Power

Xcel filed a Texas tariff to lock data centers into 15-year contracts with exit fees

A tariff filed with Texas regulators on September 28 would make data centers fund their own transmission and generation, with 15-year commitments and exit fees. The same week, Colorado bills rose $5.16 a month and Xcel agreed to exit Michigan: one utility moving its capital from legacy territory to contracted AI load.

Vincent JiangVincent Jiangthree-minute read
Share
Keith Ellison speaking at a Minnesota DFL convention, holding a microphone and raising a finger
Keith Ellison, now Minnesota's attorney general, at a Minnesota DFL convention. His office argues Google's Pine Island data center agreement could leave Xcel's other customers with roughly $1 billion in net costs.

The tariff that names who pays

On September 28, Xcel Energy+0.53% — Xcel Energy, up 0.53 percent today asked the Public Utility Commission of Texas to approve a large-load tariff making data centers and other huge users pay for the transmission, substations, interconnection upgrades and new generation their projects require 12. The terms read like a lender's covenant: commitments typically of 15 years or more, financial security if a project is delayed or scaled back, minimum monthly payments while usage ramps up, and exit charges to recover project-specific infrastructure if a customer walks early 2. Xcel says it has already advanced large-load tariffs in other states and expects to file next in New Mexico 1. "These projects can drive economic opportunity in the communities we serve, but it's critical that growth is handled the right way," said Brad Baldridge, interim president of Xcel Energy Texas and New Mexico 1.

The fight that produced it

The filing answers a live political fight over who pays for AI power. In Minnesota, Attorney General Keith Ellison's office argues Google's Pine Island agreement could leave Xcel's other customers with roughly $1 billion in net costs, against Xcel's projection of more than $1.1 billion in net benefits; the project sits on hold pending an environmental review 34. In Colorado, Xcel's own April tariff plan for loads above 50 MW covers an estimated 2 GW of new data-center demand by 2031, with poles and wires alone possibly costing more than $1 billion, company estimates show 5. And from October 6, Colorado households pay $5.16 more a month for gas under a $123 million settlement regulators cut from a $190 million ask 6.

Ohio already ran this experiment

The template exists. In 2025, Ohio approved AEP's data-center tariff: qualifying facilities pay for at least 85% of contracted capacity for up to 12 years, with collateral and exit charges 7. AEP Ohio said in February it holds 17,861 MW of data-center contracts through 2035, about 70% above its historic peak demand 7. Per the Ohio Consumers' Counsel, Amazon−2.75% — Amazon, down 2.75 percent today, Google, Microsoft−1.86% — Microsoft, down 1.86 percent today and Meta−4.82% — Meta, down 4.82 percent today fought that binding tariff and backed a softer alternative; on September 30 they signed a voluntary pledge to cover their full energy costs 84. The pledge is voluntary. The tariff is not.

The capital is already committed

Xcel's capex has outrun its operating cash in 11 of the last 12 quarters

  • Capital spending
  • Operating cash flow
$0B$1B$2B$3B$4BQ4 '23Q2 '24Q4 '24Q2 '25Q4 '25Q2 '26$2.95B
Data
Capital spendingOperating cash flow
Q3 '23$1.64B$1.9B
Q4 '23$1.61B$0.97B
Q1 '24$1.54B$1.05B
Q2 '24$1.83B$1.19B
Q3 '24$1.78B$1.74B
Q4 '24$2.22B$0.66B
Q1 '25$1.99B$1.03B
Q2 '25$2.43B$1.08B
Q3 '25$3.06B$1.77B
Q4 '25$3.44B$0.21B
Q1 '26$3.02B$1.7B
Q2 '26$2.95B$1.1B
Quarterly figures from Xcel Energy's SEC filings, in billions of US dollars, Q3 2023 through Q2 2026. Source: Xcel Energy SEC filings [9].9

Xcel is spending like a company that expects the fight to break its way: quarterly capital spending has roughly doubled since 2023 while operating cash flow has gone sideways, leaving the buildout funded increasingly by debt and equity rather than the meter 9.

The quiet third leg

On October 6, Xcel also agreed to exit Michigan: 6,000 gas customers to SEMCO, 9,000 electric customers to Upper Peninsula Power, 15,000 customers across two counties in all, closing in 2027 with financial terms undisclosed 1011. Small legacy territory out, contracted AI load in: read together, the week is one capital reallocation.

Three regulators, three verdicts

Three regulators now hold the thesis: the PUCT on the Texas tariff, the Colorado PUC on the April plan by year-end, and the Minnesota PUC on the Google agreement 153. Approval hands Xcel a data-center pipeline that arrives contracted rather than contested; nothing in the record yet says CenterPoint or DTE follow the same path. Every utility with a data-center queue faces the same fork: contract the load, or litigate the bill.

ProceedingRegulatorWhat it decidesStatus
Large-load tariff for data centersPublic Utility Commission of TexasCommitments typically of 15 years or more, minimum monthly payments and exit charges for huge new loadsFiled September 28
Large-load tariff planColorado PUCTerms for loads above 50 MW, covering an estimated 2 GW of new data-center demand by 2031Decision expected by year-end
Google Pine Island agreementMinnesota PUCRoughly $1 billion in claimed net customer costs against more than $1.1 billion in projected net benefitsOn hold pending environmental review
The three regulatory decisions over Xcel's data-center load, per sources 1, 3 and 5.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading XEL

Reader comments

0 comments

    Power

    An Indiana county asks American Electric Power to suspend a 75-mile line behind its $100 billion plan

    AEP's growth case, 84 gigawatts of new contracted load and $100 billion of spending through 2031, needs land, ballots and regulators to say yes. On Nov. 17 an Indiana county board asked the utility to suspend one of the transmission lines behind it, two weeks after voters restricted data centers in 40 of 41 ballot contests.

    Power

    Southern Company closed a $2 billion equity-unit sale at 8.625%, a third of it paid in stock

    Underwriters took their option in full on November 17, and only 5.50 of the 8.625 points is cash interest; the rest is paid in stock out of Southern's equity. Three days later Alabama Power handed $160 million of the same data-center revenue back to ratepayers.

    Power

    Ameren asks Missouri to bill customers for its 2,100 MW gas plant while it is built, cost still redacted

    Ameren pressed the request at a Nov. 18 hearing, with the plant's cost still redacted in its own filings. The financing ruling decides who pays during construction: Missouri bills if it is granted, Ameren's $38.1 billion plan and $5 billion of new equity if it is refused.

    Power

    Alabama Power files to cut 2027 rates by $160 million, crediting data centers

    The Southern Company utility says data centers that pay their own way will cut a typical Alabama home's bill by more than $50 a year from January. It lands while US electricity inflation runs 4.4 percent and utilities elsewhere seek $23 billion of increases.

    Power

    Iberdrola says it fixes data-center power prices for 20 years in Spain, where 88% of grid requests fail

    Spain let in 12% of grid-access requests in 2025, and Iberdrola's Spain chief says the data-center money has already applied to plug in. The 20-year fixed price he described turns AI power demand into contracted cash for Iberdrola shareholders and locks the biggest cost line in a data center's budget.

    Power

    Illinois cuts WEC's Peoples Gas rate increase 72% to $40 million as 15 banks market up to $4 billion of stock

    The order is the second regulator trim of a WEC Energy utility in two weeks. It lands while 15 banks market up to $4 billion of WEC stock for a $47.5 billion data-center build whose biggest customers pay on terms no rate case can touch.

    Subscribe to TheInference for free