Power

AEP counts 84 GW of contracted data-center load; 46 GW of it, in Texas, cannot yet energize

AEP sells investors 84 GW of contracted demand and a $100.4 billion buildout, but half of that load is Texas letters of agreement that obligate no one to buy power, and ERCOT has paused the process that could approve any of it. The stock, at 20.9 times earnings, prices the full headline.

Vincent JiangVincent Jiangtwo-minute read
Share
A wide AEP switchyard of steel lattice and tubular structures carrying high-voltage lines, with a gas-fired power station behind it under a clear blue sky
1 / 6Slide 1 of 6
AEP's Flatlick substation, with the Rolling Hills gas plant behind it. AEP counts 84 GW of contracted data-center load; the Texas wiring that would deliver 46 GW of it sits "not in the plan," as upside.

The press release says 84 gigawatts of "contracted" load by 2031 1. The filing says none of the Texas half of it can switch on yet. On the October 28 call, American Electric Power+0.12% — American Electric Power, up 0.12 percent as of its last quote chief executive Bill Fehrman reported collecting "over $2 billion of cash or collateral just for Texas" from data-center developers 1. The money is real. What it buys is not a contract.

The split the release does not make

Chief financial officer Trevor Mihalik supplied it when he spoke: 35 GW of the 84 sits under firm take-or-pay electric service agreements in PJM and SPP, grids where customers pay for reserved capacity 1. All 46 GW of Texas, 55 percent of the headline, is backed only by letters of agreement under state law SB6, commitments to pursue service that obligate no one to buy a kilowatt 1. In April, a Jefferies−4.25% — Jefferies, down 4.25 percent today analysis counted 36 GW of AEP's then-56 GW Texas book under letters of intent; the number has grown since, the instrument has not 1.

AEP's letter-backed Texas load has climbed from 36 GW to 46 GW since April

  • Texas load under letters of agreement, GW
  • Estimate
35 GW40 GW45 GW50 GWApril 2026 (Jefferies count)Q2 2026 filingOctober 28 call36 GW46 GW
Data
Texas load under letters of agreement, GW
April 2026 (Jefferies count) (estimate)36 GW
Q2 2026 filing40 GW
October 28 call46 GW
Gigawatts of AEP's Texas load that the company counts as contracted but that is backed only by letters of agreement under state law SB6: 36 GW from a Jefferies analysis in April 2026, 40 GW in the company's second-quarter filing, and 46 GW on the October 28 earnings call. Source: Electron Economics.1

A deposit you can mostly get back

The 10-Q behind the call carries a quieter sentence: ERCOT "has currently paused Batch Zero classification and study activity" and "will not authorize large loads to energize until verification is complete" 1. About $1.2 billion of the $2 billion sits in a segregated cash account, roughly $44 per kilowatt across 45 GW, below the $50,000/MW the Texas commission's September rule sets 1. The refund terms let a developer recover most of it, in full if ERCOT allocates zero 1.

The dollars have not followed the gigawatts

AEP raised its 2027 to 2031 capital plan to $100.4 billion, rate base to $162 billion by 2031 2 (The Inference covered the raise itself on October 29). But Texas takes $17 billion of it, mostly reliability work; broader Texas load wiring sits "not in the plan," as upside 1. ERCOT is 55 percent of claimed gigawatts and 17 percent of the dollars 1. Next door, Oncor holds about $6 billion of similar collateral and books it as upside, never as contracted 13.

AEP's capital spending jumped 48% in 2025 and now runs well ahead of its operating cash

  • Capital spending
  • Operating cash flow
$0B$5B$10B$15BFY2020FY2021FY2022FY2023FY2024FY2025$11.91B
Data
Capital spendingOperating cash flow
FY2020$6.25B$3.83B
FY2021$6.43B$3.84B
FY2022$7.88B$5.29B
FY2023$7.53B$5.01B
FY2024$8.03B$6.8B
FY2025$11.91B$6.94B
Capital spending and cash from operations, US dollars in billions, fiscal years ended December 31, from AEP's annual SEC filings. The 2027 to 2031 capital plan of $100.4 billion is a forecast and is not shown. Source: AEP filings.4

December is when 46 GW gets tested

The stock, at 20.9 times earnings after an 84.9 percent three-year run 2, prices all 84 GW. ERCOT files its verification report on December 10 and the commission meets December 17; ERCOT's own general counsel says the study will not be done by April 9, 2027 1. If verification trims the queue, the contracted-load number investors quote falls first. The $2 billion measures intent 1. The wires, not yet.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading AEP

Reader comments

0 comments

    Power

    Bloom Energy's newest billion-dollar NTT DATA and Google power deals ship nothing until 2027

    The stock trades at 39.2x forward earnings, above GE Vernova and Enphase, yet the NTT DATA 900 MW order and the AEP plant for Google ship nothing until 2027 and 2028 while Q3 cash flow ran negative. The de-rating is a bet on when signed megawatts become invoiced ones.

    Power

    Pinnacle West files 25-year deal making TSMC fund its own power ahead of a December rate decision

    The 25-year contract is the template for every data-center deal that follows it, and it lands before two Arizona regulators elected three days earlier on bill anger. Pinnacle West's growth story now rides on convincing them.

    Power

    Energy Department paid BWXT $68 million for uranium work as its first US new-build order slips to 2027

    The payment has sat unremarked in federal data for eleven days, and the one tracker that noticed coded the award to L3Harris. It is the funded half of BWXT's growth paying out in cash, while the commercial half, the AI-power half, waits on an order that slipped to 2027.

    Power

    CPUC proposal would cut PG&E's 5,000-mile undergrounding plan to about 1,100 miles

    A judge has moved $1.7 billion of wildfire costs onto California ratepayers, and on November 19 the commission votes on a cost test PG&E says would strike 3,900 miles from the capital it earns on. The utility has already cut $2 billion from its own 2027 plan.

    Power

    Southern Company prices $1.75B of equity units at 8.625%, forcing stock buys by 2029

    The units pay 8.625% a year and force buyers to take Southern stock by December 2029, funding a data-center build that Georgia's newly Democratic regulators were elected to police.

    Power

    First Solar booked $1.34 billion of profit and negative $837 million of free cash flow in nine months

    First Solar earned $1.34 billion in nine months and still ran free cash flow $837 million negative, with the profit booked as $1.29 billion of uncollected tax credits. After a five-session, $3.2 billion slide with no company news, that gap, not the P/E, is what owners of a 9.9-times-earnings stock are holding.