Power

BlackRock's $33 Billion Utility Buyout Got Two Answers: Ohio Drew a Line, Indiana Kept Billing

PUCO approved the $33.4 billion AES takeover with a ban on merger costs in rates and data-center recusals for directors. Indiana's $71 million increase keeps billing 500,000 meters while a rehearing triggered by Google's data center and the buyout itself waits until March 2027.

Vincent JiangVincent Jiangthree-minute read
Share
Larry Fink, BlackRock's chairman and chief executive, in a portrait
1 / 6Slide 1 of 6
Larry Fink, BlackRock's chairman and chief executive. BlackRock's Global Infrastructure Partners leads the consortium buying AES.

Half a million meters, no answer yet

Indiana bills through the $71M increase while the rehearing waits until March 2027

  • AES Indiana base-rate increase in effect
  • Estimate
$0M$20M$40M$60M$80MJun 2025Jul 2026Jan 2027Mar 2027$71M$71MPhase one: 500,000+ accounts startpayingEvidentiary hearing on therehearing
Data
AES Indiana base-rate increase in effect
Jun 2025$0M
Jul 2026$71M
Jan 2027$71M
Mar 2027 (estimate)$71M
Annualised base-rate revenue AES Indiana may collect above the prior rate, in millions of US dollars, from the June 2025 filing through the March 2027 evidentiary hearing. The March hearing date is the scheduled proceeding that could revisit the whole order, not an approved outcome. Sources: Hoosier Enquirer [1]; WXIN Fox59 [9].1,9

Indianapolis households began paying phase one of AES Indiana's+0.34% — AES Indiana's, up 0.34 percent today $71 million increase on 27 July 2026. Phase two, about $8.50 a month for a typical household, lands in January. The evidentiary hearing that could revisit the whole order sits in early March 2027, and more than 500,000 accounts are living inside that gap 1.

The $33.4 billion math

BlackRock's Global Infrastructure Partners, EQT Infrastructure VI−2.52% — EQT Infrastructure VI, down 2.52 percent today, CalPERS and the Qatar Investment Authority are paying $15.00 a share for AES: about $10.7 billion in equity, $33.4 billion with debt 2. Stockholders approved it on 26 June 2026 with roughly 98 percent of votes cast, and closing is expected late 2026 or early 2027 23. The fund behind the bid targets up to 20 percent gross annual returns, against roughly 9 percent for public utilities over the past decade 4. AES Ohio is separately seeking a $143 million rate increase 4.

The bid targets 20% gross returns against roughly 9% for public utilities

  • Annual return
  • Estimate
0%5%10%15%20%Buyout fund target, grossPublic utilities, past decadeImplied by the 17-cent spread9%
Data
Annual return
Buyout fund target, gross (estimate)20%
Public utilities, past decade9%
Implied by the 17-cent spread (estimate)1.15%
Annual return rates in per cent. The first two columns are the gross annual return the fund behind the bid targets and the approximate past-decade return for public utilities, as cited by the Private Equity Stakeholder Project [4]. The third is not a return forecast: it is the 17-cent gap between the $15.00 offer and the $14.83 share price on 25 September 2026, annualised over the roughly four months to the expected close [2][12].2,4,12

Ohio's answer: the bill is not the exit

PUCO authorized the change of control on 17 September while barring merger costs from customer rates, ordering directors with data-center interests off data-center votes, and requiring three years of updates 57. The recusal proviso is unusual enough that trade press flagged it alone 6. PUCO also noted the limit of its reach: it regulates the utility's conduct, not who owns the parent 5.

