title: "Segra bet 22.5% of its fund on X-Energy. The prize is a fuel factory, not a permit"
description: "Segra Capital finished the third quarter holding $222 million of X-Energy, its biggest position, days after the NRC handed the first US small-reactor construction permit to a GE Vernova design. What the concentrated buyers own is the fuel chain: a licensed TRISO plant in Oak Ridge and a HALEU supply deal with Centrus."
publisher: "The Inference"
section: "Power"
published: 2026-10-07T23:14:30.702Z
modified: 2026-10-07T23:14:30.702Z
canonical: https://theinference.org/article/segra-bet-22-5-of-its-fund-on-x-energy-the-prize-is-a-fuel-factory-not-a-permit
language: en
keywords: "Nuclear, Energy, Markets, Hedge Funds"
---

# Segra bet 22.5% of its fund on X-Energy. The prize is a fuel factory, not a permit

> Segra Capital finished the third quarter holding $222 million of X-Energy, its biggest position, days after the NRC handed the first US small-reactor construction permit to a GE Vernova design. What the concentrated buyers own is the fuel chain: a licensed TRISO plant in Oak Ridge and a HALEU supply deal with Centrus.

## One fund has 22.5% of its book in a single reactor stock

Segra Capital Management bought 1,202,283 more shares of [X-Energy](https://theinference.org/markets/companies/x-energy) in the third quarter and finished holding 15,678,017, worth $222.3 million [1]. That is 3.86% of the company and 22.5% of Segra's portfolio, its biggest position [1]. [Filing arithmetic marks the stake at about $14.18 a share](https://www.marketbeat.com/instant-alerts/filing-segra-capital-management-llc-acquires-1202283-shares-of-x-energy-inc-xe-2026-10-06/), below the stock's $17.48 fifty-day average [1][2].

*Chart: **Segra's $222M stake dwarfs X-Energy's other recent 13F buyers** Bar chart of disclosed X-Energy institutional positions from 13F filings: Segra Capital at $222.3 million as of Q3 2026, Two Seas Capital at $19.8 million as of Q3 2026, State Street at $8.5 million as of Q2 2026, BlueCrest Capital at $7.4 million as of Q2 2026 and Tidal Investments at $3.3 million as of Q2 2026.*

*Disclosed X-Energy positions from 13F filings as reported by MarketBeat on October 6, 2026; each bar's as-of quarter is marked on its label. US$ millions. [1][2][5]*

Two Seas Capital lifted its own stake 39.4% to 1,394,413 shares, about $19.8 million [2]. A quarter earlier, [filings showed Peter Thiel's Thiel Macro buying 200,000 Class A shares](https://www.fool.com/investing/2026/08/28/palantir-billionaire-peter-thiel-just-put-33-of-hi/), the smallest line in a rebuilt $419 million book [3][4]. X-Energy rose 6.6% on October 6 to about $15.27, still 59% below its $37.10 twelve-month high, with Piper Sandler at $9 underweight against Guggenheim's $57 buy [5][2].

*Chart: **From $9 to $57: analyst targets bracket a $15.27 close** Column chart of six X-Energy share-price reference points in US dollars: Piper Sandler's $9 target, the $14.18 filing-implied cost, the $15.27 close of October 6, the $17.48 fifty-day average, the $37.10 twelve-month high and Guggenheim's $57 target.*

*X-Energy share-price reference points, US dollars per share. Filing basis is Segra's implied 13F cost; close, average and twelve-month high as reported by MarketBeat, October 6, 2026. Analyst targets are estimates. [1][2][5]*

## The first permit went elsewhere. The fuel line did not

On September 29 the Nuclear Regulatory Commission [issued the country's first small-reactor construction permit](https://www.rtoinsider.com/147009-nrc-authorizes-tva-build-1st-us-small-modular-reactor/), to the Tennessee Valley Authority for GE Vernova's 300-megawatt BWRX-300 at Clinch River, after a 14-month review [6][7]. NuScale holds the only NRC-certified SMR design, yet no utility has applied to build one, and it booked $75,000 of second-quarter revenue [6]. The tape prices these stocks by permits; this week's filings are pricing one by fuel.

X-Energy's TRISO-X unit [holds a 40-year NRC license to fabricate high-assay fuel](https://www.world-nuclear-news.org/articles/milestone-for-x-energys-triso-xs-fuel-facility), and on September 24 it finished the shell of the 214,000-square-foot TX-1 plant in Oak Ridge, set to be the first commercial-scale advanced nuclear fuel plant built in the United States in more than 50 years [8][9]. Interior build-out has begun, on the schedule the company laid out in August [10][13].

## One plant, 700,000 pebbles, eleven reactors

At capacity TX-1 is designed to produce about 700,000 pebbles a year, five tonnes of uranium, [enough for up to 11 of the company's 80-megawatt reactors](https://theinference.org/article/x-energy-s-fuel-plant-feeds-11-reactors-its-order-book-runs-to-144) [8][9]. Centrus [signed the definitive supply contract on August 6](https://www.morningstar.com/news/pr-newswire/20260806ph20576/centrus-energy-signs-leu-and-haleu-supply-agreement-with-x-energy), with X-Energy paying prepayments up the chain, while the supplier carries a $900 million DOE award, a $4.5 billion backlog and an Oklo deal on the same shelf [11][12].

