title: "Ulanqab's AI compute doubled in a year to 190,000 petaflops, official count shows"
description: "The first official tally of China's fastest-growing AI hub lands days after Washington restricted remote access to US chips, one of two back doors behind nearly half the country's AI compute. Seven million contracted racks in one Inner Mongolia city now wait on a single bottleneck: Huawei's Ascend supply."
publisher: "The Inference"
section: "Data Center"
published: 2026-11-21T14:09:32.565Z
modified: 2026-11-21T14:09:32.565Z
canonical: https://theinference.org/article/ulanqab-s-ai-compute-doubled-in-a-year-to-190-000-petaflops-official-count-shows
language: en
keywords: "China, Huawei, Data Centers, Export Controls, AI Compute"
---

# Ulanqab's AI compute doubled in a year to 190,000 petaflops, official count shows

> The first official tally of China's fastest-growing AI hub lands days after Washington restricted remote access to US chips, one of two back doors behind nearly half the country's AI compute. Seven million contracted racks in one Inner Mongolia city now wait on a single bottleneck: Huawei's Ascend supply.

## A steppe city that counts its wealth in petaflops

Ulanqab, a prefecture of 1.5 million people on the Mongolian plateau, already draws close to 1% of all electricity used in China, and the power is going into servers [2]. On October 23, China's National Energy Administration put the city's operational capacity at 190,000 petaflops, a unit of raw processing power, up 112% in a year, with more than 95% of it running AI workloads [1]. [Huawei](https://theinference.org/markets/companies/huawei), [Alibaba](https://theinference.org/markets/companies/alibaba), [ByteDance](https://theinference.org/markets/companies/bytedance), Kuaishou, the data-center operator VNET and [DeepSeek](https://theinference.org/markets/companies/deepseek) are all building there [1].

## Seven million racks are signed

The contracts behind that line run to about 109 computing centers and more than 7 million server racks [1], part of [investment agreements worth more than $74 billion](https://www.msn.com/en-us/technology/cloud-computing/china-s-ulanqab-plans-5mn-server-racks-in-ai-compute-race-with-us/ar-AA2cs6Ag) [2] and [roughly 15GW of committed capacity](https://cryptobriefing.com/xi-national-computing-power-network-inner-mongolia/) [3]. The queue now has names and dates.

ByteDance is negotiating a further 5-6GW for delivery in early 2028, and DeepSeek plans [at least 160,000 of Huawei's Ascend 950DT AI chips](https://seekingalpha.com/news/4640307-deepseek-said-to-order-at-least-160k-huawei-ai-accelerators-for-new-data-center-report) in a roughly 1GW project, with the first phases live between late 2027 and early 2028 [1][6]. An annual average of 4.3C and 20,288MW of installed renewables keep the power bill down [1].

*Chart: **Named projects already fill most of Ulanqab's 15GW pipeline** Bar chart of Ulanqab AI data-center capacity in gigawatts: committed total about 15, ByteDance 5-6 in negotiation, Envision Galaxy 2 operational, DeepSeek about 1 planned*

*Capacity in gigawatts. Committed total as of mid-October per Crypto Briefing; ByteDance figure is a reported negotiation of 5-6GW; DeepSeek project is planned; Envision's Galaxy campus is commissioned. Sources: DIGITIMES, IntelliNews, Crypto Briefing. [1][2][3]*

## Washington closed the back doors the same month

On November 16 the US Commerce Department issued [an interim final rule to stop China reaching advanced American chips through data centers abroad](https://www.datacenterdynamics.com/en/news/us-dept-of-commerce-issues-rule-to-restrict-remote-access-to-advanced-ai-chips/), with licenses now required to move chips into and within Malaysia, Singapore, Thailand, Indonesia and Brazil [5]. The routes it targets are not marginal. Smuggled chips supply about 22% of China's AI data-center capacity and rented compute abroad another 25%, according to Institute for Progress estimates; [SemiAnalysis](https://theinference.org/markets/companies/semianalysis) counts roughly 1.5GW, about 1 million restricted [Nvidia](https://theinference.org/markets/companies/nvidia) chips, already inside China [4]. Ulanqab is the replacement under construction.

