title: "Who stands on the other side of GE Vernova's $176 billion backlog"
description: "Oracle invoked force majeure on a Stargate campus and the power-equipment trade sold off; the same week, GE Vernova signed Egyptian state-utility work running to 2035 and a four-way nuclear pact aimed at Poland and the UK. The $176 billion backlog is gaining customers on decade-long service schedules, and most of that new work is not yet firm."
publisher: "The Inference"
section: "Power"
published: 2026-09-28T02:43:37.499Z
modified: 2026-09-28T02:43:37.499Z
canonical: https://theinference.org/article/who-stands-on-the-other-side-of-ge-vernova-s-176-billion-backlog
language: en
keywords: "GE Vernova, Oracle, Data Centers, Nuclear, Power"
---

# Who stands on the other side of GE Vernova's $176 billion backlog

> Oracle invoked force majeure on a Stargate campus and the power-equipment trade sold off; the same week, GE Vernova signed Egyptian state-utility work running to 2035 and a four-way nuclear pact aimed at Poland and the UK. The $176 billion backlog is gaining customers on decade-long service schedules, and most of that new work is not yet firm.

## A tenant's escape hatch

[Oracle](https://theinference.org/markets/companies/oracle) wants to stop paying for a data center until the data center exists. On 24 September it [sent a force majeure notice](https://www.msn.com/en-us/news/other/oracle-triggers-force-majeure-on-data-center-project-over-power-delays-source-says/ar-AA2cVgAM) to the developer of [Project Jupiter](https://theinference.org/article/oracle-moves-to-defer-the-rent-on-a-data-center-it-says-is-on-schedule), the 1,400-acre Stargate campus in New Mexico, keeping the right to delay payments if the site misses its planned 2028 start; the obstacle is power, Oracle's own responsibility under the contract, with a gas pipeline slipped to February 2027 after permit denials and an air-quality ruling due 23 November [1][3].

The equipment makers paid for it anyway. [Bloom Energy](https://theinference.org/markets/companies/bloom-energy) closed down 3.1% and [GE Vernova](https://theinference.org/markets/companies/ge-vernova) fell as much as 1.3% before ending up 0.3%, as investors repriced the delivery schedules those order books assume [2][4][10].

## The number under pressure

The stock that wobbled carries a $176 billion order book [4]. [Strazik](https://theinference.org/markets/people/scott-strazik) [told a Morgan Stanley conference on 16 September](https://247wallst.com/investing/2026/09/16/ge-vernova-climbs-5-as-ceo-sees-backlog-hitting-200b-early-eaton-and-quanta-services-edge-higher/) that the backlog should cross $200 billion "very early in 2027," a milestone he called humble; shares rose 5% that day [5]. The price already assumes delivery: about 36 times earnings, against 19 for the S&P 500 [2].

## The other order book

The week's signings came from a different page of the customer file. On 23 September GE Vernova [announced rotor life extensions for five Egyptian state-utility gas turbines](https://www.marketscreener.com/news/ge-vernova-advances-asset-longevity-for-egypta-s-power-sector-with-rotor-life-extension-services-ce785ad9dd8bf326), about 1,250 MW with services running from 2028 to 2035, and the same day [signed a four-way memorandum](https://www.world-nuclear-news.org/articles/ge-vernova-hitachi-sge-and-samsung-ct-sign-mou-on-bwrx-300s-in-europe) with Hitachi, Samsung C&T and Poland's SGE to push the BWRX-300 small reactor across Europe, behind Poland's decision in principle for 26 units and a UK proposal for 14 [6][7].

[A March summit in Hanoi](https://energiesmedia.com/ge-vernova-vietnam-lng-hvdc/) had already produced Vietnam's first LNG-fired plant, 1.6 GW on GE Vernova turbines, three technology selections on further projects, and a planned $200 million transformer plant at full operations in 2028 [8].

*Chart: **Nineteen gigawatts of state-grid work, and most of it is not a firm order yet** Five bars comparing gigawatts behind GE Vernova's state-grid items, from 1.25 GW in Egypt to 7.8 GW in Poland*

*Named capacity in gigawatts. Vietnam selections sum the stated plant capacities; SMR bars are unit counts times the BWRX-300's 300 MWe rating. Only the first two bars are contracted or operating. Announced September 2026. [6][7][8]*

## Soft where it counts

The hedge is thin where hedges usually are. Technology selections are not orders, the memorandum binds no one, Egypt is maintenance on machines already running, and none of the three carried a dollar figure [6][7][8]. The Egypt order was booked in Q2, so it sits inside the $176 billion already, not on top of it [6].

