title: "Vistra CEO calls data-center power queues overstated as Texas logs 194 GW of requests against a 91 GW peak"
description: "James Burke says the queues behind America's data-center load forecasts are inflated by developer speculation, and wants higher collateral and take-or-pay transmission contracts. The filings behind the words show a company split in two: contracted nuclear megawatts that need no queue, and a merchant 2028 with a fifth of its output unsold."
publisher: "The Inference"
section: "Power"
published: 2026-11-25T18:26:33.439Z
modified: 2026-11-25T18:26:33.439Z
canonical: https://theinference.org/article/vistra-ceo-calls-data-center-power-queues-overstated-as-texas-logs-194-gw-of-requests-against-a-91-gw-peak
language: en
keywords: "Vistra, ERCOT, Data Centers, Nuclear, Texas"
---

# Vistra CEO calls data-center power queues overstated as Texas logs 194 GW of requests against a 91 GW peak

> James Burke says the queues behind America's data-center load forecasts are inflated by developer speculation, and wants higher collateral and take-or-pay transmission contracts. The filings behind the words show a company split in two: contracted nuclear megawatts that need no queue, and a merchant 2028 with a fifth of its output unsold.

## The queue is inflated, says the company selling into it

[Vistra](https://theinference.org/markets/companies/vistra) chief executive James Burke told investors on November 6 that the interconnection queues behind forecasts of American data-center load growth are overstated [1]. "Load interconnect queues were overstated across the country and especially in [ERCOT], driven by speculation from developers," he said, in [remarks Utility Dive reported on November 24](https://finance.yahoo.com/energy/articles/midterms-clarity-data-center-development-155455752.html) [1]. He asked for guardrails in the same breath: tougher interconnection standards, higher collateral and take-or-pay transmission contracts, paying for reserved capacity even unused [1]. Texas's utility commission already charges a $100,000 study fee and $50,000 per megawatt of refundable security to enter the queue [2]; the chief executive wants the bar higher.

"The pacing was already being impacted ahead of the election," he said, "but our plans have always had a more conservative view of the AI build-out" [3]. His growth outlook did not move: 4 to 6 percent a year in ERCOT, the Texas grid, through 2030 [1].

## A record quarter, with a bigger 2027 promised

The quarter behind the remarks was Vistra's biggest: adjusted EBITDA up more than 50 percent to $2.378 billion, 2026 guidance raised to $7.1 billion to $7.5 billion, and [a first 2027 range of $7.7 billion to $8.5 billion](https://theinference.org/article/vistra-guided-2027-ebitda-to-7-7-to-8-5-billion-with-98-of-output-hedged-before-the-texas-vote) [4]. That range already counts the 5,500 megawatts of Cogentrix gas plants closed on October 30 for $2.2 billion in cash plus five million shares [5].

## Half the fleet needs no queue: Meta holds 2,609 megawatts

Half the company does not need the queue: [Meta](https://theinference.org/markets/companies/meta) holds [20-year nuclear contracts for 2,609 megawatts](https://theinference.org/article/vistras-1-billion-ai-bet-changes-who-carries-the-risk) from the Perry and Davis-Besse plants, first delivery late 2026, full by end-2027, with the 433 megawatts of uprates only delivering from 2031 [5]. [The same filing](https://www.sec.gov/Archives/edgar/data/1692819/000169281926000025/vistra-20260930.htm) carries a $1 billion commitment to KKR's Helix AI-infrastructure fund, its second half payable at Vistra's election whether or not milestones are met [5]. The merchant half is the exposed one, and its armor is the hedge book [4].

![Two cooling towers of the Perry Nuclear Power Plant in Ohio, one venting steam, seen from the plant entrance road](https://storage.googleapis.com/theinference-public/img/b93640baa8e4e1e0.jpg)

*Perry Nuclear Power Plant in Ohio, one of the two Vistra plants whose output Meta has contracted for 20 years. Its 2,609 megawatts need no interconnection queue. (Cards84664, CC BY-SA 4.0)*

*Chart: **Vistra has sold forward 98% of 2027 output, and only 78% of 2028** Column chart: hedged share of Vistra's expected generation volumes as of October 30, 2026, is about 100 percent for delivery year 2026, 98 percent for 2027 and 78 percent for 2028.*

*Hedged share of Vistra's expected generation volumes as of October 30, 2026, by delivery year, from the company's third-quarter earnings release of November 6, 2026. Figures are approximate as reported. [4]*

## 194 gigawatts of requests against a 91-gigawatt peak

The Texas numbers back the skepticism. ERCOT's audit has conditionally classed 204 large-load projects totaling 66.4 gigawatts as base load and 158 more, 127.9 gigawatts, as studied: about 194 gigawatts of requests against a record 91-gigawatt peak set this year [6][1].

