CoreWeave's $104.2 billion backlog depends on 2.7 gigawatts it has not switched on

CoreWeave's $104.2 billion revenue backlog rests on 4.2 gigawatts of contracted power, of which only 1.5 gigawatts is switched on. The November earnings report will show whether the backlog is a contract or a construction schedule.

Vincent JiangVincent Jiang · 2 min read
Share
CoreWeave chief executive Michael Intrator testifying at the Senate Commerce Committee hearing on AI, May 8, 2025
1 / 6Slide 1 of 6
CoreWeave chief executive Michael Intrator at the Senate Commerce Committee's "Winning the AI Race" hearing, May 8, 2025. The November earnings report tests the 4.2 gigawatts of power his company has contracted.

CoreWeave's+4.82% — CoreWeave, up 4.82 percent today revenue backlog is the number bulls quote: $104.2 billion of sales contracted but not yet delivered, up 246% in a year, against $7.59 billion of trailing revenue and a $1.93 billion net loss 1. The backlog audited itself on the August 11 earnings call 1. Asked about the growth plan, management said it had contracted 4.2 gigawatts of power while running 1.5 gigawatts switched on 1. So roughly 2.7 gigawatts of the backlog is not a contract so much as a promise about a site, a substation and a local hearing 1.

CoreWeave has contracted 4.2 GW of power but switched on only 1.5 GW

  • Estimate
02468Active, end fiscal Q2 20261.5Year-end 2026 goal1.85Power contracted4.22030 goal8
Data
Value
Active, end fiscal Q2 20261.5
Year-end 2026 goal (estimate)1.85
Power contracted4.2
2030 goal (estimate)8
Gigawatts of data-center power. Active and contracted figures reported by CoreWeave management on its August 11, 2026, earnings call; the 2026 and 2030 figures are management goals, drawn as guidance. Source: Trefis via Yahoo Finance, October 26, 2026.1

Land is the input a cloud company cannot order

Those hearings are already going wrong. On the same call an analyst raised local opposition, and management answered that communities imposing moratoriums will change where CoreWeave builds, not whether, and will not touch guided numbers 1. Land is the one input a cloud company cannot order from a supplier. Meanwhile the debt that pays for the concrete is repricing: insuring CoreWeave's bonds against default costs more than 11%, and the shares are down 41% since October 6 34.

Two camps, one audit date

The camps have split cleanly. Nvidia's+2.18% — Nvidia, up 2.18 percent today Jensen Huang calls neocloud demand "off the charts" 25. Chamath Palihapitiya expects 2027 compute "bought and paid for but effectively underearning, or collecting dust," and Elon Musk, answering him, forecast "guppy-level death" for most of the sector's 200-plus companies 35. Bernstein analysts studied thousands of planned US data centers and concluded only about 35% of announced capacity gets built: "Press releases are cheap … concrete is not" 3.

Nebius+1.16% — Nebius, up 1.16 percent today and Iren, both Nvidia-backed like CoreWeave, defend demand and say customers keep coming 5. Fine. But the audit date is set. CoreWeave reports in November, and it has raised its year-end target to more than 1.85 gigawatts of active power from 1.5 at fiscal Q2's close 1. If that number comes in light, the $104.2 billion backlog is a schedule, not a contract 1. If it lands, the skeptics own a harder question. Watch the gigawatts, not the backlog.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading CRWV…

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Murati's Thinking Machines just took on Firmus's delivery risk

    Mira Murati's lab signed its models to Firmus's Asian AI factories mid-fundraise. The contract is real, but so is the US$3 billion Firmus must raise first, and the OpenAI termination clause shows what a delay would cost.

    Data Center

    Nebius's NEOM demand receipt is a preliminary agreement sitting under a one-year loan

    The Saudi framework Nebius signed at GTC Berlin is billed as proof of international demand, but a preliminary agreement for capacity that arrives in 2027 does not collateralize a loan due in 364 days.

    Data Center

    Jane Street paid $109 a share for CoreWeave now near $54, with $6 billion of rented compute on the line

    The quant trading firm paid $109 a CoreWeave share in April and now marks it at about $54. Its $6 billion of rented AI compute depends on a landlord whose interest bill is growing faster than its revenue.

    Data Center

    Comfort Systems beat everything, refused the AI labs, and the stock fell 9%

    Comfort Systems beat every estimate and booked a record $17.8 billion backlog, yet CFO Bill George told investors the company has not reached terms it would accept from frontier AI labs and colocation providers. The stock fell 9 percent anyway, and investors must judge discipline against lost growth.

    Data Center

    A $90 million Korean filing says Sanmina's AI racks are still selling. The tape says otherwise.

    A Korean supplier's mandatory filing shows a third straight year of data-center orders flowing to Sanmina's India operations, worth about $90 million, even as the stock shed 30.4% in four weeks. Both camps get tested at the November 9 fiscal-year report.

    Data Center

    Databricks charges $7 per H100 GPU-hour, 2.4 times the market rate, and caps a node at eight GPUs

    AI Runtime, Databricks' serverless GPU service, went generally available on October 21 at $7.00 per H100-hour, about 2.4 times the market rental rate. The docs cap a node at eight GPUs and warn regional capacity can run out.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.