NextDC fell 42% after a Melbourne suburb's parked cars delayed the power line for its M3 data center

Australia's largest listed data-center developer lost as much as 45 percent of its market value on October 21 after residents of one Melbourne suburb stopped the power line its M3 campus was waiting for, forcing a full-year guidance cut. The delivery gap, not demand, is now the constraint investors price.

Richard TangRichard Tangtwo-minute read
Share
Craig Scroggie, chief executive and managing director of NextDC
1 / 5Slide 1 of 5
Craig Scroggie, NextDC's chief executive, whose company cut fiscal 2027 guidance after a power-line delay at its Melbourne M3 campus

The buyers are ready and the delivery is not, and that difference just cost NextDC+5.58% — NextDC, up 5.58 percent today almost half its market value. Australia's biggest listed data-center developer fell as much as 45 percent to A$5.07 on Wednesday after cutting fiscal 2027 guidance because the power line to its Melbourne M3 campus slipped to fiscal 2028; the stock closed down 42 percent at A$5.35 12. The binding constraint on the AI build-out has moved from chips and signed customers to grid connections and community consent.

A suburb's cars and shovels delayed the power line

The chain runs through one street in Maribyrnong, west Melbourne. Grid operator Jemena suspended high-voltage pole work in September after residents parked cars across access routes and backfilled trenches, and says work cannot restart before February 2027; the council is withholding consent while it consults the community 13. Because Victoria's government enters caretaker mode on November 3 before the November 28 election, the planning decision on M3 stages 6 and 7 is deferred to 2027 3.

NextDC stripped about A$140 million of contracted revenue and EBITDA from guidance, cutting net revenue to A$475-500 million and EBITDA to A$245-265 million 12. It paused all new developments and land purchases, is weighing force majeure on the affected contracts, and warns that service-level credits could push EBITDA below even the new range 13.

The new fiscal 2027 guidance: A$140 million stripped from contracted revenue and EBITDA

  • from
  • to
A$0MA$100MA$200MA$300MA$400MA$500MNet revenueA$475MA$500M+5.3%EBITDAA$245MA$265M+8.2%
Data
fromtoChange
Net revenueA$475MA$500M+5.3%
EBITDAA$245MA$265M+8.2%
NextDC's revised fiscal 2027 guidance after the M3 power-line delay, in millions of Australian dollars. About A$140 million of contracted revenue and EBITDA was removed; service-level credits could push EBITDA below the new range. Sources: KuCoin News (1), RTTNews (2).1,2

This is a repricing, not a demand verdict

Demand is not the problem here: contracts are signed and construction of the data halls continues. But the market had priced NextDC at roughly 37 times fiscal 2027 EV/EBITDA against a 22 times global peer average, and UBS expects no profit before fiscal 2031 with debt peaking at A$11.2 billion 1. At that entry price, a delivery slip of one year is a valuation event, not a rounding error.

The same force is visible beyond Melbourne: Bloomberg counts at least 106 US data-center projects blocked or delayed this year, worth about $198 billion, and Oracle+0.47% — Oracle, up 0.47 percent today has invoked force majeure on its New Mexico campus over permitting and power 1. Goldman Sachs−0.12% — Goldman Sachs, down 0.12 percent today initiated NextDC at Neutral eight days before the crash, calling capital "the real brake" and flagging a funding gap above A$1 billion 1.

The concrete thing to watch is NextDC's board decision at the November 20 annual general meeting on selling development sites no longer needed, the results of a full capital-expenditure review due by that date 3. Then watch Jemena's February 2027 restart 3. AI demand is real, and the reward now goes to whoever closes the power gap: behind-the-meter generation, and sites built with the community's consent rather than against it.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading ORCL

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    NetApp counts 350 AI deals instead of reporting AI revenue, and insiders sold 33 times without buying

    NetApp closed its Peak:AIO purchase with no price disclosed, in the same week the books closed on a period of insider selling: 33 sales in six months, not one purchase. The stock's premium rests on an AI business the company has never reported as a revenue line.

    Data Center

    Microsoft can wait out data-center protests; its landlord Pure Data Centres cannot, with $1 billion at stake

    Activists broke into Microsoft's Amsterdam data-center site at the start of a 16-country protest weekend. The exposure is not Microsoft's; it belongs to the developers and miners paying interest before revenue, and Texas just moved against them.

    Data Center

    Texas Governor-elect Gina Hinojosa wants a SpaceX pause as Goldman syndicates $40 billion of chip debt

    Goldman and Apollo are syndicating $40 billion of SpaceX chip debt secured against a Texas buildout that the state's new governor-elect wants paused. Lenders bought pre-election terms into a post-election state.

    Data Center

    Fermi's ousted CEO sold $13 million of stock into a 52-week low, then said it 'should be soaring'

    Toby Neugebauer, ousted as Fermi's chief executive in April, sold 7,657,800 shares for about $13 million in three sessions, 5 million of them on the day the stock touched its 52-week low. The next morning he demanded the company be sold, with its only tenant lease unsigned and $62.5 million of cash against a $737.9 million trailing loss.

    Data Center

    Data-center orders tripled at Carrier, and the cost of rolling its debt doubled

    On November 4 Carrier sold $1.5 billion of notes at more than double the coupon of the paper they retire, between record data-center orders and a $3.1 billion European write-down. The coupon is the market's new price for financing the AI buildout's supply chain.

    Data Center

    Oracle's $165 billion New Mexico campus permit slipped past December 7 as lenders sell the debt

    Oracle's $664 billion backlog assumes its biggest Stargate campus switches on. The New Mexico air-permit decision just slipped past December 7, the project's lenders are heading for the exits, and the stock's 8% drop was blamed on politics instead.

    Get the newsletter

    The day's AI and market news, in your inbox every weekday.