Nvidia's $3 billion prepayment buys a factory that opens in 2028

Nvidia is prepaying Amkor $3 billion across Arizona and South Korea for packaging capacity that opens in 2028. Lam Research's cleanroom warning explains why the customer pays two years early, and tonight's earnings show whether the shortage has reached Amkor's order book.

Richard TangRichard Tangtwo-minute read
Share
Aerial view of Amkor's Arizona advanced packaging campus under construction, cranes and steel frames rising out of the desert
1 / 6Slide 1 of 6
Amkor's $12 billion Arizona advanced packaging and test campus under construction in Peoria. Its cleanroom is not due to open until early 2028.

Nvidia+3.65% — Nvidia, up 3.65 percent today is paying Amkor+7.71% — Amkor, up 7.71 percent today $3 billion in advance for packaging capacity that does not exist yet, and Lam Research+8.64% — Lam Research, up 8.64 percent today just told the market why: certified cleanroom space and scarce upstream parts, not demand, are what the AI hardware chain is short of through 2027 123. The $1.3 billion South Korea agreement announced on October 21, on top of July's $1.5 billion Arizona prepayment, buys Amkor's place in a queue, not chips already rolling 123.

Nvidia is prepaying for a cleanroom that opens in 2028

The detail that dates the money: Amkor's $12 billion Peoria, Arizona campus does not open its cleanroom until early 2028 5. Nvidia is prepaying two years ahead because that is how long the bottleneck runs. Amkor cannot bridge the wait on its own; fiscal 2025 capex of $900 million against roughly $1.1 billion of annual operating cash leaves about $200 million of free cash flow, so the customer is financing the factory 3.

Amkor's capex has outrun operating cash in three of the last four quarters

  • Operating cash flow
  • Capex
$0B$0.2B$0.4B$0.6B$0.8BQ2 '25Q3 '25Q4 '25Q1 '26Q2 '26$0.44B
Data
Operating cash flowCapex
Q2 '25$0.26B$0.15B
Q3 '25$0.17B$0.25B
Q4 '25$0.64B$0.33B
Q1 '26$0.15B$0.22B
Q2 '26$0.24B$0.44B
Amkor Technology quarterly figures from its SEC filings, US dollars. Series starts in Q2 2025, after a break in the reported cash-flow series in early 2025.9

The market split over the same fact. Amkor rose 7.1% on the deal, then fell 10.1% the next session after Lam Research said equipment makers cannot meet demand through 2027 because of cleanroom and component shortages 24. Both moves read the same signal: capacity is scarce. The bull case says prepayments prove demand and fund the build; the bear case says the cash lands against 2028 revenue while Amkor, having broken its stock with weak July guidance, still has to execute 36.

One layer down, orders already run at 2.5 times sales

TTM Technologies+6.93% — TTM Technologies, up 6.93 percent today reported commercial board orders at 2.5 times sales, with laminate and glass lead times of 12 to 24 weeks and rising, and its new lines mostly serve 2028 8. Amkor reports fiscal Q3 after the close on October 26, its first print since July, and the closest read on whether packaging shows the same gap 36.

Consensus sees Amkor earnings rising 71% in fiscal 2026

  • Normalized EPS
  • Estimate
$0 per share$1 per share$2 per share$3 per share$4 per shareFY2025FY2026FY2028$1.5 per share
Data
Normalized EPS
FY2025$1.5 per share
FY2026 (estimate)$2.57 per share
FY2028 (estimate)$3.3 per share
Consensus normalized earnings per share for Amkor Technology, in dollars; fiscal 2026 and 2028 are analyst estimates, shown dashed.3

Shares closed Friday at $39.30, well below their 52-week high, at about 13.9 times forward earnings against a 16.0 five-year average, with consensus expecting normalized earnings to jump 71% this year 367. The prepayments turn that build from speculative into customer-funded. What to watch tonight: whether bookings run ahead of shipments. If they do, Nvidia is buying scarce capacity. If not, this is a two-year wait financed by a customer with other packagers.

