Southern Company prices $1.75B of equity units at 8.625%, forcing stock buys by 2029

The units pay 8.625% a year and force buyers to take Southern stock by December 2029, funding a data-center build that Georgia's newly Democratic regulators were elected to police.

Vincent JiangVincent Jiangthree-minute read
Share
Chris Womack, chairman, president and chief executive of Southern Company, smiling with arms folded in a dark suit and tie.
1 / 6Slide 1 of 6
Chris Womack, Southern Company's chairman, president and chief executive. The Atlanta utility priced $1.75 billion of 8.625% equity units on November 12 to fund a data-center build that has outrun its cash flow.

$1.75 billion priced, closing Tuesday

Southern Company+1.21% — Southern Company, up 1.21 percent today, the Atlanta holding company whose utilities serve about 9 million customers across the Southeast, priced 35 million Series A equity units at a $50 stated amount on Thursday, November 12, $1.75 billion in all, settling Tuesday, November 17 12. Underwriters hold a 13-day option on 5 million more units, another $250 million 1.

Each unit is a bond wrapped around a promise. The holder collects 8.625% a year, 3.125% on the stock-purchase contract plus 5.50% on each of two remarketable note series, and owes $50 cash for common stock no later than December 15, 2029 1. The share count floats between 0.4326 and 0.5407 against a $92.47 pricing-day close and a $115.58 threshold 25% above it 1.

The first $1.7 billion goes to debt

Net proceeds of $1.723 billion, $1.970 billion if the option is exercised in full, go first to debt: about $135.3 million retires roughly $125.8 million of 4.50% convertible notes due June 2027, leaving about $335 million of that stack, and the rest repays short-term borrowings of $776 million and funds subsidiaries 1.

The plan grew to $100 billion; the cash flow did not

The scale behind it: a week earlier, executives added about $4 billion to the $81 billion five-year plan from February and said it could reach $100 billion, resting on 21 gigawatts of signed large-load contracts, 7 more in late stages, and data-center usage up 59% year over year in the third quarter 3.

Southern's filing record since that call shows one other securities registration, a November 10 prospectus for its dividend reinvestment plan, so these units are the first money priced since the plan grew 5, a path we charted when the shelf talk began.

The build already outruns the cash engine. Capital spending exceeded operating cash flow in eight of the last twelve quarters, by nearly $2 billion in the first quarter of 2026 4.

Capex outran operating cash in eight of the last twelve quarters

The data-center build outran Southern's cash engine; the equity units fund the gap

  • Capital expenditure
  • Operating cash flow
$1B$2B$3B$4B$5BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26the AI build steps up
Data
Capital expenditureOperating cash flow
Q4 '23$2.76B$1.81B
Q1 '24$2.14B$1.31B
Q2 '24$1.98B$2.69B
Q3 '24$2.21B$3.62B
Q4 '24$2.52B$2.17B
Q1 '25$2.6B$1.25B
Q2 '25$2.64B$2.18B
Q3 '25$3.1B$3.77B
Q4 '25$4.05B$2.6B
Q1 '26$3.2B$1.23B
Q2 '26$3.13B$3.05B
Q3 '26$3.26B$3.6B
Quarterly capital expenditure versus operating cash flow, in USD billions, from Southern Company's quarterly SEC filings. The gap is what the equity units and new borrowings fund.4,9

Customers carry the ramp risk

Chief Financial Officer David Poroch told analysts the data-center contracts carry minimum bills covering at least 100% of the cost of serving them: "Before the kilowatt moves over the meter, we are recovering our costs embedded in those minimum bills" 3. In Southern's telling, if a customer never ramps, the customer still pays.

The referees changed anyway. Democrats won Georgia's governorship and, with Peter Hubbard and Sheila Edwards taking seats, a 3-2 Public Service Commission majority that takes office in January, after campaigns animated by rate hikes and data-center growth 6. Governor-elect Keisha Lance Bottoms has said she will call for a pause on data-center development 7. Chief Executive Chris Womack's answer: "I feel pretty confident about what we have in place," and no one has raised retroactive contract freezes 3.

The first tests land in January and February

The units should list on the NYSE under SONN within 30 days, the over-allotment window runs into early December, and the new commission's first votes land in January 16. The tell is data-center usage, 59% higher at the last reading, with the next count at fourth-quarter results in early February 3. Traders marked the stock down about 1% on pricing day 8. The 8.625% payout is the market's price tag on utility growth capital in this cycle, and Georgia's ratepayers are the ones asked to make it good 8.

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading SO

Reader comments

0 comments

    Power

    First Solar booked $1.34 billion of profit and negative $837 million of free cash flow in nine months

    First Solar earned $1.34 billion in nine months and still ran free cash flow $837 million negative, with the profit booked as $1.29 billion of uncollected tax credits. After a five-session, $3.2 billion slide with no company news, that gap, not the P/E, is what owners of a 9.9-times-earnings stock are holding.

    Power

    Vistra sold 20 years of Texas power to a campus with no tenant to pay its $110 million first-year bill

    New Era Energy & Digital's 10-Q prices the deal at about $110 million a year, take-or-pay, secured by a $116 million letter of credit. It matters because 2028, the first year the power flows, is the year Vistra left only 78% hedged.

    Power

    Fairfax County schools want $100 million if NextEra's $67 billion takeover of Dominion Energy is approved

    Virginia's comment window has closed and oral arguments open Monday in Richmond on the $67 billion NextEra-Dominion merger, with a ruling due January 11. Rejection would hand Dominion a $4.83 billion breakup fee; approval hands the utility serving the nation's biggest data-center market to a Florida parent.

    Power

    Evergy Sees $4 Billion of Generation Behind a Deal Digital Realty Has Not Signed

    A 1.4-gigawatt letter of intent at a former Kansas ammunition plant is the durable news in a weather-inflated quarter. The funding decisions that come first are a Missouri rate order in December and a new capital plan in February; the contract is not expected until the first half of 2027.

    Power

    China's turbine export push aims at GE Vernova's 122-gigawatt queue as Dongfang books 30 in Canada

    Beijing wants an independently controlled gas-turbine supply chain by 2030, and Dongfang Electric booked 30 turbines for Canadian data centers in late October. The five-year queue GE Vernova monetizes, 122 reserved gigawatts inside a $197 billion backlog, sits on the other side of that plan.

    Power

    Michigan AG asks regulators to reopen DTE Energy's 1-gigawatt Google deal, with $44.2 billion riding on it