title: "Quanta Computer's third Bloom Energy order, $367 million, lifts its fuel-cell total to about $950 million"
description: "Quanta's third fuel-cell order in 25 months takes the AI-server assembler's disclosed own-power commitments to about $950 million, roughly three-quarters of the capital budget it has set for 2027."
publisher: "The Inference"
section: "Power"
published: 2026-11-26T17:12:38.591Z
modified: 2026-11-26T17:12:38.591Z
canonical: https://theinference.org/article/quanta-computer-s-third-bloom-energy-order-367-million-lifts-its-fuel-cell-total-to-about-950-million
language: en
keywords: "Quanta Computer, Bloom Energy, Fuel Cells, AI Servers, Data Center Power"
---

# Quanta Computer's third Bloom Energy order, $367 million, lifts its fuel-cell total to about $950 million

> Quanta's third fuel-cell order in 25 months takes the AI-server assembler's disclosed own-power commitments to about $950 million, roughly three-quarters of the capital budget it has set for 2027.

## A third order, a week after a Tennessee lease

On November 25, 2026 Quanta Manufacturing Nashville, the US subsidiary of [Quanta Computer](https://theinference.org/markets/companies/quanta-computer) (2382.TW), a Taiwanese contract manufacturer [3], [disclosed a $367 million purchase of fuel-cell microgrid systems](https://econotimes.com/Quanta-Announces-About-367-Million-in-U-S-Fuel-Cell-Microgrid-Purchases-1780711), which generate electricity on site, from [Bloom Energy](https://theinference.org/markets/companies/bloom-energy), a fuel-cell maker [1][2]. About $249.9 million covers its California operations and $117.1 million Tennessee, technical services included [1]. Quanta's investor page [lists the filing as a machinery acquisition on behalf of a subsidiary](https://www.quantatw.com/quanta/english/default.aspx) [4]. On November 18 the same unit leased a 252,072-square-foot building in La Vergne, Tennessee, for 62 months at about $14.9 million [5].

## Three orders now equal three-quarters of the 2027 budget

Two earlier purchases sit behind this one: $79.75 million in October 2024, and $502 million on December 30, 2025, for the B16, B18 and B19 buildings in California [1][2]. Together the three orders come to about $950 million [1].

*Chart: **Quanta's three Bloom Energy fuel-cell orders total about $950 million in 25 months** Column chart of Quanta's three Bloom Energy fuel-cell purchases: $79.75 million in October 2024, $502 million in December 2025 and $367 million in November 2026.*

*Disclosed purchase values in US$ millions by Quanta Manufacturing Nashville, as reported November 26, 2026 (sum $948.75 million); the December 2025 order covered the B16, B18 and B19 buildings in California. Sources [1], [2]. [1][2]*

At the November 26, 2026, rate of 32.9 New Taiwan dollars to the US dollar [6], that is roughly NT$31 billion. Quanta's 2027 capital budget is NT$40 to 45 billion, after NT$34.6 billion spent in the first nine months of 2026, nearly 80 percent of it in California and Thailand [1]. The purchases are disclosed; no filing says how the systems are booked, whether that budget already holds them, or when payment falls due.

## Record revenue, a gross margin down to 4.75 percent

[Quanta's November 11 results](https://www.ad-hoc-news.de/boerse/news/nebenwerte/quanta-aktie-umsatz-springt-im-dritten-quartal-um-125-2-prozent/70545264) showed third-quarter revenue of NT$1.12 trillion, up 125.2 percent from a year earlier, and net profit of NT$28.42 billion, up 73 percent [7]. Gross margin fell to 4.75 percent from 5.02 percent in the second quarter and 6.85 percent a year earlier [3], a slide Quanta attributed to product mix and more customer-specified components [7]. Servers were over 80 percent of revenue and are guided to 85 to 90 percent in 2027 [7][3]. Operating profit still rose 75.3 percent to NT$32.2 billion [3]. [The Inference covered that quarter on November 12](https://theinference.org/article/quanta-computer-revenue-rose-125-to-nt-1-12-trillion-as-it-seeks-to-shift-inventory-to-ai-customers) [8].

