Applied Digital signed a $5.4 billion lease, then delivered 25 megawatts of it
Two days after a lease took contracted revenue past $41 billion, Applied Digital handed over 25 MW of a 200 MW deal, with interest already outrunning rent and a 300 MW year-end goal one hall from failure.
Vincent Jiangtwo-minute readDrafted with AI from the documents listed under Sources, then edited and fact-checked by Vincent Jiang. How we work

$41 billion of paper, 25 megawatts of steel
Applied Digital's+4.40% — Applied Digital, up 4.40 percent today numbers now argue both sides of its own stock. On November 23 the Dallas-based AI data center developer signed an 18-year, 150 MW lease with a tier-one investment-grade hyperscaler, worth about $5.4 billion in base-term revenue and $12.7 billion if renewals run, lifting contracted base-term revenue above $41 billion 2. On November 25 it announced its first ready-for-service hall at Polaris Forge 2 in Harwood, North Dakota: 25 megawatts, one-third of the first 75 MW phase, and 12.5% of the 200 MW lease the building sits under 14. Signed paper: $41 billion 14. Delivered steel: 25 MW 14.
Applied Digital's fixed claims ran 2.6 times its base rent in the August quarter
- Estimate
Data
| Value | |
|---|---|
| Base rent | $65.8M |
| Interest expense | $77.4M |
| Fixed claims incl. preferred (2.6x, implied) (estimate) | ~$171M (implied) |
A goal the release stopped quoting
The release did not repeat the target the company set on October 7: 300 MW of delivered critical IT load across North Dakota by December 31 1. Harwood's hall lifts the state total to 275 MW 1. One more 25 MW hall inside 37 days decides whether that goal is met, and the release names no date for the next two halls 1.
Lenders and Macquarie get paid before shareholders
The fixed claims sit ahead of equity. In the August quarter, base rent was $65.8 million 3, against interest expense of $77.4 million 3 on $6.4 billion of debt; with Macquarie Asset Management's preferred dividend, fixed claims ran 2.6 times rent 3. Revenue still leans on one-time tenant fit-out fees, $152.4 million of $258.7 million in fiscal Q4, which convert to recurring rent only as halls reach service 1. Debt rose from $0.8 billion to $6.5 billion in eight quarters of filings 5.
Applied Digital's debt rose $5.7 billion over eight quarters, almost matching $5.5 billion of capital spending
- Capital spending
- Total debt
Data
| Capital spending | Total debt | |
|---|---|---|
| Q4 '24 | $0.17B | $0.8B |
| Q1 '25 | $0.26B | $0.99B |
| Q2 '25 | $0.17B | $0.91B |
| Q3 '25 | $0.25B | $0.7B |
| Q4 '25 | $0.55B | $2.61B |
| Q1 '26 | $0.78B | $2.83B |
| Q2 '26 | $1.29B | $5.1B |
| Q3 '26 | $2.08B | $6.48B |
The bulls are trimming into the good news
Lucid Capital cut its target to $40 from $83 on November 23, still 227% above the $12.22 close; Roth MKM cut to $28, Morgan Stanley+0.40% — Morgan Stanley, up 0.40 percent today to $25 3. And the tenant is the pressure point: CoreWeave+1.77% — CoreWeave, up 1.77 percent today, whose leases are about a quarter of the backlog, carries a 1,314 basis point credit default spread pricing a 68% five-year default probability 6. Contracts show demand; rent that covers the interest bill shows delivery. If a second Harwood hall lands by December 31, the conversion story holds 6. If it does not, the market has already priced the answer at $12.22 6.
Sources
- 1Tech Times, Applied Digital Polaris Forge 2 Data Center Hall Ready for Service; North Dakota 25 MW Short of Goal, 25 November 2026
- 2Applied Digital press release, Applied Digital Secures New 150 MW, 18-Year Lease with Tier-One Investment-Grade Hyperscaler, 23 November 2026
- 3Yahoo Finance/TIKR, Lucid Capital Cut Its Applied Digital Target to $40 From $83. It Still Sees 227% Upside, 26 November 2026
- 4Data Center Dynamics, Applied Digital brings online 25MW data hall at Polaris Forge 2 data center in North Dakota, 25 November 2026
- 5Applied Digital quarterly figures from SEC filings, via The Inference company_series, retrieved 26 November 2026
- 6The Economic Times, AI credit risk mounts as Oracle and CoreWeave hit record CDS spreads, 25 November 2026
- 7Applied Digital, quarterly figures from its SEC filings, retrieved 26 November 2026