Nvidia amended its supply deal with Samsung Electro-Mechanics to add MLCCs, but the dollar figures in its announcement went to Amkor, SPIL and Kinsus. Customer prepayments of $777 million are underwriting the Korean company's buildout instead, and most of those contracts expire in December 2027.

Vincent JiangVincent Jiangthree-minute read
Share
A cardboard carton printed with the Samsung logo and the words "CHIP CAPACITOR (MLCC)" beside a stack of black plastic crates
A carton of Samsung Electro-Mechanics chip capacitors (MLCCs), labelled for the company's Shenzhen unit, photographed in December 2024. Nvidia's amended supply agreement adds these capacitors to the Korean company's remit.

Nvidia signed; the dollars went to other suppliers

Nvidia−2.79% — Nvidia, down 2.79 percent today interim CEO Colette Kress told the November 17 earnings call that Nvidia signed new substrate contracts with Samsung Electro-Mechanics+7.43% — Samsung Electro-Mechanics, up 7.43 percent today and Taiwan's Kinsus, and a packaging agreement with SPIL 1. Samsung Electro-Mechanics (SEMCO), the Samsung group's components arm listed in Seoul as 009150, confirmed a day later that its supply agreement now includes multilayer ceramic capacitors for the first time: the MLCCs that stabilize power delivery in AI servers 2. The shares closed 7.43% higher at 810,000 won 3. The pull from the other end is Nvidia's own quarter, $115.8 billion of revenue up 103%, with $130 billion guided for the next one 4.

Nvidia revenue nearly quadrupled in two years, and its parts suppliers are the bottleneck

$20B$40B$60B$80B$100BQ2 '24Q4 '24Q2 '25Q4 '25Q2 '26$96.22B
Data
Revenue
Q1 '24$26.04B
Q2 '24$30.04B
Q3 '24$35.08B
Q4 '24$39.33B
Q1 '25$44.06B
Q2 '25$46.74B
Q3 '25$57.01B
Q4 '25$68.13B
Q1 '26$81.62B
Q2 '26$96.22B
Nvidia revenue by quarter, in billions of dollars, for the quarters ended April 2024 through July 2026, from its SEC filings. The quarter ended October 2026, reported on November 17, came in at $115.8 billion, with $130 billion guided for the next. Source: Nvidia, quarterly figures from its SEC filings, retrieved November 18, 2026.11

Everyone in the release got a number except SEMCO

Nvidia's release names its money for everyone but the Korean company: nearly $3 billion of multiyear agreements, prepayments included, for Amkor; multibillion-dollar funding for SPIL; and a more than 3.5x expansion of Kinsus' Nvidia-dedicated substrate capacity 5, an investment reported at over $1 billion 6.

For SEMCO the release names no figure; the company says Nvidia is only "considering" additional support for its Sejong and Busan plants 2. Amkor+3.19% — Amkor, up 3.19 percent today got nearly $3 billion, Kinsus got more than $1 billion, and SEMCO got the word "considering" 2. In October, when the partnership was first announced, no advance was named either; the amendment widens the scope, not the funding.

Its customers are paying instead

What SEMCO has is prepaid demand. Advance payments under long-term supply agreements reached $777 million at end-September, above 1 trillion won for the first time and up 43.9% in three months 78.

Contracts disclosed this year total 5.18 trillion won across more than 50 customers, from TSMC+0.48% — TSMC, up 0.48 percent today, Google, Intel−1.45% — Intel, down 1.45 percent today and Bosch to Nvidia, AMD+4.57% — AMD, up 4.57 percent today, Broadcom+3.56% — Broadcom, up 3.56 percent today and Amazon+3.47% — Amazon, up 3.47 percent today 79, and SEMCO intends to cover a significant share of a 10 trillion won, three-year substrate expansion with them 8. The scarcity is measurable: MLCC lead times run 40 weeks against a normal 12, per TrendForce, and SEMCO holds an estimated 40% of the AI-server MLCC market 28.

Close-up of multilayer ceramic capacitors soldered onto a green printed circuit board, marked C4, C5, C8, C9 and C10
Multilayer ceramic capacitors on a circuit board. AI servers use them by the hundreds of thousands to steady power delivery, and MLCC lead times now run about 40 weeks against a normal 12.Giovanna 27

MLCC prices are up 21.4% and substrate prices 28.1% against last year's average, and the substrate division's revenue rose 58% to 939 billion won 8. Sales to Samsung Electronics+2.31% — Samsung Electronics, up 2.31 percent today, 47.1% of revenue in 2019, have fallen to a record-low 24% 9.