Get Deals by email, free

The acquisitions, rounds and contracts that move AI money. In our daily email, every weekday.

Loading NVDA

More about NVIDIA

NVDAFiscal Q2 2027
Fiscal Q2 2027 · quarter to 26 Jul 2026 · changes vs a year earlier

Revenue rose 106% to $96.2B, 92.5% of it from Data Center, “driven by the ramp of our Blackwell Ultra infrastructure”. Gains on equity stakes of $7.8B lifted net income to $59.7B.

Revenue$96.2B▲ 106%
Gross margin75.0%▲ 2.6 pts
Operating margin66.2%▲ 5.4 pts
Net income$59.7B▲ 126%
Hyperscale$48.7B▲ 102%AI clouds & enterprise$40.3B▲ 138%Data Center$89.0B▲ 117%Edge Computing$7.2B▲ 27%Revenue$96.2B▲ 106%Gross profit$72.1B75.0% marginCost of revenue$24.1BOther income$7.8Bequity-stake gainsOperating income$63.7B66.2% marginOperating expenses$8.4BNet income$59.7B▲ 126%Tax$11.8B16.5% rateR&D$7.1BSG&A$1.4B
Show as a table
LineValue
Revenue$96.2B
Gross margin75.0%
Operating margin66.2%
Net income$59.7B
Hyperscale$48.7B
AI clouds & enterprise$40.3B
Data Center$89.0B
Edge Computing$7.2B
Gross profit$72.1B
Cost of revenue$24.1B
Other income$7.8B
Operating income$63.7B
Operating expenses$8.4B
Tax$11.8B
R&D$7.1B
SG&A$1.4B

Reader comments

0 comments

    Deals

    Marvell agreed to buy Lumentum for $115 billion, leaving open who supplies the wafers for its AI lasers

    Marvell's $115 billion purchase of Lumentum consolidates the indium phosphide laser layer of AI networking, and four days later UK wafer maker IQE raised guidance on the same boom. The open question is who ends up controlling the wafer layer between them.

    Deals

    Chicago voted 72.5% to bring back ShotSpotter; SoundThinking's tender offer still pays $8.00 cash

    Chicago's November 3 vote, 72.5% for restarting gunshot detection, is the clearest demand signal ShotSpotter has ever won. It cannot reach SoundThinking shareholders: the vote binds no one, the city has awarded no replacement contract in more than two years, and a tender offer prices the stock at $8.00 in cash.

    Deals

    BWX Technologies launched $500 million of 2034 notes after bookings fell to $538 million from $2.25 billion

    BWX Technologies launched $500 million of 2034 notes to retire its 2028 and 2029 paper days after the first U.S. new-build equipment order slipped toward 2027, pre-funding a commercial buildout that has no firm order behind it yet.

    Deals

    Bending Spoons closed $1.25 billion of junk notes at 9.625%, and Airtable's cash services them

    The Milan roll-up settled $1.25 billion of dollar notes at 9.625% and €500 million of euro notes at 8.625%, both due 2032, issued at par, issued by subsidiaries with no parent guarantee. The acquired businesses' earnings must now service roughly $3.4 billion equivalent of new secured debt, and November 20's Q3 is the first check.

    Deals

    Trane to buy coil maker Cancoil as a $12.5 billion backlog outruns its chiller production

    Trane booked record cooling demand last quarter and still gave back margin in two of three regions, so it is buying the companies that make the parts behind its chillers. Whether owning the supply chain buys the margin back is the question underneath the stock.

    Deals

    AXT's record quarter is being repriced in Beijing, and the clock runs out December 20

    Institutional investors signed for up to $545 million of Tongmei, the Beijing subsidiary that makes most of AXT's AI-optics wafers, with the right to demand their money back plus 8% a year if no qualified IPO lands within three years. The agreement terminates on December 20 if it has not closed, and AXTI has fallen about 26% since the day it was signed.