Oracle Bought the Option to Pay Late. Bloom and Blue Owl Carry the 2028 Date

Oracle filed contract language on 24 September that lets it defer payments if Project Jupiter misses its 2028 online date, then reaffirmed the 2.4-gigawatt order that notice hedged against. Five sessions of tape show who underwrites the date.

Vincent JiangVincent Jiangthree-minute read
Share
A row of Bloom Energy fuel-cell servers installed on paving outside a glass office building
1 / 6Slide 1 of 6
Bloom Energy fuel-cell servers, the boxes behind the 2.4-gigawatt Project Jupiter order Oracle reaffirmed on 29 September after a force majeure notice hedged the 2028 online date.

The marker: Bloom gets the week back in one session

Bloom Energy−13.43% — Bloom Energy, down 13.43 percent today rose as much as 13% on 29 September after Oracle−6.58% — Oracle, down 6.58 percent today reaffirmed the 2.4-gigawatt fuel-cell order behind Project Jupiter, the AI campus rising near Santa Teresa, New Mexico 15. The session also credited a second document: Bloom has taken another 158,000 square feet in Fremont, California, nearly the size of the 164,000-square-foot plant it already runs there 2. Oracle, whose reassurance did the lifting, slipped about 1% on the day it delivered it 3.

The rewind: one notice, five sessions

On 24 September Oracle sent a force majeure notice to Blue Owl Capital, owner of the builder Stack Infrastructure, preserving the right to defer payments if the campus is not online in 2028 as planned 5. Oracle closed down 3.5% with its credit default swaps at a record, Blue Owl fell 3.6%, and Bloom dropped as much as 7% 857. Arm−11.67% — Arm, down 11.67 percent today fell about 7% to near $305.50 on read-through alone: its architecture sits under Oracle's cloud processors, and a deferred campus defers the CPU demand meant to fill it 6.

Roughly $18 billion of construction loans on the campus were already quoted at 89 to 91 cents on the dollar 5. Bloom recovered 8.7% on 25 September after saying Oracle "remains committed" to the 2.4 gigawatts 4. On 28 September it gave that back, down 8.7% as the notice revived financing concerns and the loans were quoted below 90 cents 9.

Oracle's paperwork moved its suppliers; Oracle itself barely moved

-1001020Oracle, 24 Sep (close)Arm, 24 Sep (intraday)Bloom, 24 Sep (intraday)Bloom, 25 Sep (close)Oracle, 25 Sep (intraday)Bloom, 28 Sep (close)Bloom, 29 Sep (intraday)8.7-8.7Force majeure notice lands2.4 GW order reaffirmed
Data
One-day move
Oracle, 24 Sep (close)-3.5
Arm, 24 Sep (intraday)-7
Bloom, 24 Sep (intraday)-7
Bloom, 25 Sep (close)8.7
Oracle, 25 Sep (intraday)-1
Bloom, 28 Sep (close)-8.7
Bloom, 29 Sep (intraday)13
One-day share price moves in percent as reported each session; (close) marks reported closing moves and (intraday) marks moves reported as session extremes. Arm holds no Jupiter contract; it trades on read-through demand for data-center CPUs.1,3,4,5,6,7,8,9

The pattern: the option sits with Oracle, the date with everyone else

The notice is routine for Oracle and load-bearing for everyone else. A filing bought the right to pay late; Bloom's order book, Blue Owl's buildings and the desks holding $18 billion of loans all sit on 2028 holding. The schedule rests on permits none of them controls.

New Mexico's environment department has until 23 November to rule on the air permit for the 2,462-megawatt fuel-cell microgrid, which cannot begin construction without it 10. The gas line feeding the cells has slipped from August to February 2027, and federal regulators have not yet authorized building it 10. In July the microgrid's developer told the state it stood to lose $325 million a month beginning in November 10.

The counterweight: everyone says nothing changed

Oracle calls such notices commonplace on projects of this scale, saying they "do not, by themselves, establish a project delay" 10. Stack says the companies remain "fully aligned" and the notice "does not change the financial commitments" 5. Bloom declined to answer questions about the microgrid's construction status and commissioning schedule, referring to a social media statement 10. The statements address intent. The permits decide the date.

The fork: 23 November prices 2028

If the permit lands and gas flows by early 2027, the notice stays paperwork and lenders get repaid at par. If either slips, Oracle's deferral right activates against the same counterparties that just spent five days trading on its reassurance, and $325 million a month becomes someone's income statement. The next hard reading on 2028 is a state ruling due 23 November 10.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading ORCL

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Arista Networks co-founder's preset trading plan sold $56 million of stock two days before a 12% drop

    Andreas Bechtolsheim's preset trading plan averaged $187.04 a share on November 18; two sessions later Arista closed at $167.62, down 11.6 percent. The Form 4 reached EDGAR after Friday's close, so the drop's coverage does not carry it, and it lands on a company that owes suppliers $11.4 billion on the view that AI demand keeps growing.

    Data Center

    Everpure fell 13% after a 51% revenue quarter, trading below its insiders' $98.88 sale price

    Two sessions after a 51% revenue quarter and a third straight guidance raise, Everpure fell 13% on November 20 to near $92, under the $98.88 low of the November 10 insider sales and just above UBS's $89 Sell target. Twenty analysts average $149.53; that $58 gap is the disagreement investors are now pricing.

    Data Center

    Atreides and SCGE paid $423 million for Ciena shares now worth about a third less

    Atreides Management and SCGE Management disclosed the stakes this week, set at Sept. 30 prices weeks before the post-election AI slide. Ciena's December 10 report is the first document that can say who was right.

    Data Center

    Hut 8 fell 15% the day after Anthropic's $119.5 billion IPO; $10.7 billion of River Bend rent is unsigned

    Anthropic closed its second session at $88.30, near its $83 IPO price, and the listing pitched as fresh money for Hut 8's expansion gave back its debut gain within a day. Of River Bend's potential $17.7 billion in lease value, $10.7 billion is renewals that Google does not guarantee and Anthropic has not signed.

    Data Center

    Mutual funds hold Equinix 7 basis points light as Blackstone pays a 7% yield

    Large-cap mutual funds now hold Equinix seven basis points below its benchmark weight, three days after Blackstone's new trust paid a 7.0% cap rate for Amazon-leased data centers. Two prices for the same AI real estate, and the public REITs sit between them.

    Data Center

    Arizona's attorney general asks Cochise County to delay vote on SpaceX's $50 billion data center

    Kris Mayes wants the December 9 zoning vote held until state and federal reviews are done, three days after a Texas county rejected SpaceX's Starbase tax break. The spending those campuses must justify is already committed: $48.1 billion out the door and $44 billion of chip debt borrowed at up to 8.36%.

    Subscribe to TheInference for free