The Power Can Leave Oracle's Data Center. The $18 Billion Cannot.

Bloom Energy's CEO says the fuel cells bound for Oracle's Project Jupiter are "fungible" and can be rerouted after shipping. The roughly 20 banks behind the campus's $18 billion loan, quoted at 89 to 91 cents, can redeploy nothing.

In this storyORCL
Vincent JiangVincent Jiang · 3 min read
Share
A man in a suit rests his hand on a row of dark metal Bloom Energy fuel-cell servers
1 / 6Slide 1 of 6
Bloom Energy's fuel-cell servers, the boxes its chief executive says are fungible enough to redirect to another site after shipping

The trucks can turn around

Bloom Energy chief executive KR Sridhar answered Oracle's force majeure notice on Bloomberg TV on 1 October: the fuel cells headed for Project Jupiter are not married to New Mexico. 1 Bloom boxes are "fungible," he said, because "after they're on the trucks, we can redirect the trucks to go to some other location." 1 He reiterated guidance for this year and next and said Bloom "will not be the constraint"; the stock closed at $277.58 on Thursday and is up more than 181 percent this year, while Oracle is down 28.6 percent. 12 The company line is narrower: Bloom says Oracle remains committed to the 2.4 gigawatt contract on Oracle's planned timeline, and declined questions on construction and permitting. 3

The money cannot move

The notice Oracle sent the developer STACK Infrastructure on 24 September draws the line the other way. 4 The lease is hell-or-high-water: it cannot be terminated, and Oracle owes rent whether or not the power arrives; a force majeure event can push back the start of full rent by up to three years, with an automatic extension so the total paid does not fall. 5 About 20 banks lent $18 billion to build the campus; the loans are quoted at 89 to 91 cents, at least one arranger has sold below 90, and the sales imply a paper loss of at least $1.8 billion. 56 Blue Owl's funds put in about $3 billion of equity and earn the equivalent of 9 percent a year until the rent starts. 5

Six dollars of bank debt ride on every dollar of Blue Owl equity

$0B$5B$10B$15B$20BConstruction loans, ~20 banks$18BSold below 90 cents after the noticeBlue Owl equity$3BPaper loss on the loans, at least$1.8B
Data
Value
Construction loans, ~20 banks$18B
Blue Owl equity$3B
Paper loss on the loans, at least$1.8B
Financing behind Project Jupiter, in billions of US dollars; the loss is implied by loan sales below 90 cents on the dollar and is a floor, not a final tally.5,6

The filing that disagrees with the press release

Oracle says the campus "remains on our planned schedule," and more than 3,600 construction workers are helping build it. 3 The power plant's own permit filing says otherwise: the April application puts construction start "upon permit issuance" and completion in November 2029, a year past the opening. 3 The state's high court lifted its permitting stay on 17 September, and New Mexico must rule on the fuel cells' air permit by 23 November; pipeline gas has slipped to February 2027. 3 The applicant, Yucca Growth Infrastructure, told a July hearing it stands to lose $325 million a month from November. 3

The flooding changed nobody's script

Force majeure notices are common on projects of this scale and "do not, by themselves, establish a project delay," Oracle says. 3 Then the water arrived: flooding reached the campus this week, and Oracle and STACK, working with partners and insurers, said no critical infrastructure was damaged and the schedule holds. 7

23 November decides

Grant the air permit and the $18 billion has a path back toward par. Deny it and the trucks turn around, leaving the banks holding a campus whose rent has not started. The market started pricing the bet after Oracle reaffirmed the contract on 29 September: RBC kept a $335 target on Bloom and Jefferies raised its own to $264. 8 The fuel cells have wheels. The debt does not.

Deepdive

AI-generated from this story and its cited sources. Not investment advice.

Reader comments

0 comments

    Sign up

    Get your curated digest

    After email confirmation, you will receive a daily digest of the most relevant news that matter to your portfolio