Power

Alabama Power files to cut 2027 rates by $160 million, crediting data centers

The Southern Company utility says data centers that pay their own way will cut a typical Alabama home's bill by more than $50 a year from January. It lands while US electricity inflation runs 4.4 percent and utilities elsewhere seek $23 billion of increases.

Vincent JiangVincent Jiangthree-minute read
Share
Moses Feagin, chief financial officer of Alabama Power, smiling in a company headshot
Moses Feagin, chief financial officer of Alabama Power, which filed to cut 2027 rates by $160 million and credited data-center revenue. "We negotiated these agreements so that growth pays for growth," he said.

Alabama Power filed with the Alabama Public Service Commission on Friday, November 20, 2026, to cut customer rates by $160 million in 2027, beginning with January bills. 1 The Southern Company+0.11% — Southern Company, up 0.11 percent today utility serves 1.6 million customers in the state. 1

The cut runs through Rate Stabilization and Equalization (RSE), Alabama's annual formula check on the utility's rates in place of full rate cases, and the company says the lower level holds through 2028. 1 A home using 1,000 kilowatt-hours a month saves more than $50 a year. 1 The company credits the reduction primarily to 2027 revenue it expects from large-load data centers, which a state law passed this year requires to pay the grid costs their demand creates. 12 "We negotiated these agreements so that growth pays for growth," chief financial officer Moses Feagin said. 1

The signed load is meant to cover its own costs

Southern's third-quarter results give the claim scale. Data-center power use across its utilities rose 59 percent year over year, and signed large-load contracts reached 21 gigawatts, with Alabama Power adding about 2 gigawatts in the quarter. 3 Those contracts' minimum bills cover at least 100 percent of the system costs they create, chief financial officer David Poroch told analysts. 3 The same call sketched a five-year capital plan that could approach $100 billion 3.

21 GW of large-load contracts are signed; the 75 GW pipeline is still talk

The rate cut rides on 21 GW of signed contracts

  • Estimate
0 GW20 GW40 GW60 GW80 GWSigned contracts21 GWLate-stage talks7 GWProspective pipeline75 GW
Data
Value
Signed contracts21 GW
Late-stage talks (estimate)7 GW
Prospective pipeline (estimate)75 GW
Gigawatts of large-load, mostly data-center, electricity contracts at Southern Company as of its third-quarter 2026 earnings call on November 5, 2026. Late-stage and pipeline figures are company projections.3

Southern's capex has outrun operating cash in three of the last four quarters

  • Capex
  • Operating cash flow
$1B$2B$3B$4B$5BQ1 '24Q3 '24Q1 '25Q3 '25Q1 '26Q3 '26
Data
CapexOperating cash flow
Q4 '23$2.76B$1.81B
Q1 '24$2.14B$1.31B
Q2 '24$1.98B$2.69B
Q3 '24$2.21B$3.62B
Q4 '24$2.52B$2.17B
Q1 '25$2.6B$1.25B
Q2 '25$2.64B$2.18B
Q3 '25$3.1B$3.77B
Q4 '25$4.05B$2.6B
Q1 '26$3.2B$1.23B
Q2 '26$3.13B$3.05B
Q3 '26$3.26B$3.6B
Southern Company capital spending and cash from operations, US dollars in billions, by quarter, from the company's quarterly SEC filings. Capex is capital spending shown as a positive figure.9

Everywhere else, bills climb

Nationally, household electricity prices rose 4.4 percent in the 12 months through September 2026, the Bureau of Labor Statistics reported. 4 Electric and gas utilities sought more than $23 billion of rate increases in the first nine months of 2026, an October PowerLines tally cited in the announcement. 1

A day earlier, Entergy−1.70% — Entergy, down 1.70 percent today Louisiana reported to state regulators that its Waterford 5 gas plant for Meta's−4.82% — Meta, down 4.82 percent today $50 billion Hyperion data center is now forecast at $1.755 billion, 63 percent over estimate, with ratepayers funding at least $470 million of the project's wires. 5 In Louisiana the data center shows up as a $676 million overrun; in Alabama it shows up as a $50 rate cut. 5

