title: "TeraWulf has $3.5 billion of debt to price before Google's backstop starts in 2028"
description: "Google's backstop at the $19 billion Hawesville campus starts only when the last data hall commences in 2028. Until then TeraWulf funds a $4 billion-plus build from $2.36 billion of cash and an unpriced $3.5 billion raise, and the coupon decides who eats the gap."
publisher: "The Inference"
section: "Data Center"
published: 2026-11-27T19:40:52.884Z
modified: 2026-11-27T19:40:52.884Z
canonical: https://theinference.org/article/terawulf-has-3-5-billion-of-debt-to-price-before-google-s-backstop-starts-in-2028
language: en
keywords: "TeraWulf, Anthropic, Data Centers, Debt Financing, Google"
---

# TeraWulf has $3.5 billion of debt to price before Google's backstop starts in 2028

> Google's backstop at the $19 billion Hawesville campus starts only when the last data hall commences in 2028. Until then TeraWulf funds a $4 billion-plus build from $2.36 billion of cash and an unpriced $3.5 billion raise, and the coupon decides who eats the gap.

[Anthropic](https://theinference.org/markets/companies/anthropic), the AI lab behind the Claude models, closed at $81.91 on November 24, its first close below the $83 it priced its public listing at on November 18, after bond investors told reporters they expect its debt to be rated junk [3]. Its landlord took the bigger hit. [TeraWulf](https://theinference.org/markets/companies/terawulf), the bitcoin miner turned data center owner, fell 14.4% to $9.34 that day, breaking its 52-week low of $9.51 [2]. Two days earlier, chairman and chief executive Paul Prager had written on X: "I hate dilution" [1].

## $4 billion of building, $3.5 billion of it unbought

At Hawesville, Kentucky, TeraWulf is building a campus called Justified on a former Century Aluminum smelter it bought for $200 million in February [4]. Anthropic [signed a 20-year lease there on July 6](https://thecrossover.io/p/terawulf-leased-a-kentucky-smelter-site-to-anthropic-for-20-years) for about 401 megawatts of computing load, worth about $19 billion of contracted revenue over the initial term [4][6].

![Aerial view of rows of rooftop cooling units and pipework at a TeraWulf data center](https://storage.googleapis.com/theinference-public/img/84479d5f76ed0e20.jpg)

*Cooling plant at a TeraWulf site. Hawesville is budgeted at $10 million to $12 million per critical IT megawatt, or roughly $4 billion to $4.8 billion. (Courtesy of TeraWulf)*

Management pegs the cost at $10 million to $12 million per critical IT megawatt, roughly $4 billion to $4.8 billion for the site, and says about 30% is equity on the company's own precedent, $550 million of it already in [7]. The rest, about $3.5 billion, is [the debt raise Bloomberg reported in July](https://www.thestreet.com/crypto/markets/google-backed-ex-bitcoin-miner-reveals-3-5-billion-debt-raise): leveraged loans plus high-yield bonds, led by [Morgan Stanley](https://theinference.org/markets/companies/morgan-stanley) [8]. It has no price. Interest expense already ran $53.6 million in the third quarter, [about 85% of the quarter's $63 million of lease revenue](https://theinference.org/article/terawulf-s-63-million-ai-lease-line-contains-46-million-of-rent) [16].

*Chart: **Capex runs at $0.8 billion a quarter and operating cash covers almost none of it** Column chart of TeraWulf capital spending against operating cash flow by quarter, Q4 2024 to Q3 2026: capital spending climbs from $0.13 billion to $0.85 billion while operating cash flow stays between negative $0.14 billion and positive $0.06 billion.*

*Capital spending and cash from operations, $ billions, by quarter. Reported figures from TeraWulf's SEC filings [17]; the Hawesville budget itself is not in this series. [17]*

## The guarantee that starts too late

"They don't walk away from deals. That debt is guaranteed by Google," Prager said on television on November 24 [3]. [The filing he leans on](https://www.sec.gov/Archives/edgar/data/1083301/000162828026069810/wulf-20261104.htm) is narrower. Each [Google](https://theinference.org/markets/companies/alphabet) credit support agreement takes effect as of the commencement date of the final data hall under its lease, with deliveries phased from late 2027 through the second quarter of 2028, and it terminates once Anthropic holds investment-grade ratings for three months [6]. Until the last hall turns on, the junk rating everyone expects is TeraWulf's problem.

