Google offers $10.8 million to bring power to its Ohio data center sooner

· 79 sec

The first voluntary, corporate-funded transmission upgrade on a US regulated grid now sits before Ohio regulators. How they rule decides whether hyperscalers can buy speed on the grid, and whose bills fund the rest of AEP's $100 billion buildout.

  1. 0:00American Electric Power · Nov 25
  2. 0:07The joint filing · November 19
  3. 0:20The buildout behind the corridor
  4. 0:28The market's read
  5. 0:35Developing
  6. 0:46Who pays for the grid
  7. 0:53Watch the dockets, then the next contract.
  8. 1:00The market's answer

Subscribe to TheInference for free