AES asked Indiana for $193M and got $71M; Ohio's $143M ask is still open

  • Estimate
$0M$50M$100M$150M$200MAES Indiana asked, June 2025 filing$193MAES Indiana approved, June 2026$71MAES Ohio pending ask$143MPUCO barred deal costs; this case is separate
Data
Value
AES Indiana asked, June 2025 filing$193M
AES Indiana approved, June 2026$71M
AES Ohio pending ask (estimate)$143M
Base-rate revenue requested versus approved or pending, millions of US dollars, across AES's Indiana and Ohio utilities; the Ohio figure is the pending request, not an approved amount. Sources: Hoosier Enquirer [1]; Private Equity Stakeholder Project [4].1,4

The chain that forced the question

A tenant, a plant and the wires

EQT-backed EdgeConneX wants two hyperscale data centers and a dedicated 800 megawatt gas plant in Ashville, Ohio, enough power for roughly 600,000 homes 48. Buy the parent and the consortium holds the tenant, the plant and the wires. Indiana's is sharper: the rehearing was granted solely over Google's Monrovia data center and the buyout, with the Citizens Action Coalition alleging AES executed Google agreements mid-case without correcting sworn testimony 19.

The defense: equity, not leverage

Supporters answer that the purchase is funded entirely with equity, layers on no new debt and leaves credit ratings affirmed, and that AES has signed 11.8 gigawatts of supply agreements with technology firms for 1.1 million utility customers who need the capital 10. PUCO's own order says no rates, terms, employees or operations change because of the merger 57.

Secretary of State Marco Rubio shakes hands with AES chief executive Andres Gluski at an AES liquefied natural gas facility in Colon, Panama, in February 2025
Andres Gluski, AES's chief executive (left), with Secretary of State Marco Rubio at an AES liquefied natural gas facility in Colon, Panama, in February 2025.U.S. Department of State

FERC is the last gate

PJM's Independent Market Monitor has questioned whether the deal's market-power analysis captures BlackRock's utility holdings, and PESP with Public Citizen and the Citizens Action Coalition has asked FERC to block the sale or force a breakup, Docket EC26-99 410. Twenty-three Republican governors, including Indiana's Mike Braun, have signed a pledge that data centers pay the full cost of their own power 11. The stock trades at $14.83 against the $15.00 offer 12. Those 17 cents are the market's charge for everything unresolved above.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading AES

Reader comments

0 comments

    Power

    Global X funds now hold 5.08% of Oklo and 5.61% of NuScale, a bid that moves with ETF flows

    The Street's average Oklo target has collapsed from $117 to $56 while the ETF house behind the sector's theme funds quietly crossed the 5% line in both reactor names. The bid under this theme is turning mechanical, and the same channel can reverse it.

    Power

    PPL paid $9.9 million for a Lancaster farm to wire a data center; 1.5 million customers may share the bill

    A 143-acre Pequea Township purchase anchors 16.4 miles of new wires feeding the Lancaster AI Hub East project. Who pays for the shared parts, the data center's owners or the utility's 1.5 million customers, now sits with Pennsylvania regulators, and the governor has asked to join the case.

    Power

    North Carolina regulators approve Duke's $834 million rate rise and impose 15-year data-center terms

    The November 16 orders set Duke's North Carolina return at 9.8%, below the 10.1% Duke Energy Carolinas earned in its last case, and imposed 15-year minimum contracts and stranded-plant security on data centers above 100 MW. The question for DUK holders is whether a $103 billion AI-load buildout still compounds on the thinner return.

    Power

    Bloom Energy's newest billion-dollar NTT DATA and Google power deals ship nothing until 2027

    The stock trades at 39.2x forward earnings, above GE Vernova and Enphase, yet the NTT DATA 900 MW order and the AEP plant for Google ship nothing until 2027 and 2028 while Q3 cash flow ran negative. The de-rating is a bet on when signed megawatts become invoiced ones.

    Power

    Pinnacle West files 25-year deal making TSMC fund its own power ahead of a December rate decision

    The 25-year contract is the template for every data-center deal that follows it, and it lands before two Arizona regulators elected three days earlier on bill anger. Pinnacle West's growth story now rides on convincing them.

    Power

    Energy Department paid BWXT $68 million for uranium work as its first US new-build order slips to 2027

    The payment has sat unremarked in federal data for eleven days, and the one tracker that noticed coded the award to L3Harris. It is the funded half of BWXT's growth paying out in cash, while the commercial half, the AI-power half, waits on an order that slipped to 2027.

    Subscribe to TheInference for free