Management says the remaining commitments get funded "without accessing the equity capital markets" [7]. The record this year says otherwise: shares outstanding rose to 501.4 million from 420.1 million in nine months, including $1.2 billion of common stock sold [16].

## The cash is nearly spent, and bitcoin is not helping

[Cash, equivalents and restricted cash fell $1.37 billion in the nine months to September](https://www.sec.gov/Archives/edgar/data/1083301/000162828026071671/wulf-20260930.htm), to $2.36 billion; about $1.1 billion sits at the parent company, $300 million of it pledged against Muskie letters of credit [7][16]. About $150 million more arrives from the Abernathy joint venture sale on or before December 31, 2026, and about $130 million on or before April 30, 2027 [7].

Bitcoin, the other cash engine, traded as low as roughly $59,470 this week, and mining revenue was already down 69% year over year at $13.2 million in the quarter [2]. The cushion that funds equity is thinning from both ends.

*Chart: **The 2025 cash pile is draining while debt holds at $5.26 billion** Line chart of TeraWulf quarter-end cash, cash equivalents and restricted cash against total debt, Q4 2024 to Q3 2026: debt jumps to $5.2 billion in Q4 2025 and stays above $5.2 billion while cash falls from $3.72 billion to $2.36 billion.*

*Quarter-end cash, cash equivalents and restricted cash, and total debt, $ billions. Reported figures from TeraWulf's SEC filings [14][17]; cash matches the $2.36 billion in its Form 10-Q. The series starts at Q4 2024, after the reported break in both cash and debt in the preceding quarters. [14][17]*

## The price of money moved while they waited

[Morgan Stanley now discounts TeraWulf's pipeline projects at 11% to 14%](https://finance.yahoo.com/markets/stocks/articles/morgan-stanley-cuts-terawulf-target-163237446.html), from 9% to 12%, and models debt coupons of 8.5% for hyperscaler tenants and 12.5% for neoclouds [9]. On November 16, [Blackstone bought 75% of two Amazon Web Services data center joint ventures at a 7.0% cap rate](https://gcn.com/aws-sells-majority-stake-data-centers/23512/), the price of finished shells leased to an AA+ tenant [10].

At an 8.5% coupon, $3.5 billion costs about $298 million a year; at 7%, $245 million [9][10]. Anthropic's $19 billion of rent works out, on simple arithmetic over the 20-year term, to roughly $950 million a year, covering either many times over once the halls run [9][10]. The fight is over the two years before that.

*Chart: **Hawesville's money prices above what finished data centers yield** Column chart comparing annual cost of capital in percent: Blackstone-AWS cap rate 7.0, TeraWulf 7.75 percent secured notes, Morgan Stanley modeled hyperscaler coupon 8.5, Morgan Stanley modeled neocloud coupon 12.5.*

*Annual cost of capital, percent. The two Morgan Stanley coupons are modeled estimates, not quoted deals. Sources: GCN on the Blackstone-AWS transaction; Blockspace via Yahoo Finance on Morgan Stanley's rates; TeraWulf Q3 2026 earnings call for the 7.75% notes. [7][9][10]*

## The rent covers the build four times over

The counterpoint is arithmetic too. The $19 billion of contracted revenue is roughly four times the build [6]. Once live, [Google's backstop](https://theinference.org/article/google-backstops-anthropic-s-19-billion-terawulf-lease-and-takes-equity-if-anthropic-stops-paying) prices the debt off Alphabet's AA+ rating, and on a payment default Google can assume the lease as tenant or pay a termination fee for an equity stake in the campus entity [6].

