Power

Bloom Energy's 63.5x premium rides on Oracle's 2.45-gigawatt campus and a December 7 air-permit hearing

Oracle reaffirmed Bloom fuel cells as Project Jupiter's primary power this week and added no revenue. The campus stands nearly finished without electricity, short an air permit and a gas pipeline, and the hearing that can change that starts December 7, five weeks after Thursday's earnings print.

Richard TangRichard Tangthree-minute read
Share
KR Sridhar, Bloom Energy's chief executive, gestures while speaking during a CNBC interview with Jim Goldman
1 / 6Slide 1 of 6
KR Sridhar, Bloom Energy's chief executive, during a CNBC interview. His fuel cells are Oracle's chosen primary power for Project Jupiter, but the site still lacks an air permit and a gas pipeline.

Oracle+8.70% — Oracle, up 8.70 percent today settled demand this week and left delivery waiting on a permit. The database and cloud company reaffirmed that Bloom Energy's+13.91% — Bloom Energy, up 13.91 percent today fuel cells stay the primary power source for Project Jupiter, its AI campus at Santa Teresa, New Mexico, slated for up to 2.45 gigawatts 12, and posted that construction is "moving quickly" 3.

None of it reaches the fuel-cell maker's order book. The reaffirmation carries no contract value 1, and the backup agreement Oracle proposed with the local utility, El Paso Electric, pays the utility for commissioning and emergencies, which makes it Oracle's money, not Bloom's 24.

The buildings are nearly finished and have no electricity

Bloom's cells make electricity from natural gas on site, which is why Oracle replaced the gas turbines it originally planned with them 2. The campus is approaching completion with no power, and the plot where the fuel cells would sit is empty: construction there has not started, and a truck of sample tanks stood in for the 7,000 cells an Oracle executive says the site needs 5.

Between the buildings and the electrons sit a state air permit and a gas pipeline. The permit hearing, once set for September, now starts December 7, and the hearing officer has said it could slip again 5. A motion to dismiss the application, filed after state modeling showed projected pollutant concentrations doubling, is heard on October 26 56. The pipeline's start date has already slipped to February 2027 7.

Thursday's numbers cannot settle what the multiple prices

Bloom reports after the close on October 22 18. Wall Street models $1.07 billion of revenue on estimates that have sat unchanged for two months, and Zacks' own model predicts no beat, even after four straight ones 8. That figure is essentially level with what Bloom reported for its spring quarter 9. Thursday can confirm a ramp that has already happened. It cannot permit a fuel cell.

Bloom's ramp is already reported; the Street's Q3 estimate asks it to hold that level

  • Revenue
  • Estimate
$0.2B$0.4B$0.6B$0.8B$1B$1.2BQ3 '24Q1 '25Q3 '25Q1 '26Q3 '26E$1.07B$1.07B
Data
Revenue
Q3 '24$0.33B
Q4 '24$0.57B
Q1 '25$0.33B
Q2 '25$0.4B
Q3 '25$0.52B
Q4 '25$0.78B
Q1 '26$0.75B
Q2 '26$1.07B
Q3 '26E (estimate)$1.07B
Quarterly revenue, US dollars. Reported quarters from Bloom Energy's SEC filings; final point is the Zacks consensus estimate for the quarter reported October 22, 2026.8,9

The calendar risk sits with Bloom's holders

The available coverage reads this the other way around: bullish on Bloom as the stronger infrastructure buy, bearish on Oracle as the exposed party, with Baird lifting its target again 1031. The permit record runs opposite for the next two months.

Oracle has issued a force majeure notice shielding it from power-supply delays, lined up utility backup, and can truck gas at roughly four times pipeline cost while it waits; its problem is cost 27. Bloom's problem is conversion. At 63.5 times forward earnings, far above its power-equipment peers, the stock pays out only if fuel cells get permitted and energized 1.

Bloom's forward earnings multiple towers over its power-equipment peers

020406080Bloom Energy63.5GE Vernova43.2Cummins15.9
Data
Value
Bloom Energy63.5
GE Vernova43.2
Cummins15.9
Forward 12-month price-to-earnings; Zacks figures as cited on October 21, 2026.1

The bottleneck is a hearing calendar

The fuel cells work and the demand is real. The unfinished hop between them is regulatory, a state air permit and a federal pipeline review, and the premium belongs to whoever moves that paperwork forward 57. Both dated steps, the dismissal motion and the permit hearing, fall after the earnings call meant to reassure holders. Thursday will show what Bloom has already shipped; the multiple gets decided five weeks later.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading BE

Reader comments

0 comments

    Power

    MARA sold 13,597 bitcoin for $1.1 billion after FERC cleared its $1.5 billion Long Ridge gas plant buy

    FERC's clearance turns December into a double deadline for MARA: close the $1.5 billion Long Ridge gas plant, and sign the AI leases it still lacks. Analysts are split from $11 to $20 on what the unsigned megawatts are worth.

    Power

    Southern Company can sell 12 million shares at any moment as its capital plan could reach $100 billion

    Southern Company, Georgia Power's parent, can now sell stock the moment it chooses after filing an automatic shelf on November 10. The capital plan behind the filing could approach $100 billion, its remaining equity is unpriced, and in January a new Democratic majority arrives on Georgia's utility commission with authority over who pays.

    Power

    Duke Energy asks Florida for 300 MW of solar and a $1 billion savings claim, six days after a data-center loss

    The filing claims $1 billion of lifetime customer savings, but that number is avoided fuel cost, not a bill credit, and it lands six days after the same commission unanimously rejected Duke's data-center cost plan. For Duke shareholders, commissions reading this arithmetic decide whether the $103 billion build gets paid.

    Power

    Talen Energy sells 750 MW of capacity for $100 million a year, keeps the power merchant

    The seven-year Guernsey deal locks in the leg of the business Talen can price and leaves the electricity merchant, in a zone its own 10-Q shows trading far below the PJM market. It de-risks the leveraged AI-power trade that TLN holders own.

    Power

    Gov. Spanberger moves to force NextEra's sealed fitness memo into the $67 billion Dominion merger hearing

    The State Corporation Commission's evidentiary hearing starts November 17 with a ruling due by January 11, while traders who bet on deal spreads treat approval as near-certain. A rate freeze, a rate cap or a fitness finding would reprice both stocks.

    Power

    PG&E freezes $2 billion of grid spending as California's wildfire liability law stalls

    California's utility regulator now calls the liability rule underneath PG&E's hardening boom unsustainable, and a November 19 vote could cut its 5,000-mile burial plan to about 1,100 miles. PCG shareholders are forgoing rate-base growth to protect the balance sheet; ratepayers may pay either way.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.