Nvidia is helping fund the replacement of its own copper
Ayar Labs has lifted its 2026 primary funding to $650 million to build optical engines that replace the copper linking AI accelerators. Nvidia, AMD, Intel and Wiwynn are all on the cap table, and Wade's own deadline is volume qualification by the end of 2027.
Vincent Jiangtwo-minute read
$650 million in one year, at two valuations
Ayar Labs$6.45B — Ayar Labs, private, latest valuation $6.45B added $150 million on 10 September, extending the $500 million Series E it closed in March; that round valued the startup at $3.75 billion and took total funding to $870 million 1 2. A $225 million secondary led by Antero Peak Group at Artisan Partners, with Sequoia Global Equities, ARK Invest and Greycroft, let early shareholders out above $5 billion 3.
The strategic list is the tell. Wiwynn−7.34% — Wiwynn, down 7.34 percent today, the Taiwanese rack builder, invested earlier this year, joining Alchip, AMD−5.42% — AMD, down 5.42 percent today, Intel−7.07% — Intel, down 7.07 percent today, MediaTek and Nvidia−4.51% — Nvidia, down 4.51 percent today 1 4. "Copper interconnect is becoming the limiting factor for AI scale-up," chief executive Mark Wade said 1.
Light where the copper used to be
Ayar's TeraPHY optical engine puts photonics inside the package, beside the accelerator, so data leaves the chip as light. The rack it designed with Wiwynn scales to 1,024 accelerators, each carrying more than 100 terabits per second of optical connectivity 5. Wade says AI revenue growth is now capped by scale-up interconnect, that 2 and 4 terabit-per-second chiplets sit in customer labs with an 8 terabit part coming, and that fiber-to-chip coupling is the yield problem 6. One projection puts US silicon photonics at $1.00 billion in 2025, headed to $10.76 billion by 2035 7.
Nvidia is on both sides of the trade
Nvidia co-led Ayar's $155 million Series D with Intel and AMD, then joined the Series E 7 8. In June, Ayar entered the NVLink Fusion ecosystem, making its optics compatible with Nvidia's rack; Wade frames that attach as the real market 6 8 9. The open alternative, the UALink consortium, passed 115 members with optics on its roadmap, and many of the same vendors back both horses 10.
Nvidia hedges the other way too: it has bought into Lumentum, Corning and Coherent−6.59% — Coherent, down 6.59 percent today, and its own co-packaged optics switches are in full production 9. Whether the backplane is copper or light, the toll booth stays where Nvidia put it.
Qualify by 2027, or miss the ramp
Wade's clock is public: customers ramp their products in 2028 to 2029, so Ayar must be qualified for volume production by the end of 2027 3. The rest of this month's photonics wave raised far less 11.
Ayar's $150M top-up out-raises the other three photonics rounds combined
Data
| Value | |
|---|---|
| Ayar Labs add-on | $150M |
| Polaris Electro-Optics | $50M |
| Quintessent | $40M |
| PicoJool | $27.5M |
The interview ran under the banner of a road to an IPO 6. Copper is dying on schedule; the open question is whether its replacement gets built inside Nvidia's rack or against it.
Get Chips by email, free
How AI demand is reshaping chipmakers, memory and the fabs behind them. In our daily email, every weekday.
More about NVIDIA
NVDAFiscal Q2 2027Revenue rose 106% to $96.2B, 92.5% of it from Data Center, “driven by the ramp of our Blackwell Ultra infrastructure”. Gains on equity stakes of $7.8B lifted net income to $59.7B.
Show as a table
| Line | Value |
|---|---|
| Revenue | $96.2B |
| Gross margin | 75.0% |
| Operating margin | 66.2% |
| Net income | $59.7B |
| Hyperscale | $48.7B |
| AI clouds & enterprise | $40.3B |
| Data Center | $89.0B |
| Edge Computing | $7.2B |
| Gross profit | $72.1B |
| Cost of revenue | $24.1B |
| Other income | $7.8B |
| Operating income | $63.7B |
| Operating expenses | $8.4B |
| Tax | $11.8B |
| R&D | $7.1B |
| SG&A | $1.4B |