MLCCs and substrates now carry 71% of Samsung Electro-Mechanics' revenue

The AI-facing divisions went from 58% of sales in 2019 to 71%

  • 2019
  • Q3 2026
0%20%40%60%Component (MLCC)Package (substrates)Optical (camera modules)
Data
2019Q3 2026
Component (MLCC)40%47.4%
Package (substrates)18.3%23.4%
Optical (camera modules)41.7%29.3%
Share of total revenue by division, full-year 2019 versus Q3 2026, in percent. Source: Herald Business analysis of Samsung Electro-Mechanics' third-quarter report, November 18, 2026.9

The catch is the calendar

KB Securities expects the wider deal to strengthen SEMCO's customer base and improve revenue visibility 3, and its 3 million won target price is the highest among Korean brokers 10. The exposure is timing: most of the long-term contracts run out in December 2027 9, before the new Sejong substrate factory reaches mass production in September 2028 9, and the shares closed at roughly a third of their June 19 record of 2.27 million won 310. Watch two numbers from here: the year-end prepayment print, and whether "considering" ever gets a dollar figure attached.

Get Chips by email, free

How AI demand is reshaping chipmakers, memory and the fabs behind them. In our daily email, every weekday.

Loading NVDA

More about NVIDIA

NVDAFiscal Q2 2027
Fiscal Q2 2027 · quarter to 26 Jul 2026 · changes vs a year earlier

Revenue rose 106% to $96.2B, 92.5% of it from Data Center, “driven by the ramp of our Blackwell Ultra infrastructure”. Gains on equity stakes of $7.8B lifted net income to $59.7B.

Revenue$96.2B▲ 106%
Gross margin75.0%▲ 2.6 pts
Operating margin66.2%▲ 5.4 pts
Net income$59.7B▲ 126%
Hyperscale$48.7B▲ 102%AI clouds & enterprise$40.3B▲ 138%Data Center$89.0B▲ 117%Edge Computing$7.2B▲ 27%Revenue$96.2B▲ 106%Gross profit$72.1B75.0% marginCost of revenue$24.1BOther income$7.8Bequity-stake gainsOperating income$63.7B66.2% marginOperating expenses$8.4BNet income$59.7B▲ 126%Tax$11.8B16.5% rateR&D$7.1BSG&A$1.4B
Show as a table
LineValue
Revenue$96.2B
Gross margin75.0%
Operating margin66.2%
Net income$59.7B
Hyperscale$48.7B
AI clouds & enterprise$40.3B
Data Center$89.0B
Edge Computing$7.2B
Gross profit$72.1B
Cost of revenue$24.1B
Other income$7.8B
Operating income$63.7B
Operating expenses$8.4B
Tax$11.8B
R&D$7.1B
SG&A$1.4B

Reader comments

0 comments

    Chips

    Suzhou TFC posts 55% Q3 profit growth and buys Thai factory land as a US export rule names Thailand

    The Shenzhen-listed supplier's co-packaged-optics parts are already in batch delivery, while TE Connectivity's rival New York plant opens no earlier than spring 2027. A US export rule effective Thursday names Thailand, where TFC just bought factory land.

    Chips

    Cirrus Logic, which gets 93% of sales from Apple, guides December below last year's $580.6 million

    Cirrus Logic, which supplies the audio, haptic and power chips in Apple's iPhones, held September revenue flat at $559.5 million while its finance chief called the quarter's gross margin a high point. Management says the softer December guide is timing and KeyBanc says Apple cut wafer starts, and the December report decides which is right for a stock that takes 93 cents of every sales dollar from Apple.

    Chips

    Nvidia board rules out Huang return, starts permanent CEO search

    A unanimous board ruling and a hired search firm settle AI's biggest leadership question, on a record quarter reported six days into interim CEO Colette Kress's tenure. For holders and shorts, the risk has moved from who runs Nvidia to what Washington and Beijing let it sell.

    Chips

    B.Riley cuts AXT price target to $43 from $56 on China permit risk

    Washington's curbs on Chinese optical transceivers lifted AXT's biggest customers and pointed straight at AXT's single point of failure: all of its indium phosphide is grown in China and shipped on a Beijing permit. The stock now trades below both the $43 and $90 targets its covering analysts published this month.

    Chips

    Cerebras moves prompt processing to AMD GPUs, claiming 5x tokens per megawatt in production

    With Q4 cloud revenue guided flat because Cerebras has no spare data center capacity, more tokens per megawatt is the only cloud lever it controls until new power lands from mid-2027. Whether its self-measured 5x holds decides how CBRS grows in between.

    Chips

    SiTime launches FemtoClock 4 and VersaClock 8 into a $2 billion AI-rack market

    Both clock families ship now, and SiTime's own five-year sizing lands the same month its data-center segment missed consensus by $19 million and Goldman Sachs cut that segment's estimates. The December quarter, reported in early February, decides whether the launch or the line sets the multiple.