*Chart: **ERCOT's queue holds 194 GW of requests, more than twice the record peak** Column chart: ERCOT has 127.9 gigawatts of large-load requests still under study and 66.4 gigawatts conditionally classed as base load, about 194 gigawatts in all, against a record peak demand of 91 gigawatts.*

*Large-load interconnection requests in ERCOT by audit status, gigawatts, against the grid's record peak demand set in 2026. The 66.4 GW conditionally classed as base load and the 127.9 GW under study total about 194 GW. Sources: Gibson Dunn client alert, November 18, 2026, and Utility Dive, November 24, 2026. [6][1]*

## The audit, the inauguration and the fourth quarter will settle it

The audit report lands on December 10; environmental permit reviews resumed on November 16, energization approvals stay paused, and Governor-elect Gina Hinojosa, who pledges a moratorium until the legislature passes protections, takes office on January 19 [6]. [Vertiv is selling the wait too](https://theinference.org/article/vertiv-paid-1-45-billion-for-utilityinnovation-group-to-sell-data-centers-a-way-around-the-power-queue): [its outdoor medium-voltage UPS, built to speed grid connections](https://www.engineeringnews.co.za/article/vertiv-introduces-medium-voltage-power-system-to-help-ai-data-centres-connect-to-the-grid-faster-and-free-indoor-space-for-compute-2026-11-23), ships from mid-2027 [7]. The late-February fourth-quarter report should show how much of 2028, 78 percent hedged [4], has been sold [3]. The shares closed at $120 on November 24, 14 percent below Election Day's roughly $140 [1], and slid further the next day [8]. At about 13 times forward earnings [3], the price pays for the megawatts under contract, not the queue its own chief executive calls inflated.

## Takeaway

Vistra has hedged 98% of its 2027 output and only 78% of 2028, so the year a Texas data-center moratorium would land is the year its merchant fleet is most exposed.

## Sources

1. [Utility Dive (via Yahoo Finance), Midterms provide clarity on data center development: Vistra CEO, 24 November 2026](https://finance.yahoo.com/energy/articles/midterms-clarity-data-center-development-155455752.html)
2. [Steptoe & Johnson via JD Supra, Texas Raises the Bar for Large Load Interconnections: What 16 TAC §25.194 Means for Your Next Project, 20 October 2026](https://www.jdsupra.com/legalnews/texas-raises-the-bar-for-large-load-3584405/)
3. [EnergyPressWire (TIKR), Vistra Just Dropped 16% in a Month, but Its Plans Always Had a More Conservative View of the AI Build-Out, 19 November 2026](https://energypresswire.com/2026/11/19/vistra-just-dropped-16-in-a-month-but-its-plans-always-had-a-more-conservative-view-of-the-ai-build-out/)
4. [Vistra Corp. news release, Vistra Reports Third Quarter 2026 Results, 6 November 2026 (SEC Form 8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1692819/000169281926000023/vistra-20261106.htm)
5. [Vistra Corp., Form 10-Q for the quarterly period ended 30 September 2026, filed 9 November 2026](https://www.sec.gov/Archives/edgar/data/1692819/000169281926000025/vistra-20260930.htm)
6. [Gibson Dunn client alert, Updated: Texas Data Center Critical Dates and Procedures Following the 2026 Elections, 18 November 2026](https://www.gibsondunn.com/texas-data-center-critical-dates-and-procedures-following-the-2026-elections/)
7. [Engineering News, Vertiv Introduces Medium-Voltage Power System to Help AI Data Centres Connect to the Grid Faster, 23 November 2026](https://www.engineeringnews.co.za/article/vertiv-introduces-medium-voltage-power-system-to-help-ai-data-centres-connect-to-the-grid-faster-and-free-indoor-space-for-compute-2026-11-23)
8. [Blockchain.news, Vistra (VST) Stock Price Prediction: Bearish momentum meets analyst support after a sharp pullback, 25 November 2026](https://blockchain.news/news/20261125-price-prediction-vst-bearish-momentum-meets-analyst-support-after)


---

Vistra CEO calls data-center power queues overstated as Texas logs 194 GW of requests against a 91 GW peak — The Inference. Canonical: https://theinference.org/article/vistra-ceo-calls-data-center-power-queues-overstated-as-texas-logs-194-gw-of-requests-against-a-91-gw-peak