## Denser racks mean more power inside the factory

At its November 11 earnings call Quanta said denser AI racks draw more power and need more testing inside the plant, and that customers' AI road maps run two years out [2]. [DigiTimes reported the next day](https://www.digitimes.com/news/a20261112PD243/quanta-2027-capex-ai-server-revenue.html) that Quanta is steering its 2027 capital budget toward power, "the new battleground for AI server ODMs" [9]. A reason like that suggests the power constraint that data centers have been meeting with on-site generation [10] has reached the factory that builds their racks. Quanta's shareholders carry that cost from a 4.75 percent gross margin [3].

## Quanta's cost is 30 percent of Bloom's record quarter

For Bloom Energy (NYSE: BE), the San Jose fuel-cell maker, the order is about 30 percent of its [record $1.24 billion third-quarter revenue](https://www.sec.gov/Archives/edgar/data/1664703/000162828026066890/be-20261022.htm) [10][11]. It follows a [900 megawatt agreement with the data-center operator NTT DATA](https://finance.yahoo.com/markets/stocks/articles/bloom-energy-signs-largest-deal-063837088.html), signed on November 5 [10][12], and Bloom raised its 2026 revenue guidance to $4.4 to 4.6 billion on October 22 [11]. [Morgan Stanley](https://theinference.org/markets/companies/morgan-stanley) kept an Overweight rating and a $335 target on Bloom on November 24, counting more than 2.8 gigawatts of deployment opportunities since late September [13][14], [a note The Inference covered on November 25](https://theinference.org/article/bloom-energy-locks-123-million-of-outsourced-fuel-cell-supply-through-2027-in-a-korean-filing) [15].

![Four black Bloom Energy Server cabinets in a blue-lit display room](https://storage.googleapis.com/theinference-public/img/d5f80174884a7d6e.jpg)

*Bloom Energy servers, the on-site generators Quanta Manufacturing Nashville ordered for its California and Tennessee sites. Bloom's third-quarter revenue of $1.24 billion was a record. (Bloom Energy)*

*Chart: **Bloom's revenue has more than doubled in a year, to a record $1.24 billion** Line chart of Bloom Energy quarterly revenue from Q2 2024 to Q3 2026, rising from $0.34 billion to a record $1.24 billion*

*Bloom Energy revenue by quarter, in US$ billions, from its SEC filings. The third quarter of 2026, at $1.236 billion, is the record against which Quanta's $367 million order is measured. Source [16]. [16]*

## Capex against margin decides 2027

Watch whether Foxconn, Wistron and Inventec, which compete with Quanta for the same AI-server design wins [8], file their own power purchases, and how fast Bloom's fourth-quarter report, expected in February [12], turns the $367 million into revenue. The test for Quanta is whether 2027 capital spending overshoots NT$45 billion while gross margin holds above 4.75 percent as [Nvidia](https://theinference.org/markets/companies/nvidia)'s next-generation Vera Rubin racks ramp in the first quarter of 2027 [8].

## Takeaway

Three Bloom Energy orders in 25 months now come to about $950 million, roughly three-quarters of the NT$40 to 45 billion Quanta has budgeted for 2027, and at a 4.75 percent gross margin the AI-server assembler pays for its own power out of a thin slice of profit.