## Same stock, both sides

The rotation cannot de-risk what the stock is. UBS [wrote on 24 September that the expansion looks "more reliant on the AI/tech capex buildout than ever,"](https://finance.yahoo.com/technology/ai/articles/ubs-sees-rising-reliance-ai-134045684.html) naming GE Vernova's gas turbines as the channel [9]. "The broader lesson is how hard it has become to bring these campuses on," GLJ analyst Gordon Johnson wrote of Jupiter, calling it "bearish for turbines and chips" [2]. [Goldman Sachs](https://theinference.org/markets/companies/goldman-sachs) sees the five largest US hyperscalers spending more than $1.2 trillion in 2027, and both order books, state and hyperscaler, ride the same demand wave [10].

## The January tell

Conversion, not booking, is the live test, and it is passing: [Q2 2026 revenue of $11.1 billion, up 22% year over year](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0001996810), with $5.1 billion of free cash flow [11].

*Chart: **The backlog is converting into cash: free cash flow hit $5.1B in Q2 2026** Line chart of GE Vernova quarterly revenue and free cash flow rising from late 2024 to mid 2026*

*Quarterly revenue and free cash flow, US$ billions, Q3 2024 through Q2 2026, from GE Vernova's SEC filings. [11]*

Two dates settle who the backlog answers to: the 23 November permit ruling in New Mexico, and GE Vernova's January call, where the 2027 outlook lands [3][5]. The $200 billion question is not whether the orders keep coming. It is who stands on the other side of them.

## Takeaway

The $176B backlog is converting on schedule, but the newest state-grid orders are not firm; the 23 November New Mexico ruling and the January guidance call settle who the orders answer to.

## Sources

1. [Reuters (via MSN), "Oracle triggers force majeure on data center project over power delays, source says," Isla Binnie, 24 September 2026](https://www.msn.com/en-us/news/other/oracle-triggers-force-majeure-on-data-center-project-over-power-delays-source-says/ar-AA2cVgAM)
2. [Barron's (via MSN), "Why Oracle's data center issue is a problem for GE Vernova," Al Root, 24 September 2026](https://www.msn.com/en-us/money/economy/why-oracle-s-data-center-issue-is-a-problem-for-ge-vernova/ar-AA2cUwM1)
3. [TechCrunch, "Oracle sends force majeure notice on its New Mexico Stargate data center," Aditya Mehta, 24 September 2026](https://techcrunch.com/2026/09/24/oracle-sends-force-majeure-notice-on-its-new-mexico-stargate-data-center/)
4. [GuruFocus via Yahoo Finance, "GE Vernova Falls 1.3% as $200 Billion Backlog Test Approaches," 24 September 2026](https://finance.yahoo.com/markets/stocks/articles/ge-vernova-falls-1-3-192859746.html)
5. [24/7 Wall St., "GE Vernova Climbs 5% as CEO Sees Backlog Hitting $200B Early; Eaton and Quanta Services Edge Higher," David Moadel, 16 September 2026](https://247wallst.com/investing/2026/09/16/ge-vernova-climbs-5-as-ceo-sees-backlog-hitting-200b-early-eaton-and-quanta-services-edge-higher/)
6. [GE Vernova press release via MarketScreener, "GE Vernova advances asset longevity for Egypt's power sector with Rotor Life Extension services," 23 September 2026](https://www.marketscreener.com/news/ge-vernova-advances-asset-longevity-for-egypta-s-power-sector-with-rotor-life-extension-services-ce785ad9dd8bf326)
7. [World Nuclear News, "GE Vernova, Hitachi, SGE and Samsung C&T sign BWRX-300s MoU," 23 September 2026](https://www.world-nuclear-news.org/articles/ge-vernova-hitachi-sge-and-samsung-ct-sign-mou-on-bwrx-300s-in-europe)
8. [Energies Media, "GE Vernova commissions Vietnam's first LNG power plant and announces $200 million HVDC manufacturing facility at Hanoi summit," Kelly Lippke, 20 September 2026](https://energiesmedia.com/ge-vernova-vietnam-lng-hvdc/)
9. [Investing.com via Yahoo Finance, "UBS sees rising reliance on AI capex as a key growth risk," Sam Boughedda, 24 September 2026](https://finance.yahoo.com/technology/ai/articles/ubs-sees-rising-reliance-ai-134045684.html)
10. [Semi Doped, "Daily Update, September 25th, 2026," 25 September 2026](https://daily.semidoped.com/p/daily-update-september-25th-2026)
11. [Sharadar quarterly fundamentals, from GE Vernova's SEC filings, retrieved 27 September 2026](https://www.sec.gov/cgi-bin/browse-edgar?action=getcompany&CIK=0001996810)


---

Who stands on the other side of GE Vernova's $176 billion backlog — The Inference. Canonical: https://theinference.org/article/who-stands-on-the-other-side-of-ge-vernova-s-176-billion-backlog