FERC clears AES's $15.00-a-share sale to BlackRock's GIP and EQT; close set for December 2
The last contested approval is gone, and four private owners take a utility already contracted to power Google's data centers. The market-power warning from PJM's independent monitor did not slow the order, and the cost risk stays with Indiana and Ohio ratepayers.
Richard Tangthree-minute read
The last regulatory gate closed on Tuesday, and AES shares+0.34% — AES shares, up 0.34 percent today became a dated payment. The Federal Energy Regulatory Commission issued its final order on November 17, 2026, and AES expects the merger to close on or about December 2: each share converts to $15.00 in cash, and the stock leaves the New York Stock Exchange 1.
The buyers are Global Infrastructure Partners, part of BlackRock−0.56% — BlackRock, down 0.56 percent today, and the Infrastructure VI fund of EQT−2.52% — EQT, down 2.52 percent today, the Swedish infrastructure investor, alongside co-underwriters CalPERS, the California public pension fund, and the Qatar Investment Authority, Qatar's sovereign wealth fund 12. After December 2, whatever this power company compounds belongs to those four owners rather than public shareholders 12.
The spread is gone; only the calendar is left
AES closed Tuesday at $14.97, pinned to its cash-out price as it has been for months 3. In August, with FERC still the last contested approval, the stock sat near $14.75 4. Holding to a mid-December close then paid about 3.5 percent for the wait 4. That discount was the price of regulatory risk, and the order removed it: stockholders, the Committee on Foreign Investment in the United States, Ohio's utility commission and the European Commission had already cleared the deal 13.
AES has traded pinned to its $15.00 cash-out since summer
The last contested approval is gone; only the calendar is left
Data
| Value | |
|---|---|
| August 19, 2026 | $14.75 |
| 17 Nov close | $14.97 |
| 17 Nov after hours | $14.99 |
The buyers get the utility that powers Google
State regulators have approved AES Indiana's $1.3 billion solar, storage and transmission project to power a Google data center in Monrovia, under a contract of at least 15 years in which Google−0.03% — Google, down 0.03 percent today pays the project's costs 5. Demand of that kind needs capital, and AES told regulators the acquisition improves its access to capital for grid investment 6. That is the gap the deal closes: contracted data-center demand, now with a private balance sheet behind it.
The objection FERC approved over
Senator Elizabeth Warren and four House members urged FERC to block the sale, citing Global Infrastructure Partners' target returns of 15 to 20 percent against a 10 percent historical median for regulated utilities, and the risk that data-center growth lands on utility bills 6. The Independent Market Monitor for PJM, the watchdog over the regional grid operator serving the Mid-Atlantic and Midwest, separately found the acquisition would increase AES's structural market power across utilities serving about a million customers in Indiana and Ohio, with nothing offered to mitigate it 7.
AES answered that the acquisition is not expected to affect rates, that Indiana and Ohio customers would pay none of its costs, including the purchase premium, and that AES Indiana and AES Ohio remain regulated by local, state and federal authorities 16. FERC approved anyway, issuing the final suspensory order the deal required 1.
December 2 settles the deal, not the rates
Watch the close on or about December 2, the delisting from the NYSE, and whether the monitor's market-power finding resurfaces where rates are actually set, in Indiana and Ohio proceedings 17. Shareholders were paid to leave; the cost question stays with the customers who were not.
Get Deals by email, free
The acquisitions, rounds and contracts that move AI money. In our daily email, every weekday.






Reader comments
0 comments