A $90 million Korean filing says Sanmina's AI racks are still selling. The tape says otherwise.

A Korean supplier's mandatory filing shows a third straight year of data-center orders flowing to Sanmina's India operations, worth about $90 million, even as the stock shed 30.4% in four weeks. Both camps get tested at the November 9 fiscal-year report.

Vincent JiangVincent Jiangthree-minute read
Share
Rows of white server racks in a data center hall in Amravati, India
1 / 6Slide 1 of 6
Server racks at Pi Datacenters in Amravati, India. A Korean supplier's filing shows data-center orders still flowing to Sanmina's India operations.

On October 21, a small Korean component maker named Vinatech halted trading of its own shares under a KOSDAQ rule that forces disclosure of outsized contracts 1. The reason: a supply deal worth 119.47 billion won, about $90 million, to ship supercapacitors, the backup-power parts inside server racks, to Sanmina+2.46% — Sanmina, up 2.46 percent as of its last quote for data centers in India 1. The contract equals 145.30% of Vinatech's entire 2025 revenue, and it is the third consecutive year the two companies have signed a deal like this 1.

That filing is a paper trail most American investors never read. It says orders are still reaching Sanmina's India operations, 14 months after Sanmina paid AMD $2.4 billion in cash plus 1,151,052 shares, with up to $450 million more contingent, to buy ZT Systems' data-center manufacturing business and become a preferred rack maker for AMD's+12.15% — AMD, up 12.15 percent today AI clusters 4.

Revenue doubled. The stock fell anyway.

The delivered numbers back the filings. Fiscal Q3 2026 revenue came in at $3.46 billion, up 69.7% year over year, and non-GAAP diluted EPS of $3.31 beat the $2.77 consensus 5. Management guided fiscal 2026 revenue up to $14.0 billion to $14.3 billion and called demand "strong" for fiscal 2027 and into 2028 5.

Sanmina's revenue doubled the year after it bought ZT Systems

$1B$2B$3B$4B$5BQ2 '24Q4 '24Q2 '25Q4 '25Q2 '26$3.46B$2.1B$3.19B$4.01B
Data
Revenue ($B)
Q1 '24$1.84B
Q2 '24$1.84B
Q3 '24$2.02B
Q4 '24$2.01B
Q1 '25$1.98B
Q2 '25$2.04B
Q3 '25$2.1B
Q4 '25$3.19B
Q1 '26$4.01B
Q2 '26$3.46B
Sanmina's revenue doubled the year after it bought ZT Systems7

The tape tells the other story. SANM closed at $229.04 on October 2, a $12.3 billion market cap, with the average analyst price target already sitting below it at $198.33 6.

Four weeks later the stock had lost 30.4%, trading at an RSI of 25.99, deep in oversold territory, and the market cap at the October 20 peak alert had shrunk to about $9.06 billion 23. A market cap drop of roughly $3 billion against a quarter that beat estimates is the whole argument in one line: the market has stopped paying an AI price for an EMS assembler, whatever the order book says 23.

Both camps have receipts

Zacks rates SANM a #2 Buy and notes consensus EPS estimates were raised 2.1% over the last 30 days, the buyers' case that the selling has exhausted itself 2. The sellers' case: even 69.7% growth rides on a customer concentration and thin-margin assembly model that Wall Street Zen cut from strong buy to buy, and analysts never chased the stock up 6.

The dispute gets a referee on November 9, when Sanmina reports fiscal Q4 and full-year 2026 results 3. The company guided to $3.3 billion to $3.6 billion in revenue and EPS of $3.05 to $3.35 5. What matters more than the beat is the backlog line: if three consecutive years of Indian supercapacitor orders show up as contracted demand, the filing trail was right. If the momentum builds as management promised 5, the discount was the trade. The tell arrives November 9 at 5:00 PM ET 5.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading SANM

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Nvidia's $6.3 billion CoreWeave order survives a Huang exit, but the next financing does not

    A day after CoreWeave beat guidance and swore off bond markets, D.A. Davidson told investors to stay away because Jensen Huang was the real backstop. The filings say the order outlasts him; the next financing round is what would miss him.

    Data Center

    Johnson Controls and Armada ship first modular AI data center from Dublin to Norway on just 9 MW of orders

    A Johnson Controls plant in Dublin is now continuously building modular AI data centers, and the first unit has left for Fossefall in Norway. One buyer stands behind the firm orders, and the same morning JPMorgan turned wary on AI-linked industrials.

    Data Center

    Keefe Bruyette downgrades Riot Platforms on Anthropic tenant risk, $23 target vs Jefferies' $28

    A day after Jefferies more than doubled its target to $28 on the Corsicana lease, Keefe, Bruyette & Woods cut Riot to Market Perform at $23 over tenant credit. The 10-Q names the tenant Anthropic PBC, and Anthropic prices its IPO on November 18.

    Data Center

    CoreWeave named VAST Data a partner, then agreed to buy SSDs directly from Solidigm; backlog $132.5 billion

    CoreWeave's Q3 filing names VAST Data a partner and, in the same document, commits to buying SSDs directly from Solidigm, against a $132.5 billion backlog and $37-39 billion of capex. The question is what a storage software layer is worth when its biggest customer class buys the hardware itself.

    Data Center

    Oracle spent its $20 billion funding cap in five days, then lost Tencent and Microsoft

    Washington killed a $7 billion Tencent chip lease and Microsoft switched off its rented Oracle servers, days after Oracle spent the entire $20 billion it promised not to exceed through fiscal 2030. Bernstein says no more funding is needed; the mid-December quarter report now carries that whole argument.

    Data Center

    IREN's 3-year-old Nvidia H100s re-rented at double the price; $6 billion of its $15 billion build unfunded

    The doubled rent on three-year-old H100s is IREN's proof that GPU collateral holds value. It lands in front of lenders just as $6 billion of the company's $15 billion build still needs raising, and the form of that money decides who carries the risk.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.