CPUC proposal would cut PG&E's 5,000-mile undergrounding plan to about 1,100 miles
A judge has moved $1.7 billion of wildfire costs onto California ratepayers, and on November 19 the commission votes on a cost test PG&E says would strike 3,900 miles from the capital it earns on. The utility has already cut $2 billion from its own 2027 plan.
Vincent Jiangthree-minute read
Forty-three miles go first
Twelve miles of planned underground line in Fresno County and 31 in Madera County would all become ineligible under a proposed decision the California Public Utilities Commission issued on October 16 1. The decision writes the cost rules for Senate Bill 884, the 2022 law that created the pathway for ten-year burial plans 2. PG&E says its standardized cost-benefit test would leave about 1,100 of the 5,000 miles in its 2028-2037 plan standing 1.
"So 80% of what we had planned to underground would no longer be eligible," said Matt Pender, PG&E's+3.02% — PG&E, up 3.02 percent as of its last quote vice president of undergrounding and system hardening 2. The commission votes on November 19 2. The filed plan carries roughly $16 billion, about $9 a month on the average bill, for lines PG&E says cut ignition risk about 98% 3. It has buried 1,500 miles since 2021, 325 of them this year 4.
The CPUC cost test would leave a fifth of PG&E's 10-year undergrounding plan standing
PG&E says 3,900 of its 5,000 planned miles become ineligible
- Estimate
Data
| Value | |
|---|---|
| Buried by Nov 2026 | 1,500 miles |
| Filed for 2028-2037 (estimate) | 5,000 miles |
| Eligible under CPUC proposal (estimate) | 1,100 miles |
One docket pays PG&E, the other cuts it
On November 13 a commission judge found ratepayers should pay the $1.7 billion still owed from the 2019 Kincade and 2021 Dixie fires, the first such decision under Assembly Bill 1054; upheld, it clears PG&E to raise rates for the remainder 5. The Inference reported that ruling on November 14 5. Six days later, the same commission votes on striking most of the capital PG&E earns on.
Twelve point eight billion spent, two billion pulled back
The utility spent about $12.8 billion on capital across the four quarters to September 6. On September 2, after the state Assembly let a wildfire liability bill die, it deferred $2 billion of 2027 spending and kept $11.4 billion 7. Guidance beyond 2027 is suspended while a board review spanning ring fencing to sales and separations reports by summer 2027 8.
PG&E's capital spending has topped operating cash flow in 10 of the last 12 quarters
- Capital spending
- Operating cash flow
Data
| Capital spending | Operating cash flow | |
|---|---|---|
| Q4 '23 | $2.61B | $0.48B |
| Q1 '24 | $2.64B | $2.26B |
| Q2 '24 | $2.3B | $0.71B |
| Q3 '24 | $2.61B | $3.13B |
| Q4 '24 | $2.83B | $1.93B |
| Q1 '25 | $2.64B | $2.85B |
| Q2 '25 | $3.07B | $1.06B |
| Q3 '25 | $2.93B | $2.85B |
| Q4 '25 | $3.16B | $1.96B |
| Q1 '26 | $3.36B | $2.43B |
| Q2 '26 | $2.97B | $0.91B |
| Q3 '26 | $3.3B | $2.5B |
Debt stood at $65.5 billion at the end of September, and the below-investment-grade financing issued since 2017 will cost about $4 billion in extra interest 8. One docket hands PG&E $1.7 billion it can bill customers for; the other takes away the wires it bills on 8.
The load still grows, and so does the resistance
Demand is not the problem. PG&E told investors that newly connected data-center capacity reached 174 megawatts by the third quarter, nearly double the 88 at mid-year 9. The sector is leaning in: Duke Energy+1.09% — Duke Energy, up 1.09 percent as of its last quote reaffirmed a $103 billion five-year capital plan this month, and Xcel Energy−0.49% — Xcel Energy, down 0.49 percent as of its last quote rolled out $70 billion 10. PG&E's 2027 core earnings guidance of $1.78 to $1.82 a share still stands 8.
The commission's case is that the test prioritizes the highest fire-threat areas by risk reduction, reliability and cost efficiency, and forces comparison with cheaper options such as covered conductor 2. Consumer Watchdog, an advocacy group, calls the $2 billion deferral "bailout blackmail," and the commission's ratepayer arm moved on October 23 to reopen PG&E's 2027 revenue request so customers do not pay for work no longer planned 11. Three dates decide the next leg: the vote on November 19, capital guidance with February's results, and the review's answer by summer 28.
Get Power by email, free
How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.







Reader comments
0 comments