Critics credit tax breaks, not data centers

Energy Alabama executive director Daniel Tait says the cut mostly reflects federal income-tax and nuclear tax credits, not data centers. 6 Savings run $3.30 to $8.83 a month, and September bills averaged $232 at Alabama Power against $203 at Mississippi Power and $187 at Georgia Power, Southern companies both. 6 The announcement names no data-center counterparties and no contract terms, and it banks on revenue still only expected. 1

Alabama Power homes pay the highest bills in Southern's family

The $50-a-year cut is about $4 a month on a $232 bill

$0/mo$50/mo$100/mo$150/mo$200/mo$250/moAlabama Power$232/moMississippi Power$203/moGeorgia Power$187/mo
Data
Value
Alabama Power$232/mo
Mississippi Power$203/mo
Georgia Power$187/mo
Average residential electric bill in September 2026, US dollars per month, per Electricity Price Hub data cited by WPMI NBC 15 on November 20, 2026. All three utilities are owned by Southern Company.6

A bigger commission and the 2027 review will test the claim

The calendar settles the argument. The commission grows from three seats to seven in January, and commissioner-elect Jim Zeigler already calls this "a small reduction." 67 Governor-elect Tommy Tuberville has drafted legislation to strip state energy taxes from residential bills for the session that opens February 3, 2027. 8 Entergy files in December for seven more Meta plants under Louisiana's fast-track Lightning Directive. 5 The tell is the 2027 RSE review, when expected data-center revenue becomes reported revenue. 1

Get Power by email, free

How AI's hunger for electricity moves utilities, power plants and the grid. In our daily email, every weekday.

Loading SO

Reader comments

0 comments

    Power

    Iberdrola says it fixes data-center power prices for 20 years in Spain, where 88% of grid requests fail

    Spain let in 12% of grid-access requests in 2025, and Iberdrola's Spain chief says the data-center money has already applied to plug in. The 20-year fixed price he described turns AI power demand into contracted cash for Iberdrola shareholders and locks the biggest cost line in a data center's budget.

    Power

    Illinois cuts WEC's Peoples Gas rate increase 72% to $40 million as 15 banks market up to $4 billion of stock

    The order is the second regulator trim of a WEC Energy utility in two weeks. It lands while 15 banks market up to $4 billion of WEC stock for a $47.5 billion data-center build whose biggest customers pay on terms no rate case can touch.

    Power

    FirstEnergy lifts capital plan to $38 billion after West Virginia approves gas plant

    The approval came with a surcharge that bills West Virginia ratepayers while the plant is built, and FirstEnergy answered by lifting its five-year plan to $38 billion, its growth target to 7% to 9%, and its equity ask to $2.8 billion. No large-load customer is named in the filing.

    Power

    Entergy's gas plant for Meta hits $1.755 billion, 63% over estimate

    A redacted Louisiana filing puts the first hard number on construction inflation in power built for a single AI customer, weeks before regulators vote on seven more Entergy plants under a fast-track that waives lowest-cost rules. December decides whether the bill lands on Meta, on Louisiana ratepayers, or on the growth story behind Entergy's premium multiple.

    Power

    Meta walks back its 2030 net-zero deadline after emissions rose 45% on AI power demand

    Meta is the first of the giant cloud-and-AI data-center operators, the hyperscalers, to reopen a climate deadline, blaming AI power demand that grids cannot feed. The gas plants replacing the pledge face a Louisiana vote in December, and the bill lands on Meta's capex first, then on Entergy ratepayers if the AI tenant walks.

    Power

    Poland moves to extend its price guarantee to 14 GE Vernova reactors as GEV sits 36% below its June high

    Deputy energy minister Wojciech Wrochna says Warsaw is ready to open talks on extending the contract for difference behind its only financed nuclear plant to small modular reactors, the instrument Orlen Synthos Green Energy has sought since June for 14 GE Vernova BWRX-300 units. For GEV holders it sketches a reactor pipeline that does not rest on AI data centers.

    Subscribe to TheInference for free