![A hand holds a black graphite fuel pebble for a pebble-bed nuclear reactor, 60 millimetres across](https://storage.googleapis.com/theinference-public/img/2676edccadccf560.jpg)

*A graphite fuel pebble for a pebble-bed reactor, 60 millimetres across; at capacity TX-1 is designed to produce about 700,000 pebbles a year. (Weirdmeister)*

## The bill lands on this year's IPO cash

X-Energy's quarter shows who pays: [$54.6 million of revenue and grant income, up 154%, against a $105.3 million net loss](https://www.finanznachrichten.de/nachrichten-2026-08/69301650-x-energy-inc-x-energy-reports-second-quarter-2026-results-399.htm), funded by $1.9 billion of liquidity from an April IPO that raised about $1.1 billion, with no debt [13]. The Energy Information Administration prices SMR power at more than six times solar, and the only helium-cooled power reactors running, two in China, have struggled to stay online [14].

The permit queue decides who may build; the fuel line decides who gets to run. Watch the Dow project in Texas, the federal cost-share running to March 2027 [13], and whether TX-1's equipment keeps its 2028 completion date [14].

## Takeaway

The concentrated buyers own the fuel chain, not the permit: a 40-year-licensed TRISO plant in Oak Ridge and a Centrus HALEU deal, funded by $1.9 billion of IPO liquidity against a $105.3 million quarterly loss.

## Sources

1. [MarketBeat, Segra Capital Management LLC Acquires 1,202,283 Shares of X-Energy, Inc. $XE, 6 October 2026](https://www.marketbeat.com/instant-alerts/filing-segra-capital-management-llc-acquires-1202283-shares-of-x-energy-inc-xe-2026-10-06/)
2. [MarketBeat, Two Seas Capital LP Increases Position in X-Energy, Inc. $XE, 6 October 2026](https://www.marketbeat.com/instant-alerts/filing-two-seas-capital-lp-increases-position-in-x-energy-inc-xe-2026-10-06/)
3. [X, @topsecretstocks: Peter Thiel is betting on nuclear power, 4 October 2026](https://x.com/topsecretstocks/status/2106553787582456258)
4. [The Motley Fool, Palantir Billionaire Peter Thiel Just Put 33% of His Portfolio Into These 3 Energy Stocks, 28 August 2026](https://www.fool.com/investing/2026/08/28/palantir-billionaire-peter-thiel-just-put-33-of-hi/)
5. [MarketBeat, X-Energy (NASDAQ:XE) Shares Climb 6% - Here's Why, 6 October 2026](https://www.marketbeat.com/instant-alerts/price-x-energy-nasdaq-xe-shares-climb-6-heres-why-2026-10-06/)
6. [The Motley Fool via The Globe and Mail, Regulators Cleared a Small Modular Reactor for Construction. It Isn't a NuScale Design., 7 October 2026](https://www.theglobeandmail.com/investing/markets/stocks/GEV/pressreleases/4999151/regulators-cleared-a-small-modular-reactor-for-construction-it-isnt-a-nuscale-design/)
7. [RTO Insider, NRC Authorizes TVA to Build 1st U.S. Small Modular Reactor, 29 September 2026](https://www.rtoinsider.com/147009-nrc-authorizes-tva-build-1st-us-small-modular-reactor/)
8. [World Nuclear News, Milestone for X-Energy's TRISO-X fuel facility, 25 September 2026](https://www.world-nuclear-news.org/articles/milestone-for-x-energys-triso-xs-fuel-facility)
9. [Interesting Engineering, US nuclear fuel plant with 5-metric-ton uranium capacity moves closer to operations, 24 September 2026](https://interestingengineering.com/energy/x-energy-tx1-triso-nuclear-fuel-facility)
10. [EnergyPulse via OpenSentiment, X-energy Starts Interior Work at TX-1 Advanced Nuclear Fuel Plant in Tennessee, 7 October 2026](https://opensentiment.org/article/x-energy-starts-interior-work-tx1-nuclear-fuel-tennessee)
11. [Centrus Energy via PR Newswire/Morningstar, Centrus Energy Signs LEU and HALEU Supply Agreement with X-energy, 6 August 2026](https://www.morningstar.com/news/pr-newswire/20260806ph20576/centrus-energy-signs-leu-and-haleu-supply-agreement-with-x-energy)
12. [SquawkNews, Transcript: Centrus Energy Q2 2026 Earnings Conference Call, 6 August 2026](https://squawknews.com/news/424075-transcript-centrus-energy-q2-2026-earnings-conference-call)
13. [X-Energy, Inc. via GlobeNewswire/Finanznachrichten, X-energy Reports Second Quarter 2026 Results, 13 August 2026](https://www.finanznachrichten.de/nachrichten-2026-08/69301650-x-energy-inc-x-energy-reports-second-quarter-2026-results-399.htm)
14. [MIT Technology Review via Pipedot, X-energy and its helium-cooled nuclear reactors, 7 October 2026](https://pipedot.org/article/78VXN)


---

Segra bet 22.5% of its fund on X-Energy. The prize is a fuel factory, not a permit — The Inference. Canonical: https://theinference.org/article/segra-bet-22-5-of-its-fund-on-x-energy-the-prize-is-a-fuel-factory-not-a-permit