A Wisconsin docket now sets the clock on Oracle's $300 billion OpenAI backlog

Aterio sees no meaningful power at the Port Washington campus before mid-2028 against Oracle's second-half 2027 start, and the Public Service Commission of Wisconsin, not the builder, now holds the calendar for the OpenAI slice of a $664 billion backlog.

Vincent JiangVincent Jiangthree-minute read
Share
Larry Ellison speaking on stage, holding a microphone against a dark background
1 / 6Slide 1 of 6
Oracle cofounder and chairman Larry Ellison. A Wisconsin regulator's docket, not Oracle's builders, now sets the pace for the power behind its OpenAI contract.

Oracle−4.06% — Oracle, down 4.06 percent today shares fell 1.8% on Wednesday after Aterio, an infrastructure data provider, published its analysis of Project Lighthouse, the campus Vantage Data Centers is building for Oracle and OpenAI$1.18T — OpenAI, private, latest valuation $1.18T in Port Washington, Wisconsin 1. The Vancouver-based firm sees material risk the 1.3-gigawatt site misses Oracle's second-half 2027 start, with meaningful load unlikely before mid-2028 23. The $15 billion project is not waiting on construction: permits are in hand, work has run continuously since December 2025, and satellite imagery shows two of the four halls enclosed 23.

The power clock restarted in August

The campus cannot operate until American Transmission Co. builds a high-voltage interconnection, and that approval process has started over. ATC's first application spent ten months under review before the Public Service Commission of Wisconsin revoked its completeness finding on 6 August 2026, citing hundreds of post-filing changes to the project's scope; commissioners described a "moving target" 24. Both ATC and the state's ratepayer watchdog called the unanimous revocation a first in recent decades, and ATC refiled in September for a $2.48–2.72 billion project across six counties with up to five new substations 5.

The rating cut has a Wisconsin price

S&P lowered Oracle to BBB-, one notch above speculative grade, on 9 July 2026, citing $90–95 billion of fiscal 2027 capex and a projected $42 billion operating cash deficit 6. Weeks later the commission declined to soften We Energies rules that would require Oracle to post a $7 billion letter of security at more than $100 million a year, because any developer rated below A- must post collateral 7.

Oracle owns the buildings, and the commission owns the electrons

Oracle can enclose halls on its own schedule. It cannot schedule power. The $664 billion backlog, up 46% in a year with roughly $300 billion tied to OpenAI, is meant to convert half to revenue within 36 months 6, and Port Washington is one of the campuses built to carry that contract 37.

Capex outran operating cash in seven of Oracle's last eight quarters

  • Capex
  • Operating cash flow
$0B$10B$20B$30BQ4 2024Q1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026the build outran the grid
Data
CapexOperating cash flow
Q4 2024$3.97B$1.3B
Q1 2025$5.86B$5.93B
Q2 2025$9.08B$6.16B
Q3 2025$8.5B$8.14B
Q4 2025$12.03B$2.07B
Q1 2026$18.64B$7.15B
Q2 2026$16.49B$14.62B
Q3 2026$28.5B$23.1B
Quarterly capital spending versus operating cash flow, US$ billions, from Oracle's SEC filings via Sharadar; calendar-labelled quarters for fiscal periods ending November 2024 through August 2026.9

Aterio's base case gives the site full capacity around October 2028; the 360-day review the Public Service Commission used in every comparable large transmission case Aterio reviewed pushes it to April 2029 2. Lenders have already marked the sibling campus: $18 billion of Jupiter loans trade at 89–91 cents on the dollar 6.

Oracle says nothing has slipped

On 24 September 2026 Oracle sent a force majeure notice on Project Jupiter, its New Mexico campus, that could defer rent payments to the developer for up to three years 28. The company says Jupiter remains on schedule, that force majeure notices "do not, by themselves, establish a project delay or change delivery expectations" 8, and that neither site will touch fiscal 2027 guidance 6.

Oracle did not respond to requests for comment on Aterio's findings 1. The commission, for its part, has ruled on whether ATC's filing was reviewable, not on the merits of the power line 2.

19 October is the fork

The completeness decision expected around 19 October restarts a statutory clock: 180 days under Aterio's base case, 360 under its extension 2. December's fiscal second-quarter report will then show whether the backlog is converting at the guided pace 6. The buildings will be ready first.

Get Data Center by email, free

Who is building AI's data centers, and who is paying for them. In our daily email, every weekday.

Loading ORCL

Reader comments

0 comments

    More in Data Center

    All in this topic →

    Data Center

    Riot Platforms must refinance $20.8 million drawn on a $573 million Rockdale bridge by December 31

    The Rockdale bridge, and the Corsicana project-debt raise behind it, are the first market-priced test of Anthropic's $37 billion of rent, the worry behind Keefe, Bruyette & Woods' November 11 downgrade.

    Data Center

    Ford won't force AI data centers on Ontario cities that say no, stranding Prologis's 40-megawatt project

    Ontario's premier said he would rather respect a city's freeze than override it, a day after Prologis and Montcrest appealed Mississauga's ban to the Ontario Land Tribunal. The stance strands a 40-megawatt project in a year-long tribunal queue and lands on Prologis shareholders, who own a 5.8-gigawatt data center pipeline.

    Data Center

    Fastly jumps 12.6% on a Comcast deal built for GTA VI's 212 GB launch-day download

    Shares closed up 12.6 percent at $17.90 on a launch-day partnership that names no price. The quarter underneath leans on download traffic Fastly itself calls one-off, and February's report separates the game from the business.

    Data Center

    Arista Networks launches edge routers using up to 60% less power as supplier commitments hit $11.4 billion

    At SC26, Arista pushed its routers out of the data center toward users, promising up to 60% lower power than rival edge platforms by building on 5-nanometer Broadcom silicon. The bet lands on a balance sheet carrying $11.4 billion of supplier commitments and a gross margin already sliding, so the edge must arrive before the parts bill does.

    Data Center

    Lenovo posts record $30.2 billion revenue and a $640 million loss on Alat warrants

    The record quarter is real, and so is the loss: a $1.9 billion non-cash mark on the warrants Lenovo sold with its $2 billion Saudi convertible bond deal. Shareholders now price one number the release does not settle, whether a record 9.6% server margin survives the cycle.

    Data Center

    Akamai says it is turning away 2027 cloud business for lack of power

    Akamai's cloud unit is turning away 2027 customers because it cannot power the machines, while the line renting compute to Anthropic runs at $109 million a quarter against a 2027 guide of up to $1.3 billion. Anthropic, the anchor tenant on the backlog, begins trading on Nasdaq today.

    Subscribe to TheInference for free