## Sources

1. [EconoTimes, "Quanta Announces About $367 Million in U.S. Fuel-Cell Microgrid Purchases", 26 November 2026](https://econotimes.com/Quanta-Announces-About-367-Million-in-U-S-Fuel-Cell-Microgrid-Purchases-1780711)
2. [TokenPost, "Quanta Announces $367 Million Fuel-Cell Microgrid Purchases", 26 November 2026](https://www.tokenpost.com/news/business/62709)
3. [Crypto Briefing, "Quanta Computer posts record revenue as AI servers squeeze gross margin to 4.75%", 11 November 2026](https://cryptobriefing.com/quanta-computer-record-revenue-ai-servers-margin/)
4. [Quanta Computer investor site, News list: "2026.11.25 Announcing Machinery and Equipment Acquisition on Behalf of Subsidiary"; "2026.11.18 Announcing the Acquisition of Right-of-Use Assets", accessed 26 November 2026](https://www.quantatw.com/quanta/english/default.aspx)
5. [ad-hoc-news, "Quanta Computer stock: Tennessee lease adds US$14.9 million commitment", 25 November 2026](https://www.ad-hoc-news.de/boerse/news/nebenwerte/quanta-computer-stock-tennessee-lease-adds-us-14-9-million-commitment/70551099)
6. [Yahoo Finance, USD/TWD (TWD=X) quote, 32.945 as of 26 November 2026](https://finance.yahoo.com/quote/TWD=X/)
7. [ad-hoc-news, "Quanta-Aktie: Umsatz springt im dritten Quartal um 125,2 Prozent", 25 November 2026](https://www.ad-hoc-news.de/boerse/news/nebenwerte/quanta-aktie-umsatz-springt-im-dritten-quartal-um-125-2-prozent/70545264)
8. [The Inference, "Quanta Computer revenue rose 125% to NT$1.12 trillion as it seeks to shift inventory to AI customers", 12 November 2026](https://theinference.org/article/quanta-computer-revenue-rose-125-to-nt-1-12-trillion-as-it-seeks-to-shift-inventory-to-ai-customers)
9. [DigiTimes, "Quanta shifts 2027 capex toward power, the new battleground for AI server ODMs", 12 November 2026 (headline and lede only; remainder paywalled)](https://www.digitimes.com/news/a20261112PD243/quanta-2027-capex-ai-server-revenue.html)
10. [ad-hoc-news, "Bloom Energy stock: Quanta unit orders $367 million of microgrids", 25 November 2026](https://www.ad-hoc-news.de/boerse/news/corporate-news/bloom-energy-stock-quanta-unit-orders-367-million-of-microgrids/70553728)
11. [Bloom Energy, SEC Form 8-K Exhibit 99.1, "Bloom Energy Reports Record Third Quarter 2026 Financial Results and Raises Full Year 2026 Guidance", filed 22 October 2026](https://www.sec.gov/Archives/edgar/data/1664703/000162828026066890/be-20261022.htm)
12. [Yahoo Finance (TIKR), "Bloom Energy Signs Its Largest Deal Abroad: 900 MW for NTT Data Starting in 2027", 24 November 2026](https://finance.yahoo.com/markets/stocks/articles/bloom-energy-signs-largest-deal-063837088.html)
13. [TradingView, "Key facts: Quanta Unit's $367M Deal; Morgan Stanley Keeps $335 Target", 26 November 2026](https://www.tradingview.com/news/tradingview:28362ed05fc33:0-key-facts-quanta-unit-s-367m-deal-morgan-stanley-keeps-335-target/)
14. [Stocktwits, "BE Stock Slumps After AI-Driven Gains: This Analyst Sees 'An Attractive Entry Point'" (Morgan Stanley note of 24 November 2026), 24 November 2026](https://stocktwits.com/news-articles/markets/equity/be-stock-slumps-after-ai-driven-gains-this-analyst-sees-an-attractive-entry-point/cNbHRamR9lQ)
15. [The Inference, "Bloom Energy locks $123 million of outsourced fuel-cell supply through 2027 in a Korean filing", 25 November 2026](https://theinference.org/article/bloom-energy-locks-123-million-of-outsourced-fuel-cell-supply-through-2027-in-a-korean-filing)
16. [Bloom Energy, quarterly figures from its SEC filings, retrieved 26 November 2026](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0001664703)


---

Quanta Computer's third Bloom Energy order, $367 million, lifts its fuel-cell total to about $950 million — The Inference. Canonical: https://theinference.org/article/quanta-computer-s-third-bloom-energy-order-367-million-lifts-its-fuel-cell-total-to-about-950-million