## The count tests Huawei's wafer math

Huawei is the hub's landlord, with two cloud phases running, and every chip order named in the buildout is an Ascend order [1]. In September its rotating chairman Eric Xu [said Huawei cannot produce enough AI computing equipment to meet Chinese demand](https://www.usnews.com/news/top-news/articles/2026-09-16/chinas-huawei-sets-2027-launch-for-new-ai-chips-as-it-targets-nvidia) and is holding back overseas sales, with the next Ascend chip pulled forward to early 2027 [7].

The bull case rests on Xu's claim that Ascend outsells Nvidia in China, offered without data, a claim [Huawei has made before without showing the evidence](https://theinference.org/article/huawei-declares-victory-over-nvidia-in-china-on-evidence-it-will-not-show), and on Nvidia's resumed H200 sales, still under 1% of quarterly data-center revenue [8].

Domestic chips cover about a fifth of China's compute demand this year, one American Enterprise Institute estimate puts it [2]. DeepSeek's plan to [pre-train its next model, V5, on Huawei silicon](https://www.economist.com/briefing/2026/11/19/how-china-continues-to-evade-americas-tech-export-rules) is the test that settles it [4]. The racks are signed. The wafers are not.

## Takeaway

China's flagship AI hub has the contracts, the power and the government tally to prove its rise. What it lacks is Huawei silicon, and DeepSeek's V5 training run is the test that shows whether domestic chips can carry the load.

## Sources

1. [DIGITIMES, China's AI giants converge on Ulanqab in race to build computing hub by 2028, 20 November 2026](https://www.digitimes.com/news/a20261120PD220/china-data-center-capacity-2028.html)
2. [IntelliNews via MSN, China's Ulanqab plans 5mn server racks in AI compute race with US, 17 September 2026](https://www.msn.com/en-us/technology/cloud-computing/china-s-ulanqab-plans-5mn-server-racks-in-ai-compute-race-with-us/ar-AA2cs6Ag)
3. [Crypto Briefing, Xi calls for national integrated computing power network, spotlighting Inner Mongolia, 16 October 2026](https://cryptobriefing.com/xi-national-computing-power-network-inner-mongolia/)
4. [The Economist, How China continues to evade America's tech-export rules, 19 November 2026](https://www.economist.com/briefing/2026/11/19/how-china-continues-to-evade-americas-tech-export-rules)
5. [DataCenterDynamics, US Dep't of Commerce issues rule to restrict remote access to advanced AI chips, 16 November 2026](https://www.datacenterdynamics.com/en/news/us-dept-of-commerce-issues-rule-to-restrict-remote-access-to-advanced-ai-chips/)
6. [Seeking Alpha, DeepSeek said to order at least 160K Huawei AI accelerators for new data center: report, 4 September 2026](https://seekingalpha.com/news/4640307-deepseek-said-to-order-at-least-160k-huawei-ai-accelerators-for-new-data-center-report)
7. [Reuters via US News & World Report, China's Huawei Says AI Chip Demand Outstrips Supply as It Steps up Nvidia Challenge, 16 September 2026](https://www.usnews.com/news/top-news/articles/2026-09-16/chinas-huawei-sets-2027-launch-for-new-ai-chips-as-it-targets-nvidia)
8. [South China Morning Post via MSN, China to see major shift to Huawei for AI model training in 2027: deputy chair, 17 September 2026](https://www.msn.com/en-xl/technology/tech-companies/china-to-see-major-shift-to-huawei-for-ai-model-training-in-2027-rotating-chair/ar-AA2cteAR)


---

Ulanqab's AI compute doubled in a year to 190,000 petaflops, official count shows — The Inference. Canonical: https://theinference.org/article/ulanqab-s-ai-compute-doubled-in-a-year-to-190-000-petaflops-official-count-shows