TE Connectivity's $62 million fiber plant has no customer; its growth comes from copper and power connectors

The plant opens in 2027 but ramps to 2031, and the optical products behind it are still in design validation. TE's fiscal 2027 AI growth comes from copper and power connectors, which is why the stock trades at 17.6 times earnings with no AI premium.

Vincent JiangVincent Jiangtwo-minute read

Drafted with AI from the documents listed under Sources, then edited and fact-checked by Vincent Jiang. How we work

Share
TE Connectivity chief executive Terrence Curtin stands at the center of a group of company employees
TE Connectivity chief executive Terrence Curtin, center, with employees. Curtin told a Baird investor event on November 13 that the company's optical products "remain in engineering, prototyping and design validation."

A $62 million plant for a business that has not won a customer yet

New York's governor's office put a number on TE Connectivity's+1.33% — TE Connectivity, up 1.33 percent as of its last quote optical future on November 16: more than $62 million into a 135,000-square-foot fiber-array plant in Henrietta, more than 860 jobs, up to $22 million of state Excelsior tax credits, opening spring 2027 and ramping manufacturing through 2031 1. Two days later the company showed the USFP front connector, built with Nvidia−4.20% — Nvidia, down 4.20 percent today and Cisco+0.49% — Cisco, up 0.49 percent today, running 448G per channel with power delivery separated from signal integrity 2. The optics look real. The revenue is not there yet.

The chief executive says the optics still need a customer

At a Baird investor event on November 13, CEO Terrence Curtin said the optical products from the RAM Photonics acquisition "remain in engineering, prototyping and design validation" and that TE "still needs to win customer programs" 3. That is the honest clock. The fiber plant does not reach full manufacturing scale until 2031 7. Suzhou TFC, the Chinese optical components maker, announced on November 18 that its co-packaged-optics products are already in batch delivery, with supply volume expected to grow from 2027 7. By that clock TE is at least four years behind the CPO wave.

The AI wiring unit is $3 billion of TE's $19.9 billion fiscal 2026

$0B$5B$10B$15B$20B$25BNet sales, FY2026$19.89BOrders, FY2026$22.2BDDN revenue, FY2026$3B
Data
Value
Net sales, FY2026$19.89B
Orders, FY2026$22.2B
DDN revenue, FY2026$3B
TE Connectivity's reported fiscal 2026 figures: net sales of $19,885 million, orders of $22.2 billion and Digital Data Networks segment revenue of a little over $3 billion. Orders are bookings, not revenue, so the bars show scale rather than a like-for-like comparison. Sources: TokenPost (4), Kalkine (5).4,5

The money is in copper for now

Digital Data Networks, TE's hyperscaler wiring unit, generated a little over $3 billion in fiscal 2026 and is expected to add more than $1 billion in fiscal 2027 34. But the growth being bought is not optical: power products are about 30% of DDN revenue and are growing faster than the business, and 800-volt systems could lift TE's content about 1.5 times 3. Companywide, fiscal 2026 orders rose 27% to $22.2 billion, with DDN orders up about 70%, and adjusted earnings per share rose 24% to $11.52 on net sales of $19,885 million 45.

Quarterly revenue has climbed from $3.8 billion to $5.3 billion in three years

  • Revenue
  • Operating income
$0B$2B$4B$6BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26$5.31B
Data
RevenueOperating income
Q4 '23$3.83B$0.7B
Q1 '24$3.97B$0.69B
Q2 '24$3.98B$0.76B
Q3 '24$4.07B$0.65B
Q4 '24$3.84B$0.69B
Q1 '25$4.14B$0.75B
Q2 '25$4.53B$0.86B
Q3 '25$4.75B$0.92B
Q4 '25$4.67B$0.96B
Q1 '26$4.74B$0.95B
Q2 '26$5.16B$0.98B
Q3 '26$5.31B$1.09B
TE Connectivity's reported quarterly revenue and operating income for the twelve quarters from the period ended December 2023 to the period ended September 2026; the company's fiscal year ends in late September, so the labels run one quarter behind its fiscal numbering. Revenue rose 39% and operating income 57% across the twelve quarters. Source: TE Connectivity's quarterly figures from its SEC filings (8).8

The market prices the connector supplier, not the optical entrant

TEL traded at $202.43 on November 20, about 17.6 times adjusted fiscal 2026 earnings 5. First-quarter fiscal 2027 guidance of $5.35 billion in sales and about $3.30 adjusted EPS 5 is a copper-and-power story, not a fiber one. The market is pricing the connector supplier, not the optical entrant.

