Akamai says it is turning away 2027 cloud business for lack of power

Akamai's cloud unit is turning away 2027 customers because it cannot power the machines, while the line renting compute to Anthropic runs at $109 million a quarter against a 2027 guide of up to $1.3 billion. Anthropic, the anchor tenant on the backlog, begins trading on Nasdaq today.

Vincent JiangVincent Jiangthree-minute read
Share
Tom Leighton, Akamai's chief executive and co-founder, in a dark suit and blue tie, photographed in front of an office window
Tom Leighton, Akamai's chief executive and co-founder. The company says it is turning away 2027 AI cloud business because it cannot power the machines.

A backlog it cannot plug in

At RBC's technology conference on November 17, Akamai−0.39% — Akamai, down 0.39 percent today chief financial officer Ed McGowan said demand for AI cloud capacity is strong enough that some 2027 business is being turned away because power and data-center space are tight 16. Chief executive Tom Leighton put the backlog at more than $14 billion of multi-year commitments signed this year, led by $11.6 billion over seven years from Anthropic$350B — Anthropic, private, latest valuation $350B 23.

The shares jumped 8.75% to $92.05 on November 18, helped by a deal putting Akamai's security software into Microsoft's−1.72% — Microsoft, down 1.72 percent today Edge for Business browser, and rose about 3% more on November 19 as Anthropic began trading after raising a record $81.3 billion at $83 a share 769.

Two and a half times today's pace, by 2027

The line carrying the promise, Cloud Infrastructure Services, rents dedicated computing to labs including Anthropic. It booked $109 million of revenue in the September quarter, up 34%, an annual pace of about $435 million 2. The company's own 2027 guide for that line is $1.1 billion to $1.3 billion, two and a half to three times the current pace, on the way to more than $7 billion of total revenue in 2028 2. About $30 million has already slipped from the December quarter into 2027 on deployment delays 5.

Akamai's 2027 cloud guide is up to three times the current pace

Q3's annualized $435M pace is well under half the low end of the 2027 guide

  • Estimate
$0M$500M$1,000M$1,500MQ3 2026 annualized$435M2027 guide, low end$1,100M2027 guide, high end$1,300M
Data
Value
Q3 2026 annualized$435M
2027 guide, low end (estimate)$1,100M
2027 guide, high end (estimate)$1,300M
Cloud Infrastructure Services revenue: reported Q3 2026 revenue of $108.8M times four, against company guidance for 2027. Source: Akamai Q3 2026 results, November 5, 2026.2

Paying 2027 rates in 2026

The bills are due now. Cash capital spending tripled year over year to $605 million in the September quarter, and capex ran at 41% of revenue, double a year earlier 210. GAAP operating margin fell six points to 10%, trailing net margin slid to 8.8% from 12.3%, with more fourth-quarter pressure flagged from colocation, the rent paid for data-center space 28.

The build is contracted as well as physical: a seven-year Lenovo hardware agreement, and manufacturer Jabil−0.09% — Jabil, down 0.09 percent today authorized to buy about $1.7 billion of memory components 3. The Inference traced the deal's spend-now, pay-later shape in October; the cash flow statement now shows it in dollars 3.

Capital spending tripled in the September quarter, before the big contracts pay

Q3 2026 capex of $605M was triple the year-ago quarter

$0B$0.2B$0.4B$0.6B$0.8BQ4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26Q3 '26Lenovo and $1.7B Jabil supplydeals signed
Data
Quarterly capex
Q4 '24$0.16B
Q1 '25$0.2B
Q2 '25$0.22B
Q3 '25$0.2B
Q4 '25$0.21B
Q1 '26$0.19B
Q2 '26$0.23B
Q3 '26$0.61B
Akamai cash capital spending by quarter, in $ billions, from its SEC filings: $0.163B in the fourth quarter of 2024 and $0.605B in the third quarter of 2026. Source: Akamai quarterly filings, retrieved November 19, 2026.10,11

Everyone financing the build is paid above today's price

The $2.5 billion of convertible notes closed on November 12, an offering that launched at $2.2 billion on November 9 before buyers took their options in full, carry a 1.00% coupon and convert at $112.41 and $102.37, 11 to 22% above the November 18 close 4. Anthropic's warrant over up to 7.74 million shares, an effective strike of $111.33, vests in stages as it pays and commits more 3. McGowan expects EBITDA margins and cash from operations to rise significantly beginning in 2027 4.

February's report prices the first revenue and the colocation bill

The bears hold real exhibits: Evercore−1.38% — Evercore, down 1.38 percent today ISI downgraded the stock on financing concerns, Goldman Sachs−2.85% — Goldman Sachs, down 2.85 percent today cut its target to $73, 13% of the float is sold short, and Anthropic, which lost $1.3 billion on operations in the first nine months of 2026, can terminate a project plan on notice of a material outage 6593. The bulls answer with a signed backlog and a median analyst target of $124 1. February's fourth-quarter report prices the first revenue from the big contracts and the size of the colocation bill. The revenue is signed and the servers are ordered; the missing input is electricity.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading AKAM

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Riot Platforms must refinance $20.8 million drawn on a $573 million Rockdale bridge by December 31

    The Rockdale bridge, and the Corsicana project-debt raise behind it, are the first market-priced test of Anthropic's $37 billion of rent, the worry behind Keefe, Bruyette & Woods' November 11 downgrade.

    Data Center

    Ford won't force AI data centers on Ontario cities that say no, stranding Prologis's 40-megawatt project

    Ontario's premier said he would rather respect a city's freeze than override it, a day after Prologis and Montcrest appealed Mississauga's ban to the Ontario Land Tribunal. The stance strands a 40-megawatt project in a year-long tribunal queue and lands on Prologis shareholders, who own a 5.8-gigawatt data center pipeline.

    Data Center

    Fastly jumps 12.6% on a Comcast deal built for GTA VI's 212 GB launch-day download

    Shares closed up 12.6 percent at $17.90 on a launch-day partnership that names no price. The quarter underneath leans on download traffic Fastly itself calls one-off, and February's report separates the game from the business.

    Data Center

    Arista Networks launches edge routers using up to 60% less power as supplier commitments hit $11.4 billion

    At SC26, Arista pushed its routers out of the data center toward users, promising up to 60% lower power than rival edge platforms by building on 5-nanometer Broadcom silicon. The bet lands on a balance sheet carrying $11.4 billion of supplier commitments and a gross margin already sliding, so the edge must arrive before the parts bill does.

    Data Center

    Lenovo posts record $30.2 billion revenue and a $640 million loss on Alat warrants

    The record quarter is real, and so is the loss: a $1.9 billion non-cash mark on the warrants Lenovo sold with its $2 billion Saudi convertible bond deal. Shareholders now price one number the release does not settle, whether a record 9.6% server margin survives the cycle.

    Data Center

    Bitcoin fell below MARA's $62,862 mining cost for the first time since August

    MARA Holdings funds its AI data-center build by selling bitcoin, and those sales now clear the cost of mining a coin by about 2%, down from 29% six weeks ago. The 8.75% notes behind its Long Ridge purchase close November 27, and the leases meant to repay them still have no tenant.

    Subscribe to TheInference for free