Iron Mountain's raised 2026 forecast still sits below Wall Street's $8.04 billion

A record leasing quarter, a 15% dividend increase and a lifted outlook, and the shares still fell 8.1%: the raised forecast lands below the street. The question for AI-infrastructure money is what a signed megawatt backlog is worth before it starts billing.

Richard TangRichard Tangthree-minute read
Share
William Meaney, chief executive of Iron Mountain, speaking at a Horasis conference
Iron Mountain chief executive William Meaney. His leasing program signed a record 102 megawatts of data center capacity in the third quarter.

Iron Mountain−0.06% — Iron Mountain, down 0.06 percent as of its last quote, the records-storage company that also builds data centers for the cloud platforms behind AI, beat Wall Street's estimates and raised its 2026 forecast on November 5, and its shares still fell 8.1% 1. The reason is mechanical: the raise lands below the street, with full-year revenue guided to $7.95–8.02 billion against an $8.04 billion consensus 23. Because the new forecast still sits under the street, the fall prices the signed data center backlog at nothing until it starts billing.

The quarter beat; the guide did not

Revenue rose 13.5% to $1.99 billion 4, and adjusted FFO, the cash earnings measure that real estate investment trusts report, came to $1.53 a share against a $1.48 consensus 5. Fourth-quarter revenue was guided to about $2.03 billion against a $2.05 billion estimate 3. The Q4 adjusted-FFO guide of about $1.57 also came in below analyst estimates; only the adjusted-EBITDA guide of about $780 million matched consensus 6. JPMorgan cut its price target to $124 from $147 the next morning 2. The shares closed November 6 at $106.52, below their 20-, 50- and 200-day averages 1.

The Q4 guide lands under the street even after 13% growth

The raise still leaves the fourth quarter short of consensus

  • Revenue
  • Estimate
$0B$1B$2B$3BQ4 '24Q1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26Q3 '26Q4 '26EQ4 street consensus
Data
Revenue
Q4 '24$1.58B
Q1 '25$1.59B
Q2 '25$1.71B
Q3 '25$1.75B
Q4 '25$1.84B
Q1 '26$1.94B
Q2 '26$2.03B
Q3 '26$1.99B
Q4 '26E (estimate)$2.03B
Quarterly revenue, US billions; reported quarters from SEC filings, Q4 '26 is company guidance. Reference line is the Q4 analyst consensus.2,3,9

A signed lease becomes revenue only when the power comes on

Chief executive William Meaney's leasing program signed a record 102 megawatts of data center capacity in the quarter, 74 of them in India 7, and the revenue backlog now stands at $575 million 8. That capacity earns nothing until its buildings energize: about 325 megawatts are permitted with committed power, roughly two-thirds at the Richmond campus in Virginia, and come online over the next 24 months 7.

Once energized, the backlog would bill nearly $1.8 billion a year, against 2027 data center revenue guided above $1.3 billion 8. Holding that runway open cost $545 million of growth capex in the quarter 8.

Q3 growth: the AI-facing businesses outrun the records engine

The growth portfolio grows far faster than the business paying for it

0%10%20%30%40%50%Asset lifecycle management43%Data center34%Global RIM (records)7%
Data
Value
Asset lifecycle management43%
Data center34%
Global RIM (records)7%
Year-over-year revenue growth by business, Q3 2026, as reported on the earnings call.8

The records business pays for the wait

The waiting is financed by the original business. Global records and information management, still the bulk of Iron Mountain, produced a record $630 million of adjusted EBITDA at a 44% margin 8. That cash stands behind a dividend the board raised 15% to $0.993 a quarter, with the payout ratio held in the low 60s 78. Net lease-adjusted leverage sits at 4.8 times, the lowest since before the 2014 conversion to a real estate investment trust 8.

Iron Mountain records center: vaults of boxed records and data tapes beside a shred plant
The original business: records vaults, data tapes and a shred plant at an Iron Mountain records center. Global RIM produced a record $630 million of adjusted EBITDA in the third quarter.Rmayer27310 via Wikimedia Commons

Two dates now decide what the backlog is worth

We covered the short case against this data center build on October 30 1. What is new this week is that a record leasing quarter, a raised forecast and a dividend increase still left the shares below every major moving average 1. At the November 6 close, the raised dividend is about a 3.7% yield, and the records business covers it 18.

The leases are contracted and the power is committed. What the market stopped doing this week is paying for that schedule in advance, so the discount holds until the revenue appears in a quarterly report. Two disclosures could close it. One is a segment-reporting update promised for the next earnings call, which would let investors value the storage engine and the data center build separately. The other is an investor meeting and site tour in early March 78.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading IRM

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    CoreWeave's Q4 interest bill of up to $1.15 billion closes in on its full-year adjusted operating income

    Third-quarter revenue of $3.66 billion beat the company's own guidance and lifted the backlog to $132.5 billion, which answers the demand question for now. The same filing names who funds the next stretch of the build: customers, convertible holders and new shareholders.

    Data Center

    TeraWulf sues its host town of Lansing over public records

    The petition lands a week before Lansing votes on a local law that would prohibit data centers outright, the use TeraWulf's unleased 320 MW Lake Hawkeye campus depends on. Roughly 2.1 GW of the company's controlled capacity has no tenant, and WULF holders own that risk at around $12.

    Data Center

    Rackspace triples capex to $104 million with $92 million of fresh stock while AMD commits to buy nothing yet

    The filing will not say how much of the quarter's $104 million of capital spending went to the AMD GPU build, and the AMD agreement commits the chipmaker to nothing up front: for an agreed deployment it would buy only residual unsold capacity, capped per deployment. Rackspace bridged the quarter with $92 million of newly issued stock while the cloud business that must pay for it shrank 17.2%.

    Data Center

    Fermi bets its stalled campus on three refurbished New Jersey turbines

    The Amarillo developer has $62.5 million of cash, a going-concern note and an unsigned tenant lease, and it is buying cheap used megawatts to fill the gap. Earnings on November 12 will show whether the construction lender exists.

    Data Center

    Sanmina pushed $3.5 billion of loan maturities to 2031

    The same filing that guided fiscal 2027 revenue to $17.5 billion to $19.5 billion lifted the stock about 20 percent after hours. Its other page shows the bank line under the ramp: a term loan topped back to $1.4 billion, $600 million still drawable into 2027, and a profit guide stated only in adjusted earnings.

    Data Center

    MARA rose 11% on a $3 billion AI pipeline its own filing calls not yet contracted; $79 million is signed

    MARA's Q3 letter names more than $3 billion of AI demand and has signed $79 million of it. Investors bidding the shares 11% higher on Tuesday are paying for a four-gigawatt story whose only contracted AI revenue is one take-or-pay GPU deal.