Amazon says its cloud is largely sold out through 2027 while $3 billion a month of Nvidia racks wait for power

Andy Jassy says Amazon's cloud is booked into 2028 and the company could spend well past its $220 billion plan. The "dark GPU" receipts show the other side of the ledger: racks arriving monthly for sites with no electricity, and free cash flow already negative. Thursday's print is the first that can test the two against each other.

Richard TangRichard Tangthree-minute read
Share
Amazon chief executive Andy Jassy speaking on stage at an Amazon all-hands meeting, gesturing with both hands.
1 / 6Slide 1 of 6
Andy Jassy, Amazon's chief executive, on stage at an Amazon all-hands meeting. On an October 23 podcast he said AWS capacity is largely sold out through 2027, with a good chunk of 2028 gone too.

The claim is about contracts, and the constraint is electricity

Amazon Web Services+0.16% — Amazon Web Services, up 0.16 percent today, the company's cloud division, is sold out. On a October 23 podcast from the venture firm Andreessen Horowitz, chief executive Andy Jassy said 2026 capacity is already spoken for, 2027 is "largely sold out," "a good chunk of 2028" is sold out, and Amazon "could invest a lot more" than its roughly $220 billion capital plan "and it wouldn't be a bad use of capital" 1.

Taken at face value, that settles the demand side of the buildout. But sold out is a statement about contracts, and switched on is a statement about the grid. The grid is where the same company is stuck: Amazon is taking delivery of Nvidia+5.22% — Nvidia, up 5.22 percent today server racks faster than its data centers can power them, the pile-up the industry calls dark GPUs 23.

Amazon broke its own buying rule

The discipline that broke was Amazon's own. On the July 30 call, Jassy described it: servers are bought "a few months before putting them into service, so we have strong visibility into customer demand before we trigger the spend" 4.

August internal emails reported by Business Insider describe the inversion: an Early Rack Receipt process bringing roughly $3 billion of Nvidia GB300 server racks a month, paid for and recorded before deployment, because some United States sites have room for the hardware but no electricity to run it 2. One team saw no "clear forecasted path" to installing what kept arriving 2.

We reported those receipts on October 19 2. What is new is the chief executive selling scarcity on top of them. Amazon calls the warehouse staging "best business practice" and disputes that it lacks an install plan 2.

The idle months land on Amazon's balance sheet

Jassy's own math prices the wait: average break-even on servers and networking gear runs a little under three years 4, and a rack waiting for power starts that clock late. Trailing free cash flow turned negative in the second quarter, the first time since 2023, and Amazon expects it to stay negative for a while 3. The cash leaves before the hardware runs 2, so the carrying cost sits with Amazon rather than with Nvidia, which gets paid on delivery either way.

Amazon's quarterly capex has almost quintupled in three years

$0B$20B$40B$60BQ4 '23Q2 '24Q4 '24Q2 '25Q4 '25Q2 '26Racks now arrive faster than power
Data
Capital spending
Q3 '23$11.3B
Q4 '23$13.35B
Q1 '24$13.94B
Q2 '24$16.39B
Q3 '24$21.28B
Q4 '24$26.05B
Q1 '25$24.26B
Q2 '25$31.37B
Q3 '25$34.23B
Q4 '25$38.47B
Q1 '26$43.23B
Q2 '26$53.08B
Quarterly capital spending in USD billions, from Amazon's SEC filings.5

October 29 has to show racks switched on

Thursday's third-quarter print is the first public test of the sold-out claim 1. Real scarcity shows up as AWS revenue accelerating, alongside an update to Jassy's July target of doubling 2025 power capacity by the end of 2027 4. Cardboard scarcity shows up as revenue that lags the racks.

The buildout remains the right bet, and the evidence points to its constraint having moved from silicon to substations, which is why the grid side now earns the marginal dollar (our October 22 piece on AEP's sold load). The figure that arbitrates the two camps on Thursday is megawatts energized, because power is the only input that turns a booked contract into billed usage.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading AMZN

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    CoreWeave's Q4 interest bill of up to $1.15 billion closes in on its full-year adjusted operating income

    Third-quarter revenue of $3.66 billion beat the company's own guidance and lifted the backlog to $132.5 billion, which answers the demand question for now. The same filing names who funds the next stretch of the build: customers, convertible holders and new shareholders.

    Data Center

    TeraWulf sues its host town of Lansing over public records

    The petition lands a week before Lansing votes on a local law that would prohibit data centers outright, the use TeraWulf's unleased 320 MW Lake Hawkeye campus depends on. Roughly 2.1 GW of the company's controlled capacity has no tenant, and WULF holders own that risk at around $12.

    Data Center

    Rackspace triples capex to $104 million with $92 million of fresh stock while AMD commits to buy nothing yet

    The filing will not say how much of the quarter's $104 million of capital spending went to the AMD GPU build, and the AMD agreement commits the chipmaker to nothing up front: for an agreed deployment it would buy only residual unsold capacity, capped per deployment. Rackspace bridged the quarter with $92 million of newly issued stock while the cloud business that must pay for it shrank 17.2%.

    Data Center

    Fermi bets its stalled campus on three refurbished New Jersey turbines

    The Amarillo developer has $62.5 million of cash, a going-concern note and an unsigned tenant lease, and it is buying cheap used megawatts to fill the gap. Earnings on November 12 will show whether the construction lender exists.

    Data Center

    Sanmina pushed $3.5 billion of loan maturities to 2031

    The same filing that guided fiscal 2027 revenue to $17.5 billion to $19.5 billion lifted the stock about 20 percent after hours. Its other page shows the bank line under the ramp: a term loan topped back to $1.4 billion, $600 million still drawable into 2027, and a profit guide stated only in adjusted earnings.

    Data Center

    MARA rose 11% on a $3 billion AI pipeline its own filing calls not yet contracted; $79 million is signed

    MARA's Q3 letter names more than $3 billion of AI demand and has signed $79 million of it. Investors bidding the shares 11% higher on Tuesday are paying for a four-gigawatt story whose only contracted AI revenue is one take-or-pay GPU deal.