UBS cuts Cerebras target to $155 from $250 as CEO says data-center builds are behind schedule

The beat and the Microsoft logo were Thursday's story. By Friday, UBS had found the $26.1 billion backlog can shrink when data-center shells slip, and the chief executive weighing how to fund the build said it is behind schedule.

Vincent JiangVincent Jiangthree-minute read
Share
Andrew Feldman, chief executive and co-founder of Cerebras Systems, in a headshot
1 / 6Slide 1 of 6
Andrew Feldman, Cerebras Systems chief executive and co-founder. He said on Friday that the company's data-center builds are behind schedule.

UBS found the backlog behind the pop can shrink

Cerebras rose about 17% after hours on Thursday on a third-quarter beat, a raised outlook and a new cloud customer, Microsoft−0.28% — Microsoft, down 0.28 percent today 1. The day after brought the harder news. UBS kept its Buy rating but cut its target to $155 from $250, after netting down OpenAI's$1.18T — OpenAI, private, latest valuation $1.18T share of the $26.1 billion in remaining performance obligations, the contracted revenue Cerebras+8.48% — Cerebras, up 8.48 percent today has not yet booked, for data-center shell delays that could let OpenAI claim credits 34.

Two details from the same day sharpen it. The quarter's core revenue added back $36.4 million of amortization on customer warrants, tied mainly to OpenAI's 33.4 million warrant shares 3. And Amazon Web Services−1.16% — Amazon Web Services, down 1.16 percent today, Oracle−2.86% — Oracle, down 2.86 percent today and Microsoft, the logos the diversification story rests on, are not yet in that backlog and bring no revenue, on The Next Platform's reading 5. On Friday, chief executive Andrew Feldman said the data-center builds are behind schedule 6.

The quarter beat on the adjusted measure, not on GAAP

Core revenue, which adds back stock-based pay, warrant amortization and some data-center costs, rose 70% to $230.9 million against the $214.7 million analyst consensus tracked by LSEG; GAAP revenue rose 55% to $210.8 million 17. Core cloud revenue grew 272% to $144.9 million, 63% of core revenue, while hardware fell to $68.9 million from $96.8 million 138. Core net income of $29.8 million was the first adjusted profit as a public company; the GAAP net loss widened to $161.2 million 13.

The beat was on the core measure: GAAP revenue missed the $214.7M consensus

$0M$50M$100M$150M$200M$250MCore revenue$230.9MAnalyst consensus$214.7MGAAP revenue$210.8M
Data
Value
Core revenue$230.9M
Analyst consensus$214.7M
GAAP revenue$210.8M
Cerebras third-quarter 2026 revenue on its core, or adjusted, basis against the LSEG-tracked analyst consensus and GAAP revenue. US$ millions. The company's core measure adds back stock-based pay, warrant amortization and some data-center costs. Sources: The Next Web; CNBC.1,7

The guide rose and Microsoft signed in October

The 2026 core outlook rose to $940–960 million from $880–890 million, and the fourth-quarter guide of $310–330 million cleared the $271 million consensus 78. Microsoft signed in October, with revenue from the first quarter of 2027 and terms undisclosed 17. The run is real: three straight quarters above guidance and a sales pipeline up more than tenfold in the quarter, by the chief financial officer's count 38.

OpenAI is most of the backlog, and it can claim credits

OpenAI makes up the majority of the $26.1 billion in obligations, chief financial officer Bob Komin said on the earnings call 9. Fourth-quarter cloud revenue is guided roughly flat, the company said, because land, power and construction delays held back early deliveries to OpenAI 9. UBS's arithmetic gives the slippage a price: when shells arrive late, OpenAI's obligations are netted down and the customer can claim credits, so delay pays OpenAI out of the number investors marked up on Thursday 34.

Tripling revenue in 2027, as Feldman promises 8, off the roughly $950 million midpoint of the new guide implies about $2.85 billion, slightly under the $2.92 billion consensus 17.

Seven hundred megawatts still have to be paid for

Cerebras has 700 megawatts of data-center capacity under contract for delivery by the end of 2027, with new sites in Norway and Finland: a contracted figure, not capacity already running 128. Nine-month spending ran $1.05 billion on property and equipment against $388.9 million consumed by operations, and it ended September with $7.8 billion in cash and short-term investments plus $850 million of debt capacity 18. The squeeze sits late in the year: about $497 million of capital spending and a $341 million operating outflow in the third quarter alone 10.

