AEP counts 84 GW of contracted data-center load; 46 GW of it, in Texas, cannot yet energize
AEP sells investors 84 GW of contracted demand and a $100.4 billion buildout, but half of that load is Texas letters of agreement that obligate no one to buy power, and ERCOT has paused the process that could approve any of it. The stock, at 20.9 times earnings, prices the full headline.
Vincent Jiangtwo-minute read
The press release says 84 gigawatts of "contracted" load by 2031 1. The filing says none of the Texas half of it can switch on yet. On the October 28 call, American Electric Power+0.12% — American Electric Power, up 0.12 percent as of its last quote chief executive Bill Fehrman reported collecting "over $2 billion of cash or collateral just for Texas" from data-center developers 1. The money is real. What it buys is not a contract.
The split the release does not make
Chief financial officer Trevor Mihalik supplied it when he spoke: 35 GW of the 84 sits under firm take-or-pay electric service agreements in PJM and SPP, grids where customers pay for reserved capacity 1. All 46 GW of Texas, 55 percent of the headline, is backed only by letters of agreement under state law SB6, commitments to pursue service that obligate no one to buy a kilowatt 1. In April, a Jefferies−4.25% — Jefferies, down 4.25 percent today analysis counted 36 GW of AEP's then-56 GW Texas book under letters of intent; the number has grown since, the instrument has not 1.
AEP's letter-backed Texas load has climbed from 36 GW to 46 GW since April
- Texas load under letters of agreement, GW
- Estimate
Data
| Texas load under letters of agreement, GW | |
|---|---|
| April 2026 (Jefferies count) (estimate) | 36 GW |
| Q2 2026 filing | 40 GW |
| October 28 call | 46 GW |
A deposit you can mostly get back
The 10-Q behind the call carries a quieter sentence: ERCOT "has currently paused Batch Zero classification and study activity" and "will not authorize large loads to energize until verification is complete" 1. About $1.2 billion of the $2 billion sits in a segregated cash account, roughly $44 per kilowatt across 45 GW, below the $50,000/MW the Texas commission's September rule sets 1. The refund terms let a developer recover most of it, in full if ERCOT allocates zero 1.
The dollars have not followed the gigawatts
AEP raised its 2027 to 2031 capital plan to $100.4 billion, rate base to $162 billion by 2031 2 (The Inference covered the raise itself on October 29). But Texas takes $17 billion of it, mostly reliability work; broader Texas load wiring sits "not in the plan," as upside 1. ERCOT is 55 percent of claimed gigawatts and 17 percent of the dollars 1. Next door, Oncor holds about $6 billion of similar collateral and books it as upside, never as contracted 13.
AEP's capital spending jumped 48% in 2025 and now runs well ahead of its operating cash
- Capital spending
- Operating cash flow
Data
| Capital spending | Operating cash flow | |
|---|---|---|
| FY2020 | $6.25B | $3.83B |
| FY2021 | $6.43B | $3.84B |
| FY2022 | $7.88B | $5.29B |
| FY2023 | $7.53B | $5.01B |
| FY2024 | $8.03B | $6.8B |
| FY2025 | $11.91B | $6.94B |
December is when 46 GW gets tested
The stock, at 20.9 times earnings after an 84.9 percent three-year run 2, prices all 84 GW. ERCOT files its verification report on December 10 and the commission meets December 17; ERCOT's own general counsel says the study will not be done by April 9, 2027 1. If verification trims the queue, the contracted-load number investors quote falls first. The $2 billion measures intent 1. The wires, not yet.