider and a governor's petition will decide it

On September 14, PPL [filed a Customer Protection Transmission Rider](https://dailyenergyinsider.com/news/53765-new-customer-protection-rider-proposed-by-ppl-electric-in-pennsylvania/), which would assign certain transmission upgrade costs directly to the large-load rate class and take effect in the first quarter of 2028 if approved [4]. Governor Josh Shapiro petitioned on October 16 to [join the related case over PPL Electric's rates](https://theinference.org/article/shapiro-asks-to-join-ppl-s-rate-case-so-data-centers-pay-their-own-way-on-31-8-gigawatts), the first governor to intervene in a PUC hearing in at least 15 years by his office's count: "Pennsylvanians should not be left paying higher electric bills because of data center developers" [5].

## PPL says the rider adds no new charge

PPL answers that it holds Pennsylvania's only commission-approved large-load tariff and that the rider adds no new charge [4][5]. The backdrop is real: households paid 17.11 cents per kilowatt-hour in 2025, up from 15.60, and [state regulators project PPL's industrial demand, almost entirely data centers, growing about 51 percent a year through 2030](https://www.pennlive.com/news/2026/09/how-much-power-will-pas-data-centers-need-by-2030-state-regulators-give-new-projections.html) [6].

## The queue is 35 gigawatts deep, the live load 300 megawatts

[PPL's Pennsylvania data-center pipeline grew for an 11th straight quarter to 35.3 gigawatts in advanced planning](https://theinference.org/article/ppl-s-31-8-gw-pipeline-in-advanced-planning-waits-on-a-transmission-tariff-plan-update-november-6): 11.4 gigawatts under signed agreements, 8.5 under construction, and 300 megawatts actually energized [7][8]. Behind it sits [a $25 billion regulated capital plan for 2027 through 2030](https://www.utilitydive.com/news/ppl-increases-capital-plan-to-25b-with-proposed-kentucky-gas-plant/874129/), up $2 billion and largely a 645-megawatt Kentucky gas unit, lifting the earnings growth target to 7 to 9 percent a year [7][9].

*Chart: **PPL's Pennsylvania data center queue narrows to 300 megawatts live** Bars showing PPL Electric's Pennsylvania data center load by stage: 35.3 gigawatts in advanced planning, 11.4 gigawatts under signed agreements, 8.5 gigawatts under construction and 0.3 gigawatts energized*

*Gigawatts of data center load in PPL Electric's Pennsylvania territory by stage, third quarter 2026. Each stage is a subset of the one before it: the 35.3 GW in advanced planning includes the 11.4 GW signed, which includes the 8.5 GW under construction, which includes the 300 MW energized. Sources: PPL Q3 2026 earnings release; Telecom Gazette. [7][8]*

The money is already moving: quarterly capital spending ran from a third above to more than triple year-earlier levels across 2026 [10].

*Chart: **PPL's quarterly capital spending has stepped up ahead of the $25B plan** Column chart of PPL quarterly capital expenditure from the fourth quarter of 2023 to the third quarter of 2026, rising from about 0.2 billion dollars in early 2024 to 1.2 billion in the third quarter of 2026, with seasonal fourth-quarter peaks near 2 to 3 billion*

*Capital expenditures in billions of dollars per quarter, from PPL's SEC filings; fourth-quarter peaks are seasonal. Source: PPL Corporation quarterly figures from its SEC filings. [10]*

Two decisions will settle who pays for the Herrs' fields: the commission's ruling on the rider, and PPL's 2027 filing to approve the substation itself. If the rider stands with its allocation language, the large-load rate class carries the upgrade costs and the buildout funds itself. If the commission reads a substation that also replaces 1950s equipment as a shared cost, the utility's 1.5 million customers repay their share through rates.

## Takeaway

PPL paid $9.9 million for 143 acres of Lancaster County farmland to anchor 16.4 miles of new transmission for the Lancaster AI Hub East, and Pennsylvania regulators now decide whether that data center or PPL's other 1.5 million customers repay the shared upgrades.

## Sources

1. [LNP | LancasterOnline, "PPL acquires 143-acre Pequea Twp. farm for substation in $9.9M deal," 16 November 2026](https://lancasteronline.com/news/local/ppl-acquires-143-acre-pequea-twp-farm-for-substation-in-9-9m-deal/article_5939666b-fae7-455c-a759-0a6082471763.html)
2. [LNP | LancasterOnline, "PPL buys property in Pequea Twp. for $9.9M: Lancaster County deeds recorded, Nov. 16, 2026," 16 November 2026](https://lancasteronline.com/business/deeds/ppl-buys-property-in-pequea-twp-for-9-9m-lancaster-county-deeds-recorded-nov-16/article_fa44a32d-1cd4-48d5-8b33-a56820103fcd.html)
3. [LNP | LancasterOnline, "Open House Tuesday for PPL upgrades near Lancaster city data center," 5 October 2026](https://lancasteronline.com/news/local/open-house-tuesday-for-ppl-upgrades-near-lancaster-city-data-center/article_1e713a88-2912-4a76-af0d-8305457468a0.html)
4. [Daily Energy Insider, "New customer protection rider proposed by PPL Electric in Pennsylvania," 10 November 2026](https://dailyenergyinsider.com/news/53765-new-customer-protection-rider-proposed-by-ppl-electric-in-pennsylvania/)
5. [abc27 (WHTM Harrisburg), "Shapiro seeks to join case against PPL, citing potential cost increases caused by data centers," 16 October 2026](https://www.abc27.com/pennsylvania-politics/shapiro-seeks-to-join-case-against-ppl-citing-potential-cost-increases-caused-by-data-centers/)
6. [PennLive / The Patriot-News, "How much power will Pa.'s data centers need by 2030? State regulators give new projections," 6 September 2026](https://www.pennlive.com/news/2026/09/how-much-power-will-pas-data-centers-need-by-2030-state-regulators-give-new-projections.html)
7. [PPL Corporation earnings release via PR Newswire (Yahoo Finance), "PPL Corporation Delivers Strong Third-Quarter 2026 Earnings; Raises Long-Term EPS Growth Outlook," 6 November 2026](https://finance.yahoo.com/markets/stocks/articles/ppl-corporation-delivers-strong-third-122900400.html)
8. [Telecom Gazette, "PPL's Pennsylvania data center pipeline hits 35.3GW as QTS deal firms up," 16 November 2026](https://telecomgazette.com/articles/ppl-s-pennsylvania-data-center-pipeline-hits-35-3gw-as-qts-deal-firms-up)
9. [Utility Dive, "PPL increases capital plan to $25B with proposed Kentucky gas plant," 9 November 2026](https://www.utilitydive.com/news/ppl-increases-capital-plan-to-25b-with-proposed-kentucky-gas-plant/874129/)
10. [PPL Corporation quarterly figures from its SEC filings (EDGAR), retrieved 17 November 2026](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0000922224)


---

PPL paid $9.9 million for a Lancaster farm to wire a data center; 1.5 million customers may share the bill — The Inference. Canonical: https://theinference.org/article/ppl-paid-9-9-million-for-a-lancaster-farm-to-wire-a-data-center-1-5-million-customers-may-share-the-bill