Capital spending has outrun operating cash in every reported quarter

Q3 alone: $497M of plant spend against a $341M operating outflow

  • Capital spending
  • Operating cash flow
-$500M$0M$500MQ1 '25Q2 '25Q3 '25Q4 '25Q1 '26Q2 '26Q3 '26$497.19M
Data
Capital spendingOperating cash flow
Q1 '25$98.24M-$54.94M
Q2 '25$86.85M-$68.91M
Q3 '25——
Q4 '25——
Q1 '26$131.97M$12.34M
Q2 '26$416.9M-$59.82M
Q3 '26$497.19M-$341.41M
Quarterly figures from Cerebras's SEC filings, US$ millions; Q3 and Q4 2025 are not on file in the series. Source: Cerebras quarterly SEC filings.10

Feldman told CNBC on Friday that Cerebras is weighing financing options to keep up with demand 67. If the next leg of the build is funded with equity, it prices near Friday's close of $108.72 rather than the $185 of the May 14 listing, and the dilution lands below the entry of May's buyers 48.

Analyst targets cluster near the $185 IPO price; the shares do not

UBS cut to $155 after finding the backlog can shrink

$0$50$100$150$200$250Wedbush$205Needham$200Morgan Stanley$178UBS$155Shares, 13 Nov close$108.72IPO price, May 2026
Data
Value
Wedbush$205
Needham$200
Morgan Stanley$178
UBS$155
Shares, 13 Nov close$108.72
Published targets from Investing.com via Yahoo Finance, November 13, 2026; Nasdaq close from MarketScreener; IPO price from Crypto Briefing. US dollars.3,4,8

The next documents decide it: the fourth-quarter report against the $310–330 million guide, whatever financing Feldman has been weighing, and whether Microsoft's revenue starts on time in the first quarter of 2027 37.

Get Chips by email, free

How AI demand is reshaping chipmakers, memory and the fabs behind them. In our daily email, every weekday.

Loading MSFT

Reader comments

0 comments

    Chips

    STMicroelectronics puts its STM32 chip franchise on a November 18 investor call

    Three days after putting a $1.03 microcontroller into production for AI data centers, ST has scheduled a full investor call for one chip franchise; traders bought 35,790 calls, 115% above average, into a disclosure ST has never broken out. Whether management puts a number on the story decides whose money moves.

    Chips

    Sandisk's 8-for-1 split trades Nov. 20 at about $110 a share, but its price floors have never met a downturn

    Sandisk's shares have more than halved since June; on November 20 an 8-for-1 split cuts the $885 ticket to roughly $110 and widens who can take either side of the flash-cycle bet. What the new holders actually buy is a contract book whose price floors have never met a downturn.

    Chips

    Lattice Semiconductor's 130% December-quarter growth guide depends on DDR memory it cannot control

    Lattice's Asia-Pacific president said on November 13, 2026, that a rack missing any one of CPU, HBM or DDR does not ship, and Lattice cannot control DDR; Intel's Lip-Bu Tan said the same day memory prices have risen six or seven times. For a stock at 28 times forward earnings guiding December-quarter growth near 130%, that constraint is the one to price.

    Chips

    GlobalFoundries breaks ground on a $10 billion Japan-funded New York fab it will run for fees

    Japan is putting up as much as $21 billion for two fabs GlobalFoundries will run but not own; the record margins came from photonics on fabs it already has.

    Chips

    Micron's 2027 memory is sold, but $32 billion of contracts cap the price

    Micron has $32 billion of customer commitments behind 26 contracts for most of its 2027 HBM supply, but some of those contracts carry price ceilings, so the open-market 6-to-7-times price surge does not all reach shareholders. The December 16 print decides whose money is at risk.

    Chips

    Intel's CEO says memory prices rose 'six, seven times' as Micron books an 87% margin

    The cost shock behind Intel's fourth-quarter warning now has a number from its own chief executive, and an 87% margin at Micron on the other side of the table. The squeeze has a dated end in Chinese fabs, and that timing is what the stock trades on.

    Subscribe to TheInference for free