The counterpoint: Corning is building with Nvidia, Broadcom−0.41% — Broadcom, down 0.41 percent today is pushing co-packaged optics, and TE is betting a connector standard plus a New York plant can catch up 127. Watch for the first named hyperscale design win on the optical side. Until then, the $1 billion of DDN growth lands on shipped products, and the fiber bet stays ahead of the revenue 127.

Sources

  1. 1Plant Services, TE Connectivity plans to open fiber array unit manufacturing facility in New York, 16 November 2026
  2. 2Foro3D, TE Connectivity presents the USFP connector of 448G per channel at OCP 2026, November 2026
  3. 3Transcript Daily, TE Connectivity Sees 12% Growth as AI, Energy and Defense Demand Stay Strong, 16 November 2026
  4. 4TokenPost, TE Connectivity's Digital Data Networks Business Now Generates More Than $3 Billion, November 2026
  5. 5Kalkine, Heavy Trading Activity in TE Connectivity (NYSE:TEL) Stock: Fiscal 2026 Annual Results, Industrial Acquisitions and First Quarter Outlook, November 2026
  6. 7TokenPost (Turkish edition), CPO products entered batch delivery: Suzhou TFC (300394.SZ), 25 November 2026
  7. 8TE Connectivity, quarterly figures from its SEC filings, retrieved 25 November 2026

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading TEL

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Lenders freeze a $49 billion data center loan book serving ByteDance, Alibaba and Tencent

    Washington's new license rule froze the $49 billion loan book built to serve Chinese AI tenants, and the damage lands on Asian operators and their lenders, not on US demand, which inherits the capacity.

    Data Center

    Crusoe's CEO defends its $30.9 billion mark as the market cuts CoreWeave and Nebius roughly in half

    Eight days apart, Crusoe's chief executive told investors the neocloud sell-off is overblown while his $30.9 billion September valuation sits beside a public market that cut CoreWeave and Nebius roughly in half on debt fears. Crusoe's contract book is the test of which price is wrong.

    Data Center

    Riot Platforms sold 20,264 bitcoin in nine months to fund its $28 billion Anthropic lease

    The 10-Q shows the miner emptied its bitcoin treasury to fund the $5.5 billion Corsicana build for Anthropic, selling coins below their cost of production just as bitcoin broke under $59,000, and a $573 million bridge matures December 31.

    Data Center

    Fermi's $200 million prepayment is funded, but Texas Tech needs a signed tenant by December 31

    For shareholders in Fermi (Nasdaq: FRMI), the money puts crews on the Project Matador site near Amarillo, Texas. It does not deliver the signed tenant lease that Texas Tech requires by December 31, 2026, and without that lease or an extension the land deal is back in question.

    Data Center

    Backblaze's new privacy notice says it sold user data to ad networks

    The revised notice, effective December 1, says the storage company sold identifiers, browsing activity and geolocation to ad networks, walking back an April promise. Its most loyal B2 customers noticed; the stock rally did not price them in.

    Data Center

    Digital Realty's 156MW Chicago-area data center wins a 4-2 council vote and a tax break

    Four days after President Trump threatened a "tremendous tax" on US companies building data centers abroad, the Austin landlord's domestic land bank cleared its first zoning test. Its October filing shows the record leasing quarter was led by Asia-Pacific, exactly the half of the pipeline the threat targets.

    Subscribe to TheInference for free