[Lake Mariner's leases should put the company at about $700 million of annualized run-rate leasing revenue exiting the first quarter of 2027](https://finance.yahoo.com/markets/stocks/articles/terawulf-wulf-q3-2026-earnings-192816573.html), and management calls recycling capital from stabilized assets its 2027 priority [7]. If Fluor's construction schedule holds and Anthropic keeps paying on its roughly $96 billion of cash, the junk talk is noise priced into a stock that fell because the whole AI infrastructure sector did [2][3].

## The coupon settles it

The coupon on the Hawesville raise is the number that settles it [8]. The Federal Reserve meets December 8 and 9 with a quarter-point hike priced, and [the 10-year Treasury yield stood at 4.93% on November 27](https://theinference.org/indexes/us-10y-yield) after touching 5.15% this month [13].

Anthropic's rating cuts both ways: an investment-grade rating frees it to borrow cheaply and lapses Google's obligation within three months; a junk rating keeps the backstop standing as the halls start [6][3]. The late-February report carries the December quarter, and with it the answer to whether the equity that funded the gap came from the balance sheet, as promised, or from shareholders after all [7][16].

## Takeaway

Google's guarantee at Hawesville begins only when the last hall is running in 2028, so the coupon on TeraWulf's unpriced $3.5 billion raise, not the $19 billion lease, decides who eats the gap.

## Sources

1. [Blockspace, TeraWulf CEO says he won't rush a Muskie lease, citing dilution risk, 23 November 2026](https://blockspace.media/insight/terawulf-wont-rush-muskie-lease/)
2. [BeInCrypto via AskFuzz, TeraWulf Stock Plunges 14.39% Amid AI Infrastructure Selloff, 25 November 2026](https://askfuzz.ai/discover/news/companies/terawulf-ceo-says-ai-selloff-hits-price-not-demand)
3. [TIKR, TeraWulf's CEO Says Anthropic Won't Walk Away From Deals. Junk-Rating Talk Tests That, 25 November 2026](https://www.tikr.com/blog/terawulfs-ceo-says-anthropic-wont-walk-away-from-deals-junk-rating-talk-tests-that)
4. [The Crossover, TeraWulf leased a Kentucky smelter site to Anthropic for 20 years, 17 August 2026](https://thecrossover.io/p/terawulf-leased-a-kentucky-smelter-site-to-anthropic-for-20-years)
6. [SEC EDGAR, TeraWulf Inc. Form 8-K, Google Credit Support Agreements, filed 4 November 2026](https://www.sec.gov/Archives/edgar/data/1083301/000162828026069810/wulf-20261104.htm)
7. [The Motley Fool via Yahoo Finance, TeraWulf (WULF) Q3 2026 Earnings Call Transcript, 6 November 2026](https://finance.yahoo.com/markets/stocks/articles/terawulf-wulf-q3-2026-earnings-192816573.html)
8. [TheStreet, Google-backed ex-Bitcoin miner reveals $3.5 billion debt raise, 9 July 2026](https://www.thestreet.com/crypto/markets/google-backed-ex-bitcoin-miner-reveals-3-5-billion-debt-raise)
9. [Blockspace via Yahoo Finance, Morgan Stanley cuts TeraWulf target to $47 on higher discount rates, keeps Overweight, 12 November 2026](https://finance.yahoo.com/markets/stocks/articles/morgan-stanley-cuts-terawulf-target-163237446.html)
10. [GCN, AWS sells majority stake in data centers to Blackstone for $5 billion, 25 November 2026](https://gcn.com/aws-sells-majority-stake-data-centers/23512/)
13. [The Inference, 10-year Treasury yield index, as of 27 November 2026](https://theinference.org/indexes/us-10y-yield)
14. [TeraWulf, quarterly cash and debt figures from its SEC filings, retrieved 27 November 2026](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0001083301)
16. [SEC EDGAR, TeraWulf Inc. Form 10-Q for the quarter ended September 30, 2026, filed 6 November 2026](https://www.sec.gov/Archives/edgar/data/1083301/000162828026071671/wulf-20260930.htm)
17. [TeraWulf, quarterly figures from its SEC filings, retrieved 27 November 2026](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0001083301)


---