title: "Texas cleared Hut 8 to build the second half of its 1-gigawatt AI campus, but Phase 2 has no bonds yet"
description: "The November 24 Notice of Intent clears the 500 MW half of the one-gigawatt campus, whose $9.8 billion lease still has no priced bonds. ERCOT and the PUC rule on Texas power for 6.5 GW of load on December 10, and the equity carries the gap."
publisher: "The Inference"
section: "Data Center"
published: 2026-11-26T18:22:43.190Z
modified: 2026-11-26T18:22:43.190Z
canonical: https://theinference.org/article/texas-cleared-hut-8-to-build-the-second-half-of-its-1-gigawatt-ai-campus-but-phase-2-has-no-bonds-yet
language: en
keywords: "Hut 8, Data Centers, Project Finance, Texas, AI Infrastructure"
---

# Texas cleared Hut 8 to build the second half of its 1-gigawatt AI campus, but Phase 2 has no bonds yet

> The November 24 Notice of Intent clears the 500 MW half of the one-gigawatt campus, whose $9.8 billion lease still has no priced bonds. ERCOT and the PUC rule on Texas power for 6.5 GW of load on December 10, and the equity carries the gap.

[Hut 8](https://theinference.org/markets/companies/hut-8-mining)'s Texas expansion cleared a regulatory step [1][5]. On November 24 the Texas Commission on Environmental Quality, the state's environmental regulator, [issued a Notice of Intent](https://datacenterbulletin.com/headlines/hut-8-gets-texas-approval-to-build-beacon-point-phase-two/) authorizing construction of Beacon Point Phase 2, site preparation is under way, and Hut 8 expects to energize an initial 700 MW in the first quarter of 2027, with about 1,900 construction jobs and 230 permanent roles projected [1][5].

## The $7.5 billion of project bonds covers only Phase 1

Beacon Point is a one-gigawatt AI campus in Nueces County, Texas, split into two 500 MW phases of 352 MW of IT load each, leased to an unnamed investment-grade tenant for a combined $19.6 billion [1][2][4]. But the $7.5 billion of non-recourse project bonds that made this model fundable covers only River Bend ($3.25 billion) and Beacon Point Phase 1 ($4.25 billion) [2].

*Chart: **Each phase carries a $9.8B lease, but bonds sit behind only Phase 1** Column chart comparing Beacon Point's two phases: each has a $9.8 billion lease, Phase 1 has $4.25 billion of project bonds, Phase 2 has none.*

*Lease value against non-recourse project bond financing for Beacon Point's two 500 MW phases, US$ billions. Phase 2 had no financing arranged at the third-quarter 2026 print. Sources: Global Data Center Hub, Startup Fortune. [2][4]*

Phase 2's financing was still being arranged at the third-quarter print, when Hut 8 reported negative $455.7 million of free cash flow and $156.9 million of unrestricted cash against $6.4 billion of restricted project funds [2]. The lease book behind it, including River Bend's Google-backed [Fluidstack](https://theinference.org/markets/companies/fluidstack) lease, was laid out in [our November 21 piece on the Louisiana side](https://theinference.org/article/hut-8-s-27-billion-of-ai-leases-cover-949-megawatts-the-other-6-910-need-about-73-billion-to-build) [2].

*Chart: **Hut 8 has burned cash every quarter for two years, and the burn is deepening** Line chart of Hut 8 quarterly free cash flow from Q2 2024 to Q3 2026, below zero in every quarter and deepening to about minus $0.59 billion in Q2 2026.*

*Hut 8 quarterly free cash flow, US$ billions, from its SEC filings: negative in all ten quarters, deepest at about minus $0.59 billion in Q2 2026 and about minus $0.45 billion in Q3 2026. Source: Hut 8 filings. [6]*

## The power ruling lands December 10

ERCOT, the Texas grid operator, and the Public Utility Commission of Texas are expected to rule on December 10 on [Batch Zero designations](https://finance.yahoo.com/technology/articles/6-5-gw-texas-data-155707557.html) covering more than 6.5 GW of Texas large load, Hut 8 among the applicants, and Needham sees a high risk some of those projects are never completed as approvals tighten into 2027 [3]. Governor-elect Gina Hinojosa has called for a moratorium on new approvals, though proposed pauses would spare permitted projects, and Phase 2 now holds its permit [4].

## Lenders will read the lease term closely

The November 24 announcement still describes both Beacon Point leases as 15-year, while [the third-quarter disclosure](https://www.globaldatacenterhub.com/p/hut-8-signed-949-mw-now-it-must-deliver) says the Phase 2 term was extended to 17 years [1][2]. That matters because project bonds are underwritten against the lease's term: a 17-year rent stream supports a larger or longer repayment profile than a 15-year one, so the term on the bond documents will show whether lenders took the extension [1][2].

Phase 2's bonds are unpriced; watch the December 10 power ruling and the financing terms that follow, not the headline lease value [1][2][3]. [Our November 3 piece on the second $9.8 billion lease and the Keefe Bruyette downgrade](https://theinference.org/article/hut-8-fell-15-the-day-after-anthropic-s-119-5-billion-ipo-10-7-billion-of-river-bend-rent-is-unsigned) covers the stock's history here [1][2][3].

## Takeaway

The permit is now in hand for Beacon Point's second 500 MW, but the $9.8 billion Phase 2 lease still has no priced project bonds, so equity carries the build until lenders and the December 10 ERCOT ruling settle it.

## Sources

1. [Data Center Bulletin, 'Hut 8 gets Texas approval to build Beacon Point phase two', 25 November 2026](https://datacenterbulletin.com/headlines/hut-8-gets-texas-approval-to-build-beacon-point-phase-two/)
2. [Global Data Center Hub, 'Hut 8 Signed 949 MW. Now It Must Deliver.', 26 November 2026](https://www.globaldatacenterhub.com/p/hut-8-signed-949-mw-now-it-must-deliver)
3. [Yahoo Finance / Blockspace, '6.5 GW of Texas data center load faces December 10 ERCOT Batch Zero decision: Needham', 23 November 2026](https://finance.yahoo.com/technology/articles/6-5-gw-texas-data-155707557.html)
4. [Startup Fortune, 'Hut 8 and MARA shares plunge as bitcoin slips under $60,000 and AI stocks sell off', 26 November 2026](https://startupfortune.com/hut-8-and-mara-shares-plunge-as-bitcoin-slips-under-60000-and-ai-stocks-sell-off/)
5. [RootData, 'Hut 8 announced that Beacon Point Phase II AI Park has been approved for construction, and on-site preparations have begun', 25 November 2026](https://www.rootdata.com/news/843946)
6. [Hut 8, quarterly figures from its SEC filings, retrieved 26 November 2026](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0001964789)


---

Texas cleared Hut 8 to build the second half of its 1-gigawatt AI campus, but Phase 2 has no bonds yet — The Inference. Canonical: https://theinference.org/article/texas-cleared-hut-8-to-build-the-second-half-of-its-1-gigawatt-ai-campus-but-phase-